Grant v. Lathan Construction Corp. (In Re Construction Contractors of Ocala, Inc.)

196 B.R. 188
CourtUnited States Bankruptcy Court, M.D. Florida
DecidedMay 6, 1996
DocketBankruptcy No. 94-1579-BKC-3P7. Adv. No. 95-123
StatusPublished
Cited by3 cases

This text of 196 B.R. 188 (Grant v. Lathan Construction Corp. (In Re Construction Contractors of Ocala, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grant v. Lathan Construction Corp. (In Re Construction Contractors of Ocala, Inc.), 196 B.R. 188 (Fla. 1996).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

GEORGE L. PROCTOR, Bankruptcy Judge.

This proceeding came before the Court on a five count complaint regarding a contract dispute. Upon the evidence presented at trial on December 12, 1995 and February 20, *191 1996, the Court enters the following findings of fact and conclusions of law:

1. Defendant Lathan Construction Corporation (Lathan), a general contractor, entered into a construction contract to build a Lowe’s store in Ocala, Florida (the project).

2. On December 27,1993, Lathan entered into a subcontract with the debtor, Construction Contractors of Ocala, Inc., to perform sitework on the project. The total value of the subcontract was $1,268,000. A change order dated April 20, 1994, revised the subcontract amount to $1,266,256. [Lathan Ex. 1; Plaintiff Ex. 1], The subcontract stated that time was of the essence. [Lathan Ex. 1 at ¶ 11].

3. The subcontract required that all modifications of the subcontract be in writing and signed by Lathan. The subcontract also provided that no changes to the work would be made except on the written order of the contractor, signed by the project manager. A handwritten addition to the contract stated that “any rock removal as stated in the specifications shall be extra to this contract.” [Lathan Ex. 1; Plaintiff Ex. 1],

4. On April 15,1994, debtor filed a voluntary petition for relief under Chapter 11 of the Bankruptcy Code and continued to operate as debtor in possession.

5. Pursuant to the subcontract, the debt- or submitted four draw requests to Lathan. Lathan made payments on the draws on February 17, 1994, March 23, 1994, May 5, 1994, and May 24, 1994. [Lathan Ex. 5, 11, and 12]. The payments made by Lathan to debtor totalled $645,396.33. [Plaintiff Brief at 5;. Lathan Ex. 5]. Corresponding to each draw request is a release of lien signed by or on behalf of the debtor. [Lathan Ex. 12].

6. Through a series of correspondence to the debtor between February 4, 1994, and May 9,1994, Lathan documented its dissatisfaction with the rate and quality of defendant’s work on the project. [Lathan Ex. 3]. By letter dated May 9, 1994, Lathan informed the debtor that debtor’s failure to comply with he terms of the subcontract constituted a material breach and that if the breach was not cured within twenty-four hours, Lathan would employ “the necessary people and equipment to complete [the] contract work_” [Lathan Ex. 3].

7. On May 11, 1994, Lathan terminated debtor’s subcontract. [Lathan Ex. 4], On the same date, Lathan entered into a new subcontract with Michael Oehlerking and Le-ven H. Ozeel d/b/a Castlerock Landfill to complete the project in the amount of $594,-230. [Lathan Ex. 6].

8. Lathan’s payments to Castlerock, including change order variations to the subcontract, totaled $753,716.87. [Lathan Ex. 7]. Lathan’s payments to Castlerock exclusive of the change orders totaled $594,230. [Lathan Ex. 7; Lathan Ex. 6; Plaintiff Brief at 5].

9. On November 2, 1994, debtor’s case was converted to one under Chapter 7 of the Bankruptcy Code and Plaintiff was appointed as Trustee.

10. On April 21, 1995, Plaintiff commenced this adversary proceeding by filing a five-count complaint against Lathan Construction, and Michael Oehlerking and Leven H. Ozeel d/b/a Castlerock Landfill. In Count I, Plaintiff claims that Lathan breached its subcontract with the debtor by improperly terminating the contract and by failing to pay all sums due under the contract. Plaintiff alleges that debtor suffered damages as result of Lathan’s breach and that those damages are property of debtor’s bankruptcy estate.

In Count II, Plaintiff alleges that the subcontract between Lathan and the debtor was property of the estate, and that pursuant to 11 U.S.C. § 549, Lathan’s termination of the subcontract and its “reletting” of the balance of the contract to Castlerock constituted an avoidable transfer of estate property.

In Count III, alleges that pursuant to an oral contract, debtor performed additional work valued at $72,458.54 which was outside the scope of the original subcontract. Plaintiff claims Lathan breached the oral contract by refusing to pay for the additional work and that the damages are property of the estate.

In Count IV, Plaintiff alleges that the debtor was a third-party beneficiary of an *192 oral agreement between Lathan and Castler-ock, under which Castleroek agreed to pay debtor’s outstanding creditors in conjunction with its subcontract with Lathan. Plaintiff claims that Lathan and Castleroek breached the agreement and debtor’s estate has been damaged by that breach.

In Count V, Plaintiff alleges that in consideration for Lathan’s and Castlerock’s agreement to pay the outstanding creditors of the debtor, debtor agreed to release his inchoate construction lien against the project. Debtor claims that it fully performed its obligation under the agreement and that it has been damaged by Lathan’s and Castlerock’s breach.

9. As answer to the complaint, Lathan asserted the following affirmative defenses:

1. Failure to state a claim for relief;
2. Prior breach;
3. Setoff;
4. Waiver/Lack of Written Change Order;
5. Statute of Frauds.

Lathan also filed a counterclaim against the debtor’s estate, alleging that it had been damaged by debtor’s breach of the subcontract and that the estate is liable for payment of those damages.

10. Defendants Oehlerking and Ozcel also answered and asserted two affirmative defenses. First, Oehlerking and Ozcel allege that they were not party to the subcontract with Lathan, but merely signed the agreement as representatives of Castleroek. Second, Oehlerking and Ozcel allege that the subcontract between Lathan and the debtor was never assumed by the debtor or the Plaintiff and thus is not an asset of the estate.

11. At trial, Lathan, Oehlerking, and Ozcel made ore terms motions to dismiss Counts IV and V of the complaint. The Court granted the motions and proceeded to trial on Counts I, II, and III.

CONCLUSIONS OF LAW

Count I

A. Lathan properly terminated debtor’s subcontract.

Plaintiff first alleges that Lathan breached the subcontract by improperly terminating it. Under Florida law, “[a] contract will be construed according to its own clear and unambiguous terms.” Cueto v. John Allmand Boats, Inc., 334 So.2d 30, 32 (Fla. 3rd D.C.A. 1976) cert. denied 341 So.2d 290 (Fla.1976). When words or terms used in a contract have known legal meaning, it is presumed that the parties intended the contract to be interpreted in accordance with that meaning. Wilcox v. Atkins, 213 So.2d 879, 881 (Fla.2d D.C.A. 1968).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Regions Bank v. Hyman
91 F. Supp. 3d 1234 (M.D. Florida, 2015)
Manuel v. Allen (In Re Allen)
217 B.R. 952 (M.D. Florida, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
196 B.R. 188, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grant-v-lathan-construction-corp-in-re-construction-contractors-of-flmb-1996.