McGaffick v. Leigland

303 P.2d 247, 130 Mont. 332, 1956 Mont. LEXIS 56
CourtMontana Supreme Court
DecidedNovember 1, 1956
Docket9341
StatusPublished
Cited by2 cases

This text of 303 P.2d 247 (McGaffick v. Leigland) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McGaffick v. Leigland, 303 P.2d 247, 130 Mont. 332, 1956 Mont. LEXIS 56 (Mo. 1956).

Opinion

THE HON. PHILIP C. DUNCAN, District Judge:

This is an appeal from a declaratory judgment entered in the district court determining the rights of the plaintiff, George McGaffick, and numerous others, under the terms of a written contract for remodeling plaintiff’s office building.

Two separate motions to dismiss the appeal have been interposed by various respondents. Such motions challenge the sufficiency of the service of the notice of appeal, the sufficiency of the undertaking on appeal and the legibility and sufficiency of the transcript on appeal filed in this court. However, in view of the disposition here made of the cause such motions are denied.

The case arises out of the remodeling of a building in Helena, Montana, known as the Steamboat Block, which was and is owned by the plaintiff, George McGaffick.

In 1950, after negotiations with plaintiff, the Mountain States Telephone and Telegraph Company agreed to lease the building from Mr. McGaffick on what appeared to be a profitable arrangement, provided he would remodel it in a manner suitable for the company’s use, but the work required for that purpose was extensive and reqMred financing to its full extent by third parties, Mr. McGaffick having no money of his *335 own. Hence, before tbe execution of tbe lease, it became necessary to ascertain the cost of the remodeling. Consequently, Mr. McGaffiek, through his engineering and architectural firm, Morrison-Maierle, of Helena, Montana, prepared a document entitled, “Instructions for Pre-bidding, Description of Items, and Bid Forms” and submitted them to several contractors informally, including appellants, and they were invited to submit bids for the work upon the forms contained. This appellants Leigland, among others, did, and the bids were opened February 14, 1951. This procedure was called a pre-bid and appellants’ bid of $188,385.05 was the low one and they thus acquired a preferential right but not a firm contract.

On April 26, 1951, a contract for the remodeling of the building was entered into between plaintiff McGaffiek, and appellants Leigland, arrangements having been made on that day through the Union Bank and Trust Company, of Helena, for financing by that bank and the Northwestern National Bank of Minneapolis, although the promissory notes and mortgage on the property to secure the financing were not executed by plaintiff and his wife until May 26, 1951, and the mortgage to the banks was not recorded until June 8, 1951.

On April 29, 1951, appellants did their first work on the project at Great Falls, actually starting at the site in Helena on May 1, 1951.

On March 1, 1952, the task was completed and acceptance was made by plaintiff, except as to minor details not material here.

During the course of the work, progress reports or estimates, six in all, were made and after submission to the financing banks, payments in the amounts of these reports, totaling $147,-955.63, were made to appellants. A number of subcontractors and materialmen were not paid by appellants and a question developed as to how much was still owing appellants.

On April 25, 1952, plaintiff began this suit for a declaratory judgment to determine the rights and obligations of himself, the appellants, and others in the property and under the contract, alleging, among other things, that appellants had *336 failed to submit proof they had paid all subcontractors, tbat he bad been unable to obtain from appellants a final statement for tbe work, tbat be bad insufficient knowledge to form a belief as to tbe amounts due, if any, to subcontractors and materialmen, some of whom bad filed liens on the property and foreclosure actions on the same; and tbat he tendered such amount as might be found due to appellants and the subcontractors and materialmen. In their reply pleadings appellants admitted that many of the subcontractors and materialmen were unpaid and alleged, among other things, that the total cost of the work was $292,864.87 upon which only said sum of $147,955.63 had been paid, leaving a balance owing appellants of $144,909.24, for which they had filed a mechanic’s lien.

Besides tbe plaintiff McGaffick, who is a .respondent here, and tbe defendants Leigland, who are appellants here, there were brought into tbe action either originally or afterwards the subcontractors and materialmen claiming liens, the surety company which furnished appellants’ bond involved in the work, tbe two banks and telephone company heretofore mentioned, Mrs. McGaffick, and tbe Equitable Life Assurance Society.

During tbe trial tbe Equitable Life Assurance Society was dismissed as having no interest and all of the subcontractors and materialmen were disposed of by stipulation which allowed all of their claims in the amounts asked for totaling $62,860.99. The ultimate consequence of this dismissal and stipulation was to leave to the trial court solely the determination of the rights and obligations of tbe plaintiff McGaffick, the appellants, and tbe two banks, tbe banks being in tbe case to determine whether or not the mechanic’s lien, if any, claimed by appellants was superior to that of the mortgage lien of the banks, and, if so, to what extent.

After tbe tidal and submission of proposed findings and conclusions, tbe trial court entered its findings and conclusions and judgment, the net result of which was that it was thereby concluded that the total obligation of plaintiff to appellants was the sum of $200,373.97 upon which there had been paid *337 $147,953.63 leaving a balance payable of $52,418.34, that appellants and their surety company were indebted to the subcontractors and materialmen in the sum of $62,860.99 leaving and indebtedness due plaintiff from appellants and its surety company of $10,442.65, and that appellants had no lien on the property and were precluded from asserting any priority of lien upon the property over the mortgage lien of the banks.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pasquale v. Ohio Power Co.
413 S.E.2d 156 (West Virginia Supreme Court, 1991)
Smith v. School District No. 18
139 P.2d 518 (Montana Supreme Court, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
303 P.2d 247, 130 Mont. 332, 1956 Mont. LEXIS 56, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcgaffick-v-leigland-mont-1956.