Hartford Casualty Insurance v. City of Marathon

117 F. Supp. 3d 1374, 2015 U.S. Dist. LEXIS 100439, 2015 WL 4633683
CourtDistrict Court, S.D. Florida
DecidedJuly 31, 2015
DocketCASE NO. 10-10077-CIV-KING
StatusPublished

This text of 117 F. Supp. 3d 1374 (Hartford Casualty Insurance v. City of Marathon) is published on Counsel Stack Legal Research, covering District Court, S.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartford Casualty Insurance v. City of Marathon, 117 F. Supp. 3d 1374, 2015 U.S. Dist. LEXIS 100439, 2015 WL 4633683 (S.D. Fla. 2015).

Opinion

JUDGMENT

JAMES LAWRENCE KING, UNITED STATES DISTRICT JUDGE, SOUTHERN DISTRICT OF FLORIDA

THIS MATTER comes before the Court upon completion of the bench trial, held from June 16-18, 2016 in Key West, Florida.

FINDINGS OF FACT

I. Background

In 2000, Congress appropriated $100 million for the construction of wastewa-ter treatment facilities to improve water quality in the Florida Keys National Marine Sanctuary. Pursuant to this congressional appropriation, Marathon, a municipality in the Florida Keys, initiated a series of projects to construct wastewater treatment facilities within several geographical services areas of the city.

Hartford Cas. Ins. Co. v. Intrastate Constr. Corp., 601 Fed.Appx. 929, 930-81 (11th Cir.2012). In 2007, Marathon planned and initiated the construction of a series of wastewater treatment facility projects at various geographic locations throughout Marathon; the seven geographic service areas are labeled “Area 1” through “Area 7.” In May of 2009, Marathon entered into a contract with Intrastate Construction Corp. (“Intrastate”), in which Intrastate agreed to construct a wastewater treatment plant in Area 3 in exchange for $2,061,000 (the “Area 3 project”). Id. at 931.

The Area 3 contract provides, inter alia: Intrastate must secure payment and performance bonds in an amount equal to 100% of the contract price; and Marathon may order additions, deletions, or amendments to the contracted work, upon receipt of which Intrastate must secure an adjustment of its performance bond to 100% of the amended contract price. See id. To satisfy its initial bonding obligations, Intrastate turned to Hartford Casualty Insurance Company (“Hartford”). The contract also provides, if Marathon terminates Intrastate for cause, Hartford is responsible for taking over and performing the contract for Area 3. Id.

On June 3, 2009, Hartford issued performance and payment bonds in the amount of $2,061,000.00, through which Hartford bound itself as surety for Intrastate’s performance of the Area 3 project contract (and to pay all losses, damages, expenses, costs, and attorney’s fees incurred by Marathon as a result of any default by Intrastate) and for payment to all claimants supplying Intrastate with labor, material, or supplies used directly or indirectly in the Area 3 project. See id. at 932. Marathon subsequently issued its formal Notice to Proceed to Intrastate, which specified that the time to complete the project commenced on August 5, 2009.

The deadline for Intrastate’s substantial completion of the Area 3 project was June 1, 2010. However,

[b]y April 2010, approximately eight months after starting construction on the Area 3 [project], Intrastate was incurring losses on the project, and Intrastate’s subcontractors and suppliers began filing “Notices of Nonpayment” with Hartford and Marathon. On April 14, 2010, Intrastate contacted Hartford to inform Hartford of Intrastate’s insolvency and the need for financial assistance to complete its various bonded projects, including the Area 3 Project.

[1377]*1377Id. at 933. Thereafter, “Hartford directly-informed Intrastate and Intrastate’s bonding agent that Hartford would no longer be issuing new bonds or expanding bond coverage on existing bonded projects.” Id. at n. 3.

Nonetheless, on April 27, 2010, Marathon and Intrastate agreed to a change order (the “Area 7 Change Order”), under which Intrastate obligated itself to construct an additional wastewater treatment facility in Area 7 in exchange for $2,984,487 and to secure, “from Hartford or some other bonding company[,]” additional bond coverage in the amount of $2,984,487. Id. at 938-39. The Area 7 Change Order increased the original contract amount from $2,061,000 to $5,046,487. On June 30, 2010, after learning of the Area 7 Change Order, Hartford sent a letter to Intrastate stating that the Area 7 project was not covered by the previously-issued performance and payment bonds, and that Hartford had not agreed to provide additional bonding for the Area 7 project. “[M]ore than a month passed between Hartford’s June 30 disavowal^ and] ... in the interim, Intrastate still provided no bond for 100% coverage.” Id. at 939.

Soon after, on August 6, 2010, before Intrastate had áchieved substantial completion on the Area 3 project, Marathon sent Intrastate a Notice of Default and Termination letter, which threatened to terminate Intrastate for cause — based upon Intrastate’s failure to secure additional bond coverage for the expanded scope of work — unless Hartford retracted its June 30 letter disavowing coverage for Area 7 within seven days. See id. at 934. Intrastate performed no more work after receiving the Notice of Default and Termination. Id. Rather than retracting its June 30 letter, Hartford initiated the instant declaratory judgment action on August 9, 2010, asking the Court to determine and adjudicate the legal rights between Hartford, Intrastate, and Marathon with respect to Hartford’s liability for Area 7 under the performance bond. And, three days later, “Hartford wrote to Intrastate reaffirming its June 30 letter and stating that it would not issue a bond for Area 7.” Id. at 935.

“Between early September 2010 and early November 2010, Hartford, Intrastate, and Marathon unsuccessfully attempted to negotiate a global settlement.” DE 208, at ¶ 19. On October 18, 2010, Marathon counterclaimed against Hartford for breach of contract relating to Hartford’s failure to fulfill its obligations under the performance bond with respect to Area 3. See DE 19. And, “[b]y November 4, 2010, global settlement negotiations had failed.” DE 208,-at ¶ 23. On November 5, 2010, Hartford informed Marathon that it would be willing to take over the completion of the Area 3 project, and presented Marathon with a takeover agreement outlining the terms of the takeover, Id. at ¶ 23. However, Marathon found the terms of the takeover agreement unacceptable, and requested that Hartford simply perform the original bonded contract. Hartford, 501 Fed.Appx. at 935-35. Hartford declined to do so. Id.

In December of 2010, Lanzo Construction Company (“Lanzo”) submitted an offer to step in and complete the Area 3 project within 120 days in exchange for $1,442,782. DE 208, at ¶ 29. On January 5, 2011, Marathon accepted a revised proposal from Lanzo to compete the Area 3 project, in which Lanzo offered to complete the project within 150 days for a lump sum contract price of $1,362,782 (the “completion contract”). While Lanzo had initially contracted to begin work “no later than January 17, 2011,”1 due to complications in securing bonding for the project, [1378]*1378Lanzo did not begin working on the Area 3 project until March 9, 2011, and Lanzo’s substantial completion deadline was extended to August 7, 2011. Id. at ¶¶ 31-33. During the course of Lanzo’s work on the Area 3 project, Marathon granted it forty-four days of extensions of the substantial completion deadline due to change-order work for work (in the amount of $94, 420.58) that was outside the . scope of Intrastate’s original contract. Id. at 34. Lanzo achieved substantial completion of the project on September 15, 2011. Id. at ¶ 35.

II. Marathon’s Damages

A. Completion Costs

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Temple Beth Sholom v. Thyne Const. Corp.
399 So. 2d 525 (District Court of Appeal of Florida, 1981)
Centex-Rooney Const. Co., Inc. v. Martin County
706 So. 2d 20 (District Court of Appeal of Florida, 1997)
RK Cooper Builders, Inc. v. FREE-LOCK CEILINGS, INC.
219 So. 2d 87 (District Court of Appeal of Florida, 1969)
Gesco, Inc. v. Edward L. Nezelek, Inc.
414 So. 2d 535 (District Court of Appeal of Florida, 1982)
Lisa Y.S. West v. Deputy Terry Davis
601 F. App'x 929 (Eleventh Circuit, 2015)
Kritikos v. Andersen
125 So. 3d 885 (District Court of Appeal of Florida, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
117 F. Supp. 3d 1374, 2015 U.S. Dist. LEXIS 100439, 2015 WL 4633683, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartford-casualty-insurance-v-city-of-marathon-flsd-2015.