Louisville and Jefferson County Metropolitan Sewer District v. T+c Contracting, Inc.

CourtKentucky Supreme Court
DecidedDecember 13, 2018
Docket2017-SC-0274
StatusUnpublished

This text of Louisville and Jefferson County Metropolitan Sewer District v. T+c Contracting, Inc. (Louisville and Jefferson County Metropolitan Sewer District v. T+c Contracting, Inc.) is published on Counsel Stack Legal Research, covering Kentucky Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Louisville and Jefferson County Metropolitan Sewer District v. T+c Contracting, Inc., (Ky. 2018).

Opinion

RENDERED: DECEMBER 13, 2018 TO BE PUBLISHED

2017-SC-000274-DG

LOUISVILLE AND JEFFERSON COUNTY APPELLANT METROPOLITAN SEWER DISTRICT

ON REVIEW FROM COURT OF APPEALS V. CASE NOS. 2015-CA-000333 AND 2015-CA-000374 JEFFERSON CIRCUIT COURT NO. 12-CI-006235

T+C CONTRACTING, INC. APPELLEE

OPINION OF THE COURT BY CHIEF JUSTICE MINTON

AFFIRMING IN PART, REVERSING IN PART AND REMANDING

The Kentucky Fairness in Construction Act (“KFCA”),1 which became

effective over a decade ago, made dramatic changes in our existing law by

voiding, as a matter of public policy, a host of what were then customary

provisions in construction contracts. On discretionary review of this case, we

hold that the Court of Appeals erred when it applied provisions of the KFCA to

void the entire dispute-resolution process contained in the parties’ sewer-

construction contract. The KFCA nullifies contract provisions that prohibit the

parties from asserting preserved claims to a neutral third-party adjudicator,

but it does not nullify claim-preservation requirements in a contract. And the

Court of Appeals further erred by failing to apply the applicable severability

1 Kentucky Revised Statutes (“KRS”) 371.400 et seq. provisions of the KFCA that nullify only the nonconforming contract provisions,

leaving the remaining provisions intact. Accordingly, we reverse the decision of

the Court of Appeals on this point and reinstate the summary judgment

entered in the trial court. We affirm the Court of Appeals on all remaining

issues.

I. BACKGROUND.

The Louisville and Jefferson County Metropolitan Sewer District (“MSD”)

hired T+C Contracting, Inc. (“T+C”) for its Board Run Interceptor, a sewer

project in southeast Louisville, for approximately $2.3 million. The contract

governing the parties’ relationship consists of 20 pages of detailed terms,

including the timeframe for performance, the process for dispute resolution

(referred to as “Article 13”), and liquidated damages for delayed completion. As

provided in the contract, T+C began work on February 1, 2011. T+C was

supposed to substantially complete the project by January 31, 2012, but that

did not happen.

II. ANALYSIS.

Before this Court for resolution are three issues: (1) whether the trial

court correctly awarded summary judgment to MSD on one of T+C’s claims for

extra work, (2) whether the trial court properly handled MSD’s liquidated

damages claim, and (3) whether the trial court properly denied MSD’s motions

for directed verdict and judgment notwithstanding the verdict (“JNOV”) on one

of MSD’s breach of contract claims against T+C. We address each issue and

their subparts in turn.

2 A. The trial court properly granted summary judgment in favor of MSD on T+C’s claim for extra work undertaken to repair and replace damaged pipes associated with the project. MSD first challenges the Court of Appeals’ reversal of the trial court’s

grant of summary judgment in favor of MSD, clearing MSD of any liability on

T+C’s claim for costs incurred in repairing and replacing piping used in the

construction of the project. A trial court may grant summary judgment only if

the evidence before it “show[s] that there is no genuine issue as to any material

fact and that the moving party is entitled to a judgment as a matter of law.”2

“Appellate review of a summary judgment involves only legal questions and a

determination of whether a disputed material issue of fact exists. So we operate

under a de novo standard of review with no need to defer to the trial court’s

decision.”3

1. Factual and Procedural Background.

Under the contract, T+C agreed to install more than 9,400 linear feet of

sewer pipe. In early 2012, T+C advised MSD that it had completed work on the

project and requested that MSD declare the project substantially complete. On

March 5, 2012, MSD notified T+C that it had inspected the pipe system and

had discovered leaks. Because of the leaks, MSD refused to declare the project

substantially complete. On March 16, T+C notified MSD that the known leaks

had been repaired and again requested that MSD declare the project to be

substantially complete. On March 22, an MSD representative removed a

2 Kentucky Rules of Civil Procedure (“CR”) 56.03. 3 Shelton v. Kentucky Easter Seals Soc’y., Inc., 413 S.W.3d 901, 905 (Ky. 2013) (internal citations omitted). 3 manhole cover and saw water in the pipe invert. On April 2, MSD responded to

the March 16 letter, stating that it had not accepted the piping and refused to

declare the project substantially complete.

Before T+C began further repairs, T+C notified MSD in a letter dated

June 6, 2012: “If MSD continues to require that T+C Contracting perform work

outside the scope of its contract, T+C Contracting will require that a change

order be issued for an equitable adjustment to the contract.” MSD responded to

T+C’s notification in a letter dated June 14, 2012, by inquiring, in part, about

whether T+C would perform further work on the project. T+C responded in a

letter dated June 15, 2012: “T+C is not refusing to perform any further work . .

. . If the work you identify is beyond the scope of our contract, we will submit a

proper change order request for that work.”

Beginning on June 27, 2012, T+C conducted exfiltration testing to locate

the remaining leaks. On July 11, 2012, T+C sent the following email to MSD,

claiming that the failure of the pipes was due to a design defect in the pipes

that MSD mandated T+C use:

We again state that this exfiltration testing and repairs are being done under protest since the line had previously passed air testing as required by the specifications. T+C will submit a change order request for an equitable adjustment to the contract price and the contract time as the result of the duplicative testing and the work required as the result of the design deficiency.4 However, we are proceeding in good faith in an attempt to get this line open for accepting sewer flow.

4 An internal MSD memo, the evidentiary admissibility of which is disputed, indicates that around this time MSD reevaluated the type of pipe it uses under creek crossings. The memo indicates that the type of pipe MSD required in such areas failed in both the Broad Run and River Road Interceptors Projects. 4 The testing revealed cracks, which allowed groundwater to infiltrate the pipes

under four creek crossings. T+C repaired the pipe at three of the four

locations, having to replace the pipe at the fourth location because it was

beyond repair, incurring additional costs for labor, materials, and equipment.

Before replacing the pipe at the fourth location, T+C retained

independent consultants to observe its work and inspect the cracked pipe and

concrete encasement as they were removed. The consultants could not

determine what generated the large lateral forces that would have caused the

cracks in the concrete pipe and encasement, but they indicated that they were

not caused by an installation failure on the part of T+C.

On August 24, 2012, MSD certified in writing that substantial

completion was achieved on August 17, 2012. On September 7, 2012, T+C

reaffirmed that it intended to file a claim for the costs of the repairs and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Westates Construction Co. v. City of Cheyenne
775 P.2d 502 (Wyoming Supreme Court, 1989)
Mountain Water District v. Smith
314 S.W.3d 312 (Court of Appeals of Kentucky, 2010)
Mattingly Bridge Co. v. Holloway & Son Construction Co.
694 S.W.2d 702 (Kentucky Supreme Court, 1985)
DeStock 14, Inc. v. Logsdon
993 S.W.2d 952 (Kentucky Supreme Court, 1999)
Commonwealth v. English
993 S.W.2d 941 (Kentucky Supreme Court, 1999)
Green International, Inc. v. Solis
951 S.W.2d 384 (Texas Supreme Court, 1997)
Lewis v. Bledsoe Surface Mining Co.
798 S.W.2d 459 (Kentucky Supreme Court, 1990)
Wesley v. Board of Education of Nicholas County
403 S.W.2d 28 (Court of Appeals of Kentucky (pre-1976), 1966)
Robert F. Simmons & Associates v. Urban Renewal & Community Development Agency of Louisville
497 S.W.2d 705 (Court of Appeals of Kentucky (pre-1976), 1973)
Yates v. United States
135 S. Ct. 1074 (Supreme Court, 2015)
Koppers Co. v. Asher Coal Mining Co.
11 S.W.2d 114 (Court of Appeals of Kentucky (pre-1976), 1928)
Business Men's Assur. Co. of America v. Eades
161 S.W.2d 920 (Court of Appeals of Kentucky (pre-1976), 1942)
McHargue v. Scott
305 S.W.2d 929 (Court of Appeals of Kentucky, 1957)
Shawnee Telecom Resources, Inc. v. Brown
354 S.W.3d 542 (Kentucky Supreme Court, 2011)
Shelton v. Kentucky Easter Seals Society, Inc.
413 S.W.3d 901 (Kentucky Supreme Court, 2013)
Commonwealth v. Andrews
448 S.W.3d 773 (Kentucky Supreme Court, 2014)
Inverultra, S.A. v. Wilson
449 S.W.3d 339 (Kentucky Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Louisville and Jefferson County Metropolitan Sewer District v. T+c Contracting, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/louisville-and-jefferson-county-metropolitan-sewer-district-v-tc-ky-2018.