Gesco, Inc. v. Edward L. Nezelek, Inc.

414 So. 2d 535
CourtDistrict Court of Appeal of Florida
DecidedApril 14, 1982
Docket80-1178, 80-2008
StatusPublished
Cited by12 cases

This text of 414 So. 2d 535 (Gesco, Inc. v. Edward L. Nezelek, Inc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gesco, Inc. v. Edward L. Nezelek, Inc., 414 So. 2d 535 (Fla. Ct. App. 1982).

Opinion

414 So.2d 535 (1982)

GESCO, INC., the Chase Manhattan Bank, N.A., a National Banking Association and Seaboard Surety Company, a New York Corporation Authorized to Do Business in the State of Florida, Appellants,
v.
EDWARD L. NEZELEK, INC., and the Travelers Indemnity Company, Appellees.
EDWARD L. NEZELEK, INC. and the Travelers Indemnity Company, Appellants,
v.
GESCO, INC., the Chase Manhattan Bank, N.A., a National Banking Association, and Seaboard Surety Company, a New York Corporation Authorized to Do Business in the State of Florida, Appellees.

Nos. 80-1178, 80-2008.

District Court of Appeal of Florida, Fourth District.

April 14, 1982.
Rehearings Denied June 16, 1982.

*537 Karl W. Adler of Adler, Tolar & Adler, Fort Lauderdale, for Gesco, Inc.

Robert H. Haggerty, New York City, for Chase Manhattan Bank and Seaboard Sur. Co.

Wayne A. Cypen of Cypen & Cypen, Miami Beach, for Nezelek and Travelers.

PER CURIAM.

This is a consolidated appeal from both a final judgment and a post judgment order in an action on a construction contract and a mechanic's lien. Gesco, Inc. is the owner-developer of a condominium around which this controversy centers. Chase Manhattan Bank is the construction lender and the principal on a transfer bond and Seaboard Surety Company is the surety on the transfer bond. These parties appeal from a final judgment rendered in favor of Edward L. Nezelek, Inc., the project's contractor. Nezelek appeals from a stay order prohibiting execution upon post judgment orders granting it attorneys fees and costs.

Gesco filed suit against Nezelek alleging breach of a condominium construction contract and sought damages for alleged substitution of inferior materials, defective construction and delay in completion. Nezelek denied these charges and asserted several affirmative defenses, among which was a claim that Gesco was solely responsible for the construction delays. Nezelek also counterclaimed to foreclose on its $1,117,614.92 mechanics lien which represented the alleged balance due under the contract. Nezelek joined Chase Manhattan Bank and Seaboard Surety Company in this action because they had posted the bond which transferred the lien. A non-jury trial followed.

The construction contract guaranteed that $6,500,000 would be advanced in monthly installments equal to 90% of the value of the work completed at the end of each requisition period, less previous payments, with the 10% retainage due thirty days after substantial completion of all work and compliance with various other requirements of the agreement. Under the terms of the contract "time was of the essence." All work was to be substantially completed within fourteen months of the project's commencement. It was further provided that this period would be extended only for delays attributable to Gesco, its architect or unavoidable casualties. However, in order that these delays inure to the contractor's benefit, the contract required Nezelek to request an extension, in writing, within fifteen days of the delay. Otherwise, the claim was deemed waived and the completion date remained unaltered.

The condominium was not completed on schedule. A ninety day temporary certificate of occupancy, for the first ten floors of the building, was issued six months late. The final certificate of occupancy was issued three months after that. All told, the condominium was completed nine months after the date called for by the contract. *538 (Construction began on or about June 20, 1973. The final certificate of occupancy was issued May 12, 1975.)

Gesco ceased making payments on the contract after January, 1975. On May 8, 1975, Nezelek filed a lien for the entire amount it claimed was due. The lawsuit upon which this appeal is based followed shortly thereafter.

The trial, even without a jury, lasted twelve days. On January 7, 1980, the court entered final judgment in favor of Nezelek. The court found that Nezelek's lien was valid; that Gesco suffered no damage as a result of the delay in the building's completion; that there was no basis in evidence to apportion the delay between the parties; that Gesco had authorized the use of the materials utilized by Nezelek; and that Nezelek was responsible for only minor construction defects. The court also found that Nezelek was entitled to costs and attorneys fees but reserved jurisdiction to determine the amount of such award at a later date.

Following the denial of their motion for rehearing, appellants timely filed their notice of appeal. Subsequently, the lower court awarded Nezelek attorneys fees of $180,000.00. The court also assessed costs of $4,038.94 against Gesco and Chase Manhattan Bank. Seaboard Surety Company was assessed costs of $100.00. Upon motion of appellants, the court granted a stay of execution upon these awards pending final resolution of all appeals. Nezelek appeals, contesting the propriety of the stay.

Gesco now contends that Nezelek's lien was premature and therefore should be considered fraudulent and invalid pursuant to Section 713.31, Florida Statutes. However, as this argument was not pursued below, it may not now be raised on appeal. See, Ronal Builders, Inc. v. Powell Brothers, Inc., 328 So.2d 869 (Fla. 4th DCA 1976), cert. denied, 339 So.2d 1171 (Fla. 1976). Likewise, Gesco's argument that Nezelek did not comply with the affidavit requirements of Section 713.06(3)(d)(1), Florida Statutes, was not raised below and is therefore deemed waived for purposes of appeal.

Gesco further contends that the court erred by not finding Nezelek responsible for any delays in the completion of the condominium project. It relies upon the contract provisions which required the contractor to request, in writing, extensions for delays caused by Gesco's actions. The record clearly establishes that no such requests were tendered. However, once again, this argument was not raised below. Nezelek affirmatively pled that all delays in construction were attributable to Gesco. If Gesco's position was that Nezelek waived the right to hold it responsible for delay, by virtue of Nezelek's failure to request extensions, then Gesco was obligated to so inform the trial court. Having failed to do so, by either pleading or argument, Gesco is precluded from raising this issue on appeal.

Although the record demonstrates, and the trial court found, that Nezelek was responsible for some of the delay, the court was nevertheless correct in concluding that Gesco's evidence did not establish a reasonable basis for apportioning responsibility for the total delay. See, United States, ex rel. Gray-Bar Electric Co. v. J.H. Copeland & Sons Construction, Inc., 568 F.2d 1159 (5th Cir.1978), cert. denied, 436 U.S. 957, 98 S.Ct. 3072, 57 L.Ed.2d 1123 (1978). See generally, 17A C.J.S. Contracts, § 502(4). The record clearly substantiates the trial court's finding that Gesco was responsible for considerable delay by such conduct as improperly locating a sewer easement, failing to timely supply lighting fixtures, and by allowing unit owners to effectuate changes in their apartments.

Gesco also challenges the lower court's refusal to allow its real estate appraiser to testify as to damages suffered by Gesco as a result of the delay in the condominium's completion. We have reviewed the proffered testimony, as well as the testimony of Gesco's accountant, and concur in the lower court's determination.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hartford Casualty Insurance v. City of Marathon
117 F. Supp. 3d 1374 (S.D. Florida, 2015)
RDP Royal Palm Hotel, L.P. v. Clark Construction Group, Inc.
168 F. App'x 348 (Eleventh Circuit, 2006)
Aetna Cas. and Sur. Co. v. Buck
594 So. 2d 280 (Supreme Court of Florida, 1992)
Sheldon Greene & Associates, Inc. v. Williams Island Associates
571 So. 2d 549 (District Court of Appeal of Florida, 1990)
Pappalardo Construction Co. v. Buck
568 So. 2d 507 (District Court of Appeal of Florida, 1990)
Southeast Bank, N.A. v. Grefs Construction & Roofing Corp.
564 So. 2d 199 (District Court of Appeal of Florida, 1990)
Acquisition Corp. of Am. v. Am. Cast Iron Pipe Co.
543 So. 2d 878 (District Court of Appeal of Florida, 1989)
Williams, Hatfield & Stoner, Inc. v. A & E Design, Inc.
538 So. 2d 505 (District Court of Appeal of Florida, 1989)
Old Gen. Ins. Co. v. Brownell & Assoc., Inc.
499 So. 2d 874 (District Court of Appeal of Florida, 1986)
Symons Corp. v. Tartan-Lavers Delray Beach
456 So. 2d 1254 (District Court of Appeal of Florida, 1984)
Stel-Den of America, Inc. v. Roof Structures, Inc.
438 So. 2d 882 (District Court of Appeal of Florida, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
414 So. 2d 535, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gesco-inc-v-edward-l-nezelek-inc-fladistctapp-1982.