Pasquale v. Ohio Power Co.

413 S.E.2d 156, 186 W. Va. 501, 1991 W. Va. LEXIS 255
CourtWest Virginia Supreme Court
DecidedDecember 19, 1991
Docket19940
StatusPublished
Cited by9 cases

This text of 413 S.E.2d 156 (Pasquale v. Ohio Power Co.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pasquale v. Ohio Power Co., 413 S.E.2d 156, 186 W. Va. 501, 1991 W. Va. LEXIS 255 (W. Va. 1991).

Opinion

MILLER, Chief Justice:

Ohio Power Company and Central Operating Company (the Power Companies) ap *503 peal a final order of the Circuit Court of Mason County, dated February 6, 1990, dismissing their third-party claims against Gallia Refrigeration, Inc., also known as Pasquale Electric Company, and their third-party complaint against The Travelers Insurance Company (Travelers) for a declaration of coverage. We find that the trial court did err in granting summary judgment, and, accordingly, the trial court’s final order is reversed.

I.

The Philip Sporn electric generation station (the Spom plant) is a coal-fired electric generating plant located in Mason County, West Virginia. The Spom plant, while operating as one integrated electric generating plant, has five generating units, referred to as Units 1 through 5. The units are separately owned by Ohio Power Company and Appalachian Power Company. The entire plant is operated by Central Operating Company under a contractual agreement with the owners.

Although the plant has a maintenance staff, certain maintenance work is performed by independent contractors. One of those contractors is Pasquale Electric, a company owned and operated by Louis Pasquale. Pasquale Electric had performed several maintenance projects at the Sporn plant, and each time the parties entered into a written service contract. These contracts typically incorporated certain general terms and conditions, including provisions that Pasquale Electric would indemnify and hold harmless the Power Companies for accidents occurring during the performance of maintenance work on plant premises and a requirement that Pasquale Electric would maintain liability insurance.

On June 26, 1987, the Power Companies and Pasquale Electric entered into a contract to do maintenance work on Unit No. 5. On and prior to August 19, 1987, Pasquale Electric’s employees were on the premises performing work under that contract. At the same time, Pasquale Electric was waiting to see if it had been awarded another service contract with the Power Companies for work on Unit No. 2, which was owned by Ohio Power Company. As in the June 26 contract, that contract, which was later dated August 25, 1987, provided that Pasquale Electric would indemnify the Power Companies for any liability arising as a result of the maintenance work.

On or about August 18, 1987, a short circuit occurred in a cable that was connected to a boiler feed pump in Unit No. 2. Because the boiler feed pump needed to be made operational as soon as possible, the Sporn plant management asked Pasquale Electric to pull some of its employees from Unit No. 5 to work on the cable at Unit No. 2. One of the employees who was removed to work on Unit No. 2 was Michael Pasquale, Louis Pasquale’s nephew. While working on Unit No. 2, Michael Pasquale erroneously cut an energized cable and was instantly electrocuted.

Michael Pasquale’s wife, Daphne Colleen Pasquale, as personal representative of his estate, instituted a wrongful death action against the Power Companies and Pasquale Electric. The Power Companies filed cross-claims against Pasquale Electric based on an alleged written contract. The Power Companies also filed a third-party complaint against Pasquale Electric’s insurance carrier, Travelers, seeking a declaration that the insurance policy issued to Pasquale Electric entitled the Power Companies to indemnification.

Thereafter, Travelers and Pasquale Electric filed cross-motions for summary judgment, alleging that Pasquale Electric did not assume liability for indemnification in its oral agreement of August 19, 1987, and that neither the June 26, 1987 contract nor the August 25, 1987 contract applied to the work done on August 19, 1987. The trial court agreed, and, in an order dated February 6, 1990, it dismissed the Power Companies’ cross-claims against Pasquale Electric and the third-party complaint against Travelers. The Power Companies appeal.

II.

The Power Companies’ position is that the work on the short-circuited cable should be covered under either the Unit 5 *504 contract, which was dated June 26,1987, or the Unit 2 contract, which was dated August 25, 1987. With regard to the latter contract, the Power Companies point out that as a part of the scheduled maintenance under the Unit 2 contract, the cable in the boiler feed pump that short circuited would have been replaced.

Travelers and Pasquale Electric counter that there were several critical facts that were not disputed and support the trial court granting summary judgment in their favor. First, it was the Power Companies’ admitted policy not to permit outside contractors to work unless they had a written contract. In each instance that Pasquale Electric was working on the Power Companies’ premises, it was doing so under a written contract executed before the work was begun.

Second, Travelers and Pasquale Electric state that the emergency work cannot be placed under the June 26, 1987 contract for work done on Unit 5 because there was no attempt to comply with the terms of that contract. Under paragraph 39 of the contract, there can be no amendments for extra work unless in writing and signed by the parties. 1 The parties never discussed or executed such written amendments before or after the death of Michael Pasquale.

Third, with regard to the August 25, 1987 contract covering the scheduled maintenance of Unit 2, Travelers and Pasquale Electric point out that this contract was not signed by Pasquale Electric until a week after the death of Michael Pasquale. Moreover, they point to the Power Companies’ established practice not to permit the contractor to start work on the premises until the contract is signed. Finally, they state that Pasquale Electric was not even notified that it had been awarded the work on Unit 2 until after Michael Pasquale’s death on August 19, 1987.

III.

There is no disagreement that the Power Companies did not issue any work order for the emergency work on the short-circuited cable to Pasquale Electric. Instead, Pasquale Electric billed the Power Companies on August 22, 1987, for the work done in repairing the cable. The threshold question is whether the emergency work can be said to fall under either contract; if not, then there is no express indemnity agreement.

When we turn to the June 26, 1987 contract covering work on Unit 5, as previously indicated, it contains a provision for modification by the mutual consent of the parties. The Power Companies contend that the provision in the June 26 contract requiring any modification to be in writing and signed by the parties could be waived by an express oral agreement. They cite Syllabus Point 2 of State ex rel. Coral Pools, Inc. v. Knapp, 147 W.Va. 704, 131 S.E.2d 81 (1963):

“A written contract may be altered or supplemented by a valid parol contract subsequently made.”

See also W.L. Thaxton Constr. Co. v. O.K. Constr. Co., Inc., 170 W.Va. 657, 295 S.E.2d 822 (1982); John W. Lodge Dist. Co. v. Texaco, Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.F. Allen Corporation v. Sanitary Board of the City of Charleston
785 S.E.2d 627 (West Virginia Supreme Court, 2016)
New Holland Credit Co., LLC. v. Madison Creek LLC.
191 F. Supp. 2d 695 (S.D. West Virginia, 2002)
Britner v. Medical Security Card, Inc.
489 S.E.2d 734 (West Virginia Supreme Court, 1997)
Burgess Pic-Pac, Inc. v. Fleming Companies, Inc.
437 S.E.2d 742 (West Virginia Supreme Court, 1993)
Sesco v. Norfolk & Western Railway Co.
427 S.E.2d 458 (West Virginia Supreme Court, 1993)
Ground Breakers, Inc. v. City of Buckhannon
422 S.E.2d 519 (West Virginia Supreme Court, 1992)
Pasquale v. Ohio Power Co.
418 S.E.2d 738 (West Virginia Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
413 S.E.2d 156, 186 W. Va. 501, 1991 W. Va. LEXIS 255, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pasquale-v-ohio-power-co-wva-1991.