Mattingly Bridge Co. v. Holloway & Son Construction Co.

694 S.W.2d 702, 1985 Ky. LEXIS 238
CourtKentucky Supreme Court
DecidedJune 13, 1985
StatusPublished
Cited by23 cases

This text of 694 S.W.2d 702 (Mattingly Bridge Co. v. Holloway & Son Construction Co.) is published on Counsel Stack Legal Research, covering Kentucky Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mattingly Bridge Co. v. Holloway & Son Construction Co., 694 S.W.2d 702, 1985 Ky. LEXIS 238 (Ky. 1985).

Opinions

LEIBSON, Justice.

This appeal originates from a claim for liquidated damages by Holloway & Son Construction Co. (“Holloway”), as prime contractor, against Mattingly Bridge Co., Inc. (“Mattingly”), a subcontractor, charging that the subcontractor did not meet the completion date specified in its subcontract.

Holloway entered into a prime contract with the Kentucky Department of Highways (“Department”) for the construction of an 8-mile section of the Bowling Green-Somerset (Cumberland) Parkway. Holloway subcontracted to Mattingly the construction of all of the concrete structures required by the prime contract. The completion date specified in the subcontract between Mattingly and Holloway was November 15, 1971. The completion date specified in the prime contract for the entire project between Holloway and the Department was December 1, 1971.

Both the prime contract and the subcontract contained liquidated damage clauses, virtually identical. The liquidated damages clause of the subcontract read in pertinent part:

[703]*703“It is mutually agreed by and between the Contractor and the Subcontractor that time is of the essence of this subcontract, and that there will be sustained by the Contractor considerable monetary damages in the event of failure or delay in the completion of the work hereby contracted for by the Subcontractor, which damages will be difficult to definitely ascertain or establish, and the sum of Seven Hundred Fifty Dollars ($750.00) per day is hereby agreed upon by the parties hereto as the liquidated damages for each and every day after the fixed date of completion which the work hereby contracted for remains wholly or partially uncompleted. ... Said liquidated damages shall cease to accrue from and after the date when the work provided for in this contract has been completed and accepted by the owner [Department of Highways].”

After the completed project was accepted by the Department, which was sometime in 1972, the Department conducted a liquidated damage hearing against the prime contractor, Holloway, to determine liquidated damages that would be charged against Holloway for days delay in completion of the prime contract after December 1, 1971, the specified completion date. The Department decided, and Holloway accepted, that Holloway should be charged with 17⅜ days of liquidated damages at $750.00 per day, or $13,250.00, although the calendar date the project was finally inspected and formally accepted was not until July 1972.

Nevertheless, Holloway insists that it is entitled to recover from its subcontractor, Mattingly, liquidated damages at the rate of $750.00 per day from November 15, 1971, the completion date set forth in the subcontract, to July 19,1972, the date upon which the total project was formally accepted by the Department.

This ease has become a procedural nightmare. This is the third appeal. Much of the original litigation involved issues now resolved. We seek to confine this opinion to the one remaining question, whether Holloway is entitled to liquidated damages under the subcontract and, if so, what are the permissible limitations?

As we interpret the trial court’s Findings of Fact following the first trial of this case, findings which have never been reversed, as between Holloway and Mattingly, “the whole of any delay” in completing the prime contract was attributable to Holloway, the prime contractor. None of the delay in completing the prime contract was found attributable to the subcontractor, although the subcontractor also failed to complete on time. The trial court found: “[t]here is no support in the evidence for any recovery of liquidated damages against Mattingly.”

On appeal from that first judgment, reversed and remanded on other grounds, our opinion made certain observations regarding “recovery of liquidated damages for delay in completion of a contract by a primary contractor against the subcontractor” which have generated the present controversy. Holloway & Son Const. v. Mattingly Bridge, Ky., 581 S.W.2d 568, 572-73 (1979):

“First of all, if the contractor has been held liable under the terms and provisions of the primary contract for liquidated damages for delay in the completion of the whole project and the delay was occasioned by no fault of the subcontractor, then why in good conscience should the subcontractor be penalized for what is not his fault? On the other hand, if the delay was occasioned by the fault of the subcontractor, why should he not respond in damages to the degree that his fault bears to the whole of the penalty inflicted against the primary contractor? Also, we must bear in mind that the parties between themselves, by their subcontract, may fix a completion date different from that contained in the primary contract, in which event, as between the subcontractor and the primary contractor, the subcontract would fix liability.”

The opinion fails to state how these observations apply to the facts of the present [704]*704case. On a second appeal following remand and retrial, the Kentucky Court of Appeals in a “NOT TO BE PUBLISHED” opinion rendered September 18, 1981, attempted to apply the above quoted language from the first Supreme Court opinion {Mattingly # 1) to the trial court’s decision on the retrial. The trial court had again found that any delay on the part of Holloway in completing its prime contract resulted solely from its own fault and again held that Holloway was not entitled to liquidated damages from its subcontractor, Mattingly. After a discussion in the opinion of the facts and the law which sheds no light on the problem, the holding by the Court of Appeals on this second appeal {Mattingly # 2) was as follows:

“Therefore, we must remand this case to the trial court for a finding as to whether Mattingly did indeed miss completion date, and, if so, whether Holloway is entitled to liquidated damages under the subcontract.”

For technical reasons the second appeal did not come to this Court. The Court of Appeals’ decision in Mattingly # 2 is the law of the case, so far as it goes. The problem for the trial court on remand was to decide what the Court of Appeals had decided and apply it. The trial court made a valiant effort to understand and follow the mandate of the Court of Appeals. Without withdrawing its previous findings that “the whole of any delay” in completing the prime contract was in fact attributable to Holloway, and that “there is no support in the evidence for any recovery of liquidated damages against Mattingly,” it interpreted the law of the case to require a judgment awarding Holloway liquidated damages commencing from November 15, 1971, in the sum of $750.00 per day for 193 days, totaling $152,554.23, the full amount claimed.

Thus the stage was set for the third appeal {Mattingly # 3). The Court of Appeals affirmed, but we have accepted discretionary review because none of the prior decisions have served to resolve the law in this case. If Mattingly # 2 is a mandate that, regardless of whether Holloway suffered any provable damages from Mattingly’s failure to complete by November 15, 1971, Holloway was entitled to liquidated damages, the next question is, for how many days? What about the decision of the Department of Highways charging Holloway liquidated damages for only 17-⅜ days delay in completion? What about the last clause in the subcontract:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matthew Ward v. Chad Lertora
Court of Appeals of Kentucky, 2024
Granite State Ins. Co. v. Star Mine Servs., Inc.
29 F.4th 317 (Sixth Circuit, 2022)
Louisville Metro. Sewer v. T+C Contracting
570 S.W.3d 551 (Missouri Court of Appeals, 2018)
Goetz v. Asset Acceptance, LLC
513 S.W.3d 342 (Court of Appeals of Kentucky, 2016)
Bose Corporation v. Ejaz
732 F.3d 17 (First Circuit, 2013)
Patel v. Tuttle Properties, LLC
392 S.W.3d 384 (Kentucky Supreme Court, 2013)
Barrie School v. Patch
933 A.2d 382 (Court of Appeals of Maryland, 2007)
G.D. Deal Holdings, Inc. v. Baker Energy, Inc.
501 F. Supp. 2d 914 (W.D. Kentucky, 2007)
Kelly v. Marx
694 N.E.2d 869 (Massachusetts Appeals Court, 1998)
Man O War Restaurants, Inc. v. Martin
932 S.W.2d 366 (Kentucky Supreme Court, 1996)
Murray v. McCoy
949 S.W.2d 613 (Court of Appeals of Kentucky, 1996)
Wehr Constructors, Inc. v. Steel Fabricators, Inc.
769 S.W.2d 51 (Court of Appeals of Kentucky, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
694 S.W.2d 702, 1985 Ky. LEXIS 238, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mattingly-bridge-co-v-holloway-son-construction-co-ky-1985.