Don Facciobene, Inc. v. Hough Roofing, Inc.

225 So. 3d 323, 2017 Fla. App. LEXIS 10487, 42 Fla. L. Weekly Fed. D 1627
CourtDistrict Court of Appeal of Florida
DecidedJuly 21, 2017
DocketCase 5D15-1527
StatusPublished
Cited by1 cases

This text of 225 So. 3d 323 (Don Facciobene, Inc. v. Hough Roofing, Inc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Don Facciobene, Inc. v. Hough Roofing, Inc., 225 So. 3d 323, 2017 Fla. App. LEXIS 10487, 42 Fla. L. Weekly Fed. D 1627 (Fla. Ct. App. 2017).

Opinion

BERGER, J.

Don Facciobene, Inc. (DFI), a licensed general contractor, and its subcontractor, Hough Roofing, Inc. (HRI), appeal the amended final judgment entered by the trial court on HRI’s breach. of contract claim and DFI’s counterclaim after a non-jury trial. DFÍ asserts, inter alia, that the trial court err,ed in finding that its subcontract with HRI did not .apply retroactively and that, consequently, HRI was barred from receiving any payment at all due to noncompliance with the conditions precedent to progress payments and final payment in section '8 of the subcontract. HRI filed a.cross-appeal seeking, inter alia, pay *325 ment for the full value of its subcontract. 1 We agree with DFI that the trial court erred in failing to apply the subcontract retroactively. However, we find no merit in DFI’s argument that HRI was barred from receiving payment for failing to comply with conditions precedent. To the contrary, we agree with HRI on its cross-appeal and conclude it was entitled to the full value of its subcontract, minus certain setoffs. Accordingly, we reverse the amended final judgment. '

In late 2010, DFI contracted with Digia-cinto Holdings, LLC, (Owner) to perform various renovations to a house in Melbourne, Florida, known locally as the Nannie Lee House or the Strawberry Mansion (Mansion), as part of Owner’s preparations to open a restaurant on the premises. The Mansion, erected in 1905, needed a new roof. As general contractors are not permitted to place a new roof on an existing structure, DFI subcontracted the roofing work to HRI, a licensed roofing subcontractor. HRI provided an estimate and proposed statement of work to DFI in mid-March 2011. DFI’s project manager, Jim Monarchy, signed. HRI’s proposal on April 5, 2011, as well as an additional expanded proposal on April 11, 2011. The proposals stated that payment was due on completion. HRI began work on the roof on April 15, 2011. However, the parties did not actually sign the subcontract until June 8, 2011, and, by that time, the project was nearly complete. The subcontract price was $21,051.

Under section 8 of the subcontract, HRI was due progress payments, minus a ten percent retainage, for work completed in a particular month on the twentieth day of the following month. Final payment- was not due until thirty days after the completion of the entire renovation. Monarchy testified that the final payment amounted to the payment of the accrued teii percent retainage. Section 8 of the subcontract also imposed several conditions precedent to progress payments and final payments. For progress payments, DFI had tó (1) receive payment from Owner for HRI’s work that was due for the progress payment and (2) HRI had to provide, upon request from DFI, a sworn statement listing the parties who furnished labor and materials to HRI , with their names and addresses and documentation showing that HRI paid them. The conditions precedent to final payment included the conditions precedent for progress payments and additional requirements that HRI’s work was at least ninety-eight percent complete and that HRI submit unspecified closeout documents to DFI for approval and provide a final lien waiver and release to DFI.

HRI had mostly finished its work by the end of May 2011, and on Juñe 8, 2011, it submitted its first “final” invoice for $22,370. 2 Due to disputes over some of HRI’s charges, 3 DFI never paid HRI anything for its work on the Mansion even though it received payment for HRI’s *326 work from Owner on July 15, 2011, final payment for the entire project from owner on December 21, 2011, and concluded the renovations on December 30, 2011. 4 As a result, a claim of lien was filed against the property, 5 and on December 6, 2011, HRI filed its complaint for breach of contract against DFI and Owner. On December 27, 2011, DFI notified HRI that Owner had discovered a leak in the roof. 6 Despite this, Owner refused to give HRI permission to come onto the premises and repair the leak until May 2012. Consequently, DFI undertook repairing the roof, without a roofing license, and filed a counterclaim seeking damages for the estimated cost of repairing the leak. DFI also answered HRI’s breach of contract claim by asserting, as an affirmative defense, noncompliance with unspecified conditions precedent.

The case proceeded to trial, at which both parties presented expert witness testimony concerning the leak. DFI’s expert, Luke Miorelli, 7 testified that while most of the roof was installed correctly, there were potential problems with the roof installation on the south and west dormers and estimated repairs would cost $7378.80. HRI’s expert, Joseph Horschel, 8 testified that only the portion of the roof with the active leak needed to be redone and estimated that the issue could be fixed by two laborers working about six hours each.

On April 7, 2015, the trial court issued its amended final judgment. 9 It found that both parties did not sign the subcontract until June 8, 2011, and that by that point, HRI’s performance was more than ninety percent complete. The trial court determined that “to retroactively apply the language to the work performed prior to the Contract being fully executed is not required since the total work called for by the Contract was substantially performed prior to the written Contract being signed.” The trial court ruled that DFI breached the implied covenant of good faith and fair dealing by cutting off communications with HRI and deciding not to pay HRI in late June 2011. For damages, the trial court awarded HRI the uncontested charges of $10,720 for the metal roofing panels, $4100 for the plywood sheathing, $2635 for the thirty-one pitch pockets, and $2333.50 for the flat roof and base sheet. After offsetting the $1440 HRI owed DFI for the crane rental and the ten percent retainage of $1978.85, the trial court ruled that DFI should have paid HRI $16,369.65 in July 2011. The trial court further found that DFI could not recover on the unlicensed repair work it performed on the roof and that its expert’s testimony was not credible on the cost to repair the leak. The trial court found that HRI’s expert’s testimony was credible on that point and awarded DFI only $180 on the counterclaim based on six hours of labor by two workers being paid $15 per *327 hour. It also awarded DFI an offset for the $750 cost of bonding the lien off the property resulting in a $15,439.65 award in favor of HRI plus postjudgment interest. The trial court further ruled that HRI was barred from recovering the balance of the contract price because it did not comply with the conditions precedent to final payment.

We find multiple errors in the amended final judgment that warrant reversal. First, the trial court’s decision not to apply the subcontract retroactively was error in light of the merger clause found in section 18 of the subcontract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hough Roofing, Inc. v. Don Facciobene, Inc.
225 So. 3d 322 (District Court of Appeal of Florida, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
225 So. 3d 323, 2017 Fla. App. LEXIS 10487, 42 Fla. L. Weekly Fed. D 1627, Counsel Stack Legal Research, https://law.counselstack.com/opinion/don-facciobene-inc-v-hough-roofing-inc-fladistctapp-2017.