Marley Cooling Tower Co. v. Caldwell Energy & Environmental, Inc.

280 F. Supp. 2d 651, 51 U.C.C. Rep. Serv. 2d (West) 376, 2003 U.S. Dist. LEXIS 15213, 2003 WL 22079491
CourtDistrict Court, W.D. Kentucky
DecidedAugust 30, 2003
DocketCIV.A.3:02CV-32-H
StatusPublished
Cited by6 cases

This text of 280 F. Supp. 2d 651 (Marley Cooling Tower Co. v. Caldwell Energy & Environmental, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marley Cooling Tower Co. v. Caldwell Energy & Environmental, Inc., 280 F. Supp. 2d 651, 51 U.C.C. Rep. Serv. 2d (West) 376, 2003 U.S. Dist. LEXIS 15213, 2003 WL 22079491 (W.D. Ky. 2003).

Opinion

MEMORANDUM OPINION

HEYBURN, Chief Judge.

Plaintiff Marley Cooling Tower Company (“Marley”) and Defendant Caldwell Energy & Environmental, Inc. (“Caldwell”) filed cross-motions for summary judgment. Both sides contend that the main issue is whether the Caldwell-Marley agreement entitles Caldwell to hold Marley hable for losses it sustained as a result of Marley’s late delivery. Having reviewed the contract and the type of damages Caldwell incurred, the Court concludes that the broad provision in the Caldwell-Marley agreement waiving Marley’s liability for “consequential damages” covers the late charges Duke/Fluor Daniel (“D/FD”) assessed against Caldwell. Additionally, the Court concludes that Marley did not waive its rights under the contract. The Court will therefore sustain Marley’s motion for summary judgment and deny Caldwell’s cross-motion for summary judgment.

I.

The facts in this case, although lengthy, are not significantly disputed. Caldwell designs, manufactures and installs industrial cooling systems for large turbine generating systems used in power plants. On June 7, 2000, Caldwell and D/FD entered into an agreement under which CaldweU *654 would provide D/FD a cooling system for an Aiken, South Carolina power plant. Caldwell guaranteed D/FD that they would receive a completed, operational cooling system to D/FD’s South Carolina job site by April 1, 2001.

This case centers on a subsequent agreement between Caldwell and Marley. That agreement stated that Marley “shall have all the material/equipment [for the South Carolina cooling system] delivered to the purchaser [Caldwell] to the ‘Ship To’ address on April 1, 2001. This is a tentative delivery date and is subject to change only by the [Caldwell] Project Manager.” Caldwell-Marley Contract, Attachment A at ¶ 5.1 (emphasis in original). The agreement further provided that “[n]o changes in ... delivery may be made without a written change order, signed by authorized representative” of Caldwell. Id. at ¶ 4. The necessity of the April 1, 2001, due date cannot be seriously disputed. 1

It soon became clear that Marley could not complete its deliveries on-time. Realizing a late delivery was inevitable, on January 9, 2001, Marley notified Caldwell that it would be unable to comply with its contractual obligations. Similarly, on February 28, 2001, at a teleconference among Pope, Hubbuch, and other representatives from both companies, Ron Tesón, Marley’s Project Manager, stated that a late delivery was likely and suggested an April 16, 2001, delivery date was more probable.

Unhappy with the prospect of a late delivery, Caldwell restated its position that any delivery date after April 1, 2001, was unacceptable. Furthermore, Caldwell stated that it would hold Marley responsible for “any costs that Caldwell incurs as a result of late delivery.” Letter from Mike Pope to Mike Hubbuch, March 7, 2001, at ¶ 1; ¶3. Tesón responded that Marley would “not be able to accelerate the delivery date of April 16.” Letter from Ron Tesón to Mike Pope, March 12, 2001. Te-són further explained that regardless of whether the late delivery date led to charges against Caldwell, Marley was not responsible for those charges under the Caldwell-Marley contract. As support for this claim, Tesón relied on paragraph 4 of the Caldwell-Marley agreement which stated “Neither The Marley Cooling Tower Company or the Purchaser shall be responsible or held liable for any special, indirect, consequential, liquidated and/or punitive damages.”

Marley did not complete required delivery by the April 1, 2001, due date. Indeed, it only began shipping cooling tower materials on March 19th and staggered additional shipments thereafter until the work was completed on May 30, 2001— nearly two months after Marley promised to complete the project. Throughout this period, Caldwell continued to remind Marley of its liability for any costs or backc-harges D/FD imposed because of the late delivery.

The D/FD-Caldwell agreement established liquidated damages of $5,000 per day for late delivery of components to the South Carolina job site. As a result of this series of events, on June 18, 2001, D/FD demanded liquidated damages from April 9, 2001 to May 6, 2001, under the D/FD-Caldwell contract. Consequently, D/FD assessed $135,000 in liquidated damages through a set-off or “backcharge” on its next invoice. Caldwell passed this backc-harge along to Marley in a July 3, 2001, letter, stating that it would set-off the *655 $135,000 against any future Marley invoices.

The total Caldwell-Marley contract price was $407,003. On May 7, 2001, Marley submitted its first invoice in the amount of $127,811.97. Caldwell paid $126,533.85, because the invoice allowed Caldwell to deduct one percent from the total if paid within 20 days. Marley now says that Caldwell failed to pay the amount it owed in full. However, Marley made no objection at the time. On June 25, 2001, Marley submitted a second invoice in the amount of $258,840.88. Because D/FD had now backcharged Caldwell for Marley’s late delivery, Caldwell passed along the $135,000 charge against Marley when it paid that invoice.

Whether Marley agreed to accept this $135,000 backcharge is a matter of dispute. Initially, when Tesón received Pope’s July 3 letter, he spoke with several persons at Marley about whether Marley should accept the backcharge. Marley vice-president Don Meltzer thought the company should pay and instructed Tesón to notify Caldwell that, if it could provide certain documentation concerning the backcharge, Marley would cover the costs. Tesón apparently objected to what he termed an “about-face,” but complied with Meltzer’s request. On July 20, 2001, Tesón sent Pope a letter asking Caldwell to supply portions of the Caldwell-D/FD contract and to provide a letter signed by a Caldwell officer stating that Caldwell had been assessed liquidated damages and that Caldwell had done everything possible to question the validity of the damages. The letter concluded, “We would like to work with you to resolve this issue. However, before we can agree to these backcharges, we must have the documents noted above.” The letter did not state that Marley objected to accepting the backcharge.

On August 1, 2001, Caldwell President John Kraft responded to this letter by providing Tesón with copies of the relevant documents he requested. Letter & Enclosures from Ron Tesón to Mike Pope, July 20, 2001. Kraft also sent a change order formalizing the decision to accept the $135,000 charge. The change order stated, “This Change Order No.l is issued to deduct the $135,000 in backcharges for late delivery.” Id. The change order had unsigned signature lines for Caldwell and Marley. It stated at the bottom, “This contract change order shall not be valid until signed and dated by Caldwell Energy & Environmental, Inc. Signature by the Subcontractor/Vendor [Marley] indicates agreement herewith including any changes to the contract amount and/or contract time.” Id. Marley neither signed nor returned the change order.

Throughout August, Caldwell and Marley continued to correspond regarding the $135,000 backcharge.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Powerscreen USA, LLC v. D & L Equipment, Inc.
661 F. Supp. 2d 705 (W.D. Kentucky, 2009)
Reid v. Seei
9 Am. Samoa 3d 50 (High Court of American Samoa, 2004)
Nortel Networks, Inc. v. Gold & Appel Transfer, S.A.
298 F. Supp. 2d 81 (District of Columbia, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
280 F. Supp. 2d 651, 51 U.C.C. Rep. Serv. 2d (West) 376, 2003 U.S. Dist. LEXIS 15213, 2003 WL 22079491, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marley-cooling-tower-co-v-caldwell-energy-environmental-inc-kywd-2003.