J.F. Allen Corporation v. Sanitary Board of the City of Charleston

785 S.E.2d 627, 237 W. Va. 77, 2016 WL 1397301, 2016 W. Va. LEXIS 204
CourtWest Virginia Supreme Court
DecidedApril 7, 2016
Docket15-0089
StatusPublished
Cited by4 cases

This text of 785 S.E.2d 627 (J.F. Allen Corporation v. Sanitary Board of the City of Charleston) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.F. Allen Corporation v. Sanitary Board of the City of Charleston, 785 S.E.2d 627, 237 W. Va. 77, 2016 WL 1397301, 2016 W. Va. LEXIS 204 (W. Va. 2016).

Opinion

LOUGHRY, Justice:

The petitioner, J.F. Allen Corporation (“J.F. Allen”), appeals a January 5, 2015, order of the Circuit Court of Kanawha County dismissing, with prejudice, its breach of contract claim against the respondent, the Sanitary Board of the City of Charleston, West Virginia (“CSB”), pursuant to Rule 12(b)(6) of the West Virginia Rules of Civil Procedure. In this appeal, J.F. Allen seeks reversal of the circuit court’s order, contending that it alleged sufficient facts in its amended complaint, that if considered as true, would entitle it to relief.

*79 Upon consideration of the briefs and arguments of the parties, the submitted record, and the pertinent authorities, we find that J.F. Allen has set forth a claim, upon which relief could be granted. Accordingly, for the reasons set forth below, the final order of the circuit court is reversed, and this case..is remanded for further proceedings consistent with this opinion.

I. Factual and Procedural Background

On December 13, 2011, CSB, a utility owner, and J.F. Allen, a utility contractor, entered into a written agreement for construction work described as “Kanawha Two-Mile Creek Sewer .Improvements—Sewer Replacements Sugar Creek Drive Sub-Area, Contract 10-8.” The project involved a series of improvements to the City of Charleston’s municipal sewer system. The contract work was to include eight-inch and ten-inch gravity sewer replacements, manhole installation, house service connections, and restoration of paved and non-paved areas. Burgess and Niple, Inc. (“B & N”) provided professional services to CSB and served as the engineer/architect on the project. The contract price was $5,160,621.75 but was “subject to additions and deductions by change orders and quantities actually performed.” The contract required substantial completion of the project by January 2, 2013, and final completion by February 1, 2013.

Construction under the contract began on January 9, 2012, but was not completed until August 15, 2013. It is undisputed that six change orders and quantity adjustments were made during the project that increased the contract price by the amount of $394,977.00 for a final adjusted contract price of $5,555,598.00. After final payment was made under the contract, J.F. Allen submitted a written request seeking additional compensation from CSB for extra, non-contractual work that it maintains was ■ required by CSB and for increased costs that resulted from numerous delays and disruptions encountered during the project. CSB refused the request.

.Having been denied additional compensation, J.F. Allen filed a complaint in the Circuit Court' of Kanawha County on June 30, 2014, asserting breach of contract and unjust enrichment claims against CSB. The complaint alleged, inter alia, that CSB: .failed to provide J.F. Allen with accurate and adequate plans, specifications, and documents related to the work to be performed; dictated and changed the manner and method of performance; and interrupted and interfered with J.F. Allen’s ability to perform its com tractual obligations. The complaint further asserted that as a direct result of CSB’s material breach of contract, J.F. Allen suffered substantial financial loss. In response, CSB filed a motion to dismiss pursuant to Rule 12(b)(6) of the West Virginia Rules of Civil Procedure,

A hearing was held before the circuit court on September 16, 2014. At that hearing, CSB argued that J.F. Allen’s breach, of contract claim was stated too broadly and that it was required to identify each event that allegedly resulted in additional costs and delays. CSB further argued the unjust enrichment claim was barred because there was an express contract. After listening to the parties’ arguments, the circuit court granted' CSB’s motion to dismiss with regard to the unjust enrichment claim but gave J.F. Allen thirty days to amend its breach of contract claim. 1

J.F. Adíen filed its amended complaint asserting a breach of contract claim against CSB 2 on November 13, 2014. 3 The amended *80 complaint alleged that the contract required CSB to provide construction plans that showed the location of other underground facilities and allowed for adjustment of the contract price to the extent conditions encountered in performing the work were different from those indicated on the plans. J.F. Allen further alleged that, during the course of the project, there were 122 incidents where other utility lines or structures were damaged because they were unmarked or mismarked on the construction plans. J.F. Allen asserted that these incidents caused it to incur additional costs for repairs, delay, and lost productivity. J.F. Allen claimed that these incidents were conscientiously documented by CSB’s onsite representative but CSB refused to provide additional compensation, thereby breaching the contract.

The amended complaint also alleged CSB breached the agreement by allowing other contractors to perform work that interfered with J.F. Allen’s work without giving prior notice as required by the contract and by not providing additional compensation for the resulting extra costs. J.F. Allen asserted that CSB waived the contract’s provision requiring written notice of claims for extra compensation in failing to comply with the notice provision with regard to the work by other contractors.

Additionally, the amended complaint alleged that CSB ordered J.F. Allen to delay final paving and to perform additional work, including temporary paving, for which there was no bid item in the contract. J.F. Allen asserted that it entered into a subsequent oral agreement with CSB in contravention of the change order provision in the contract that provided for additional compensation for this extra work. J.F. Allen also contended that CSB directed it to perform restoration work on homeowners’ properties along the project right-of-way to repair damages that were unrelated to J.F. Allen’s contract work. Finally, J.F. Allen alleged that it suffered a substantial financial loss as a direct, proximate and foreseeable result of CSB’s material breach of contract.

CSB responded to the amended complaint by filing another motion to dismiss pursuant to Rule 12(b)(6). A hearing was held on December 2, 2014. Subsequently, the circuit court entered the final order finding that “the risk of liability with respect to Underground Facilities was contemplated by the parties at the time of contracting and was allocated to J.F. Allen, not CSB” and “[J.F. Allen] ha[d] not made any claim of timely “written notice,’ nor ha[d] it pled any specific facts to show that it followed the protocol for possible changes to the Contract Documents due to differing or unanticipated conditions arising from Underground Facilities] not shown or indicated on Contract Documents.” Accordingly, the circuit court granted CSB’s motion to dismiss the breach of contract claim with prejudice. The final order was entered on January 5, 2015, and this appeal followed.

II. Standard of Review

It is well-established that “‘[a]ppel-late review of a circuit court’s order granting a motion to dismiss a complaint is de novo.’ Syllabus point 2, State ex rel. McGraw v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
785 S.E.2d 627, 237 W. Va. 77, 2016 WL 1397301, 2016 W. Va. LEXIS 204, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jf-allen-corporation-v-sanitary-board-of-the-city-of-charleston-wva-2016.