Acquisition Corp. of Am. v. Am. Cast Iron Pipe Co.

543 So. 2d 878, 1989 WL 59172
CourtDistrict Court of Appeal of Florida
DecidedMay 31, 1989
Docket4-86-2517, 87-0501
StatusPublished
Cited by21 cases

This text of 543 So. 2d 878 (Acquisition Corp. of Am. v. Am. Cast Iron Pipe Co.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Acquisition Corp. of Am. v. Am. Cast Iron Pipe Co., 543 So. 2d 878, 1989 WL 59172 (Fla. Ct. App. 1989).

Opinion

543 So.2d 878 (1989)

ACQUISITION CORP. OF AMERICA and Kenneth V. Hemmerle, Sr., D/B/a Hemmerle Construction Company, Appellants,
v.
AMERICAN CAST IRON PIPE COMPANY, Coffman Leasing, Inc., and Earl Coffman, Appellees.

Nos. 4-86-2517, 87-0501.

District Court of Appeal of Florida, Fourth District.

May 31, 1989.

*879 Richard P. McCusker, Jr., and Lewis A. Berns, Fort Lauderdale, for appellants.

Dennis G. King of Dennis G. King, P.A., Miami, for appellee American Cast Iron Pipe Co.

Richard A. Rosenberg of Richard A. Rosenberg, P.A., Orange City, for appellees Coffman Leasing, Inc. and Earl Coffman.

ON REHEARING

WARNER, MARTHA C., Associate Judge.

We grant rehearing to correct factual errors in the issued opinion, and we substitute this opinion for the original. We have considered the other matters raised in the motion for rehearing and deny it in all other respects. For the most part, the motions are simply reargument of the issues presented.

The owner of a construction project and the general contractor appeal a final judgment in favor of the subcontractor and its supplier. We affirm in part and reverse in part.

The subcontractor, Coffman Leasing, Inc., entered into a contract with Hemmerle Construction, the general contractor, to construct water, sewer, and drainage facilities on a project in Boca Raton. The contract required the subcontractor to provide labor and materials in accordance with the plans and specifications prepared by the consulting engineers, and only as per the quantities of materials listed on the "summary of quantities" on the plans. Any additions to the quantities would "become an extra ... contract." Condition 15 of the contract provided that should the owner, architect, or general contractor desire additional work to be performed, the general contractor could direct such additional work. In no case would any claim for extra work be recognized unless authorized in writing by the general contractor. Coffman agreed to perform this contract for a lump sum price of $390,000.00.

Disputes arose as work was performed on the contract, and, shortly before job completion, Coffman walked off the job. One of Coffman's suppliers, American Cast Iron Pipe Company, filed a claim of lien against the project. When suit was filed to foreclose the claim of lien, the lien was transferred to a bond by Acquisition Corp., the owner of the property. Coffman, who was also sued by American Cast Iron, filed a cross-claim against Hemmerle Construction for breach of contract, alleging failure to pay for the contracted work plus substantial extras. Hemmerle filed its own cross-claim against Coffman for breach of contract, indemnity, and intentional misrepresentation. Acquisition also defended against American Cast Iron's assertion of a *880 fraudulent lien. The case proceeded to trial, primarily on the issues raised in the cross-claims. After trial, the court ruled in favor of Coffman and its materialman as to all counts.

Hemmerle asserts that the extras claimed by Coffman were not authorized in writing and thus not recoverable according to the contract provisions. The trial court construed the contract as authorizing "extras" without requiring written authorization because the contract contemplated that extras would be possible. We disagree with such a construction. Although the typewritten portion of the contract stated that additions would be an extra contract, the contract also specified that the subcontractor was to perform the contract in strict accordance with its conditions, which included a requirement that extra work be authorized in writing. A contract should be construed so as to give effect to all of the provisions of the contract, if possible. Bituminous Casualty Corp. v. Lewis Crane Service, Inc., 173 So.2d 715 (Fla. 3d DCA 1965). The trial court's construction in this case would not give effect to the requirement that all additions to the contract be in writing.

However, if the trial court's ruling may be sustained on other grounds, this court should do so. See, e.g., In re: Estate of Yohn, 238 So.2d 290 (Fla. 1970). Thus, the claims for additional compensation sought by Coffman must be separated to determine the basis for the additional charges and whether or not written authorization was required.

Coffman's claim may be broken down into four categories. First, Coffman claims additional compensation and extra expenses because the site was not properly prepared, requiring greater excavation than the plans called for. Second, it claims extras caused by a revision of the plans at the commencement of the job. Third, changes required by the Health Department in order to pass inspection were the third cause of claimed extra expenses. Finally, Coffman demands as a necessary extra to complete the job an increase in the tonnage of pipe fittings from what was called for in the summary of quantities.

As to the first category, where a default by the owner or its agent compels the contractor to perform additional work in order to conform to the contract plans, such work is not an alteration or addition to the contract which is required to be in writing as contemplated by the terms of the contract. City of Miami v. Nat Harrison Associates, Inc., 313 So.2d 99 (Fla. 3d DCA 1975), cert. denied, 330 So.2d 15 (Fla. 1976). In the instant case, the trial court found that the general contractor had improperly prepared the construction site. Therefore, the extra work caused by the improper site preparation is recoverable even absent written authorization.

Several increases in materials and labor were required by revisions in the plans and specifications. According to the evidence, these revisions were added to the plans in March of 1985, before construction commenced. The conditions of the contract require that no claim for extra work will be authorized unless in writing. There is no evidence of any such written authorization from the general contractor. Thus, the subcontractor cannot now make claim for the extras required by the revision. See Southern Roadbuilders, Inc. v. Lee County, 495 So.2d 189 (Fla. 2d DCA 1986), rev. denied, 504 So.2d 768 (Fla. 1987). Using the plans and specifications in evidence, simple mathematics indicate that the additional charges due to the revision amount to $8,864.10, which should be disallowed from the subcontractor's recovery.[1]

The contract also called for all water lines to be Class 50 Ductile Iron pipe or Johns Manville C-900 Blue Brute pipe. At trial, Coffman claimed an extra expense of $16,543.00 because he was required by the Health Department to use the more expensive cast iron pipe. Other extra charges were also necessitated by Health Department *881 requirements and inspections. Even without written authorization, the subcontractor is entitled to claim compensation for the pipe and other extras mandated by the Health Department. See Diana Stores Corp. v. M. & M. Electric Co., 108 So.2d 486 (Fla. 3d DCA 1959); William Zeigler & Son v. Chicago Northwestern Development Co., 71 Ill. App.3d 276, 27 Ill.Dec. 383, 389 N.E.2d 195 (1979). See also Annotation, Effect of Stipulation, In Private Building or Construction Contract, that Alterations or Extras Must be Ordered in Writing, 2 A.L.R.3d 620, at 643 (1965).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Don Facciobene, Inc. v. Hough Roofing, Inc.
225 So. 3d 323 (District Court of Appeal of Florida, 2017)
General Electric Capital Corp. v. Shattuck
132 So. 3d 908 (District Court of Appeal of Florida, 2014)
Patin v. Thoroughbred Power
Fifth Circuit, 2002
Patin v. Thoroughbred Power Boats Inc.
294 F.3d 640 (Fifth Circuit, 2002)
Ransom v. Fernandina Beach Chamber of Commerce
752 So. 2d 118 (District Court of Appeal of Florida, 2000)
Griefer v. DiPietro
708 So. 2d 666 (District Court of Appeal of Florida, 1998)
Rashdan v. Sheikh
706 So. 2d 357 (District Court of Appeal of Florida, 1998)
Department of Health and Rehab. v. Jb
675 So. 2d 241 (District Court of Appeal of Florida, 1996)
Resolution Trust Corp. v. Latham & Watkins
909 F. Supp. 923 (S.D. New York, 1995)
Becherer v. Merrill Lynch
43 F.3d 1054 (Sixth Circuit, 1995)
Metropolitan Dade County v. Bermudez
648 So. 2d 197 (District Court of Appeal of Florida, 1994)
Rupp v. Schon
608 So. 2d 934 (District Court of Appeal of Florida, 1992)
SOUTH END IMP. GROUP, INC. EX REL. BANK OF NY v. Mulliken
602 So. 2d 1327 (District Court of Appeal of Florida, 1992)
South End Improvement Group, Inc. ex rel. Bank of New York v. Mulliken
602 So. 2d 1327 (District Court of Appeal of Florida, 1992)
Pasquale v. Ohio Power Co.
413 S.E.2d 156 (West Virginia Supreme Court, 1991)
James A. Cummings, Inc. v. Young
589 So. 2d 950 (District Court of Appeal of Florida, 1991)
Trevino v. Chadderton
571 So. 2d 110 (District Court of Appeal of Florida, 1990)
Star Brite Distributing, Inc. v. Gavin
746 F. Supp. 633 (N.D. Mississippi, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
543 So. 2d 878, 1989 WL 59172, Counsel Stack Legal Research, https://law.counselstack.com/opinion/acquisition-corp-of-am-v-am-cast-iron-pipe-co-fladistctapp-1989.