Wehr Constructors, Inc. v. Steel Fabricators, Inc.

769 S.W.2d 51, 9 U.C.C. Rep. Serv. 2d (West) 488, 1988 Ky. App. LEXIS 197, 1988 WL 142777
CourtCourt of Appeals of Kentucky
DecidedDecember 22, 1988
Docket87-CA-2590-MR, 87-CA-2708-MR
StatusPublished
Cited by10 cases

This text of 769 S.W.2d 51 (Wehr Constructors, Inc. v. Steel Fabricators, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wehr Constructors, Inc. v. Steel Fabricators, Inc., 769 S.W.2d 51, 9 U.C.C. Rep. Serv. 2d (West) 488, 1988 Ky. App. LEXIS 197, 1988 WL 142777 (Ky. Ct. App. 1988).

Opinion

HAYES, Judge:

This is a case involving a construction contract in which two separate but related appeals have been filed. Wehr Constructors, Inc. and Safeco Insurance Company of America (Wehr) appeal from a judgment entered October 19, 1987 in Warren Circuit *53 Court, pursuant to a jury verdict, awarding Steel Fabricators, Inc. (Steel Fab) damages for Wehr’s breach of contract. J & D Steel Company and Vulcraft, a division of Nucor Corporation, also appeal from the judgment insofar as it dismisses their claim against Wehr.

This action was commenced July 11, 1986 by J & D and Vulcraft, and arises out of the construction of the Warren County Justice Center in Bowling Green, Kentucky. Wehr was the general contractor under an agreement entered in November, 1985, with the Warren Public Judiciary Corporation (WPJC). Steel Fab was the subcontractor pursuant to a contract with Wehr. Steel Fab, in turn, contracted with J & D and Vulcraft, requiring them to supply certain steel products. By its agreement, Steel Fab agreed to furnish to Wehr all labor, material, tools and equipment necessary to furnish and install

All structural steel and mise, iron per Section 5A; All steel joists per Section 5B; All Steel deck per Section 5C; All stairs items to be supplied by Steel Fabricators, Inc., and erected by others: aluminum handrails not on stairs, loose lintels, angles and exterior wall louvers. All work complete per plans, specifications including 5% Kentucky Sales Tax. All shop drawings are required by December 16, 1985. Shop drawings must be hand carried to Architect for review and approval.
Erection must begin by February 1, 1986.
Erection must be complete by March 1, 1986.
Your contract must be completed by March 30, 1986, or Liquidated damages
of $150 per day will be assessed. Monthly estimates are due in this office by the 20th of each month.

In addition, the contract contained a provision prohibiting modifications or additions unless accepted by Wehr in writing, and another provision prohibiting extra work except upon Wehr’s written authority. Despite this provision, Steel Fab alleged, and the jury found, that at Wehr’s oral request Steel Fab performed additional work or “extras.” As a result, the jury awarded Steel Fab $22,263.30 as the reasonable value of those extra services. The jury also found that Steel Fab had failed to timely complete its portion of the project as required by the contract but that Wehr had sustained no damages as a result. Finally, the jury found that although the material supplied by J & D failed to conform to plans and specifications of the Justice Center, they awarded no damages to Steel Fab, finding that Steel Fab incurred no cost in remedying the defects.

Wehr raises three arguments on appeal. First it is maintained that the jury should have been instructed that they must find that the “extra” work was evidenced by a written agreement pursuant to the contract in order for Steel Fab to have an enforceable claim. Wehr cites a number of cases in support of its position. In Duo County Tel. Coop. Corp. v. Reese, Ky., 379 S.W.2d 483 (1964), the Court disallowed payment to a builder of an office building for “extras” not provided for in a written, agreement. The Court, however, specifically held that payment would be denied “unless the circumstances attending the doing of the work were such as to raise a clear implication that at the time the work was done Reese expected to be paid, and the co-op expected to pay, for the ‘extras’.” Smith v. Ferguson, Ky., 295 S.W.2d 792 (1956), also involved a contract requiring prior approval before additional work could be performed on the construction of a house. The Court held against the contractor, but only because no approval of any kind had been obtained.

The general rule with respect to a clause requiring written approval of “extra” work is that while it is valid and binding upon the parties, the provision may be excused where there has been a modification, waiver, or abrogation thereof, written or oral, or where the general contractor is estopped to rely upon it. Illinois Cent. R. Co. v. Manion, 113 Ky. 7, 67 S.W. 40 (1902). Universal Bldrs. v. Moon Motor Lodge, Inc., 430 Pa. 550, 244 A.2d 10 (1968). Escott & Son v. White, 73 Ky. (10 Bush) 169 (1873). Pittsburgh Filter Mfg. *54 Co. v. Smith, 176 Ky. 554, 196 S.W. 150 (1917). The parties, by their course of dealing, may also abrogate such clause requiring written approval. Willey v. Terry & Wright of Kentucky, Inc., Ky., 421 S.W. 2d 362 (1967). “Under such contracts the courts have held the owner liable for alterations or extras made without his written order, where he orally agreed to or acquiesced in them.” 421 S.W.2d at 363. See Also Annot. 2 ALR 3d 620 (1965). The amount of the recovery is limited to the reasonable value thereof. Jackson v. Davey Tree Expert Co. 134 Md. 230, 106 A. 571 (1919). Wehr was therefore not entitled to a jury instruction that the alteration was required to be in writing.

Without citing a single supporting authority, Wehr also attempts to insert the requirements of the Uniform Commercial Code, specifically KRS 355.2-209, which provides in pertinent part that “[a] signed agreement which excludes modification or rescission except by a signed writing cannot be otherwise modified or rescind-ed_” We cannot discern how the provisions of the code apply to this case. The Uniform Commercial Code applies to transactions in goods. KRS 355.2-102. “Goods” are defined as “all things (including specially manufactured goods) which are movable at the time of identification to the contract for sale other than the money in which the price is to be paid, investment securities (article 8) and things in action.” KRS 355.2-105. The contract, clearly, was a construction contract calling for not only the necessary materials and equipment but for the labor required in the construction of the Justice Center. Even if goods were involved, whether or not Article II of the Code applies is determined by analyzing whether the predominant factor and purpose of the contract is the rendition of service, with goods incidentally involved, or whether the contract is for the sale of goods with labor incidentally involved. Allied Industrial Service Corp. v. Kasle Iron & Metals, Inc., 62 Ohio App.2d 144, 405 N.E.2d 307 (1977). Goods incorporated into a real estate construction contract are not goods. Epstein v. Giannattasio, 25 Conn.Supp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alph C. Kaufman, Inc. v. Cornerstone Indus. Corp.
540 S.W.3d 803 (Court of Appeals of Kentucky, 2017)
Five Star Lodging, Inc. v. George Construction, LLC
344 S.W.3d 119 (Court of Appeals of Kentucky, 2010)
Witt v. Eastern Kentucky University
205 S.W.3d 263 (Court of Appeals of Kentucky, 2006)
Hines v. Elf Atochem North America, Inc.
813 F. Supp. 550 (W.D. Kentucky, 1993)
LK Comstock & Co., Inc. v. Becon Const. Co., Inc.
932 F. Supp. 906 (E.D. Kentucky, 1993)
Pasquale v. Ohio Power Co.
413 S.E.2d 156 (West Virginia Supreme Court, 1991)
W. E. Brown, Inc. v. Pederson Construction & Tile Co.
20 Va. Cir. 280 (Charlottesville County Circuit Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
769 S.W.2d 51, 9 U.C.C. Rep. Serv. 2d (West) 488, 1988 Ky. App. LEXIS 197, 1988 WL 142777, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wehr-constructors-inc-v-steel-fabricators-inc-kyctapp-1988.