Business Men's Assur. Co. of America v. Eades

161 S.W.2d 920, 290 Ky. 553, 1942 Ky. LEXIS 426
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedFebruary 6, 1942
StatusPublished
Cited by14 cases

This text of 161 S.W.2d 920 (Business Men's Assur. Co. of America v. Eades) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Business Men's Assur. Co. of America v. Eades, 161 S.W.2d 920, 290 Ky. 553, 1942 Ky. LEXIS 426 (Ky. 1942).

Opinion

Opinion op the Court by

Sims, Commissioner

— Affirming.

Tbe appellee, J. T. Eades, Jr., recovered judgment against tbe Business Men’s Assurance Company (hereinafter referred to as tbe Company) for commissions of $1,763.91 alleged to be due him under a contract, and the Company appeals. Tbe case was referred to tbe master commissioner to bear proof and determine tbe accounts between tbe parties. He found in favor of Eades in tbe above sum and tbe chancellor confirmed tbe report. There is but slight controversy as to tbe amount due appellee if be is entitled to commissions and tbe real issue is whether be is entitled to any commissions under tbe contract.

On Jan. 2, 1931, Eades entered tbe employment of tbe Company as special agent solely for tbe purpose of obtaining applications for life and disability insurance. On Mar. 2, 1936, be entered into a written contract with *555 it whereby he was employed as district supervisor for a number of counties in Kentucky for the purpose of assisting in the recruiting and training of new salesmen who might be assigned to him for that purpose by the Company.

The material parts of this contract provide that Eades shall spend with the salesmen such time as may be required by the Company’s branch manager and submit reports of his training efforts when required; also, make reports each week to the branch manager of his •activities. His consideration as district supervisor was a commission of seventy-five cents on each $7 worth of •business procured by the new salesmen assigned to him for training during their first two years of service, and also during the time he is conducting the training program in accordance with the instructions of the Company. Failure on Eades’ part to spend the specified time with the new salesmen, or to make reports as above indicated, forfeited his right to receive commissions on their production during any month the training schedule was not fulfilled or reports were not furnished. The contract further provided it might be modified at any time by mutual consent, or terminated by either party upon 30 days ’ written notice.

Under this contract the Company assigned three -salesmen to Eades for training; two, V. B. Wiggins and C. L. McDowell, on March 2, 1936; and the third, E. H. Sawyer, on July 1st, of that year. Eades trained these salesmen as provided by the contract and received commissions on their production until Nov. 1, 1936. On Oct. 26, 1936, he received a letter from the Company stating in effect that it had decided the salesmen training plan was not a success and beginning Nov. 1, 1936, the Company would abandon it, and Eades would be relieved from all responsibility of the salesmen under him and would devote no further time to them and would discontinue his reports on their activities. After receiving this letter Eades relinquished supervision over the three salesmen and discontinued reports on them, but he continued with the Company as special agent under the contract of Jan. 2, 1931, until he resigned on Mar. 31, 1937.

Eades brought this action on his contract of March 2, 1936, to recover commissions from Nov. 1, 1936, to March 2, 1938, on the production of the two salesmen who remained with the Company the full two years, and to re *556 cover commissions from Nov. 1, 1936, to Jan. 1, 1938, the date the third salesman, McDowell, severed connections with it, on his production. The Company’s answer pleaded the contract was terminated by the letter of Oct. 26th,. and secondly, that Eades resigned on Mar. 31, 1937. Eades’ motion that the Company be required to elect which of the two alleged inconsistent defenses it would rely upon was sustained, and it elected to stand on the first defense and struck the second from its pleadings. As the proof of one of these defenses did not necessarily disprove the other, they are not inconsistent. Civil Code of Practice, Section 113; Jones v. Whitaker, 141 Ky. 484, 133 S. W. 223; Hicks v. Oak’s Adm’r, 233 Ky. 27, 24 S. W. (2d) 917. However, this error of the chancellor was of no consequence for the reason that the caséis governed by the contract and the letter terminating it.

It is insisted by Eades that the contract of Mar. 2,. 1936, had become executed when the Company attempted to terminate it by the letter of Oct. 26th, and that an executed contract cannot be arbitrarily terminated by one-of the parties. It is further insisted by him that if the contract were executory rather than an executed one,, then the notice not being in the terms provided by the contract, was not sufficient to terminate it. Eades argues that this is an executed contract because he trained two-of the salesmen from Mar. 2, 1936, and the third from July 1st of that year until he received the letter the latter-part of October, 1936, and this entitled him to commissions on their production for two years should they remain with the Company that long.

It will be noted that the contract does not expressly state the duration of the training period but merely provides Eades is entitled to commissions during the time he is conducting the training program in accordance with the Company’s instructions and during the first two years of service of such salesmen. The contract provides it can be modified by mutual consent or that it maybe terminated by either party upon 30 days’ written, notice.

Where a contract has been fully performed by one-party it cannot be terminated by the other. 12 Am. Jur., Section 414, page 994. But the parties may enter into an. agreement wherein either has the right to terminate it at will and the courts will enforce such agreement, insofar as it has not been executed, as the parties have writ *557 ten. Ford Motor Co. v. Alexander Motor Co., 223 Ky. 16, 2 S. W. (2d) 1031; Paragon Oil Co. v. A. B. Hughes & Sons, 193 Ky. 532, 236 S. W. 963.

Appellant Company argues this contract is not severable and can be considered only in its entirety, and as ■the entire contract had not been performed, it had the right to cancel same on 30 days’ notice as provided in the contract. Primarily the question of whether a contract is entire or severable depends upon the intention of the parties, the objects to be attained and the common sense of the situation. 13 C. J., Section 526, p. 562, Section 539, p. 568; 17 C. J. S., Contracts, Sections 332, 344; 13 R. C. L., Section 246, p. 858; Gilmore & Co. v. W. B. Samuels & Co., 135 Ky. 706, 123 S. W. 271, 21 Ann. Cas. 611; Koppers v. Asher Coal Mining Co., 226 Ky. 492, 11 S. W. (2d) 114. As this contract related not only to the three salesmen in question but to a general training plan for any salesmen the Company might send Eades and as it provided compensation for him during the training period as well as after it was completed, it is apparent the contract was severable.

The pivotal point in this ease is whether Eades had ■completed the training of the three salesmen when he received a letter terminating the contract. If so, the •contract was executed insofar as it related to them and under the authority of Ford Motor Co. v. Alexander Motor Co., 223 Ky. 16, 2 S. W. (2d) 1031, and Paragon Oil Co. v. A. B. Hughes & Sons, 193 Ky. 532, 236 S. W. 963, the Company could not terminate it and deprive Eades of commissions on the production of the salesmen he had trained.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth of Kentucky v. Darrell Strunk
Kentucky Supreme Court, 2025
Sharon Q. Elzy, Individually v. Arthur C. Elzy, Jr.
Court of Appeals of Kentucky, 2024
Louisville Metro. Sewer v. T+C Contracting
570 S.W.3d 551 (Missouri Court of Appeals, 2018)
Samuel T. Isaac & Associates, Inc. v. Federal National Mortgage Ass'n
647 S.W.2d 495 (Court of Appeals of Kentucky, 1982)
Becker v. Nahm & Turner, Inc.
435 S.W.2d 750 (Court of Appeals of Kentucky, 1968)
McHargue v. Scott
305 S.W.2d 929 (Court of Appeals of Kentucky, 1957)
Government Personnel Mut. Life Ins. Co. v. Wear
247 S.W.2d 284 (Court of Appeals of Texas, 1952)
Knight v. Hamilton
233 S.W.2d 969 (Court of Appeals of Kentucky, 1950)
Knight v. Hamilton
233 S.W.2d 969 (Court of Appeals of Kentucky (pre-1976), 1950)
Riedley v. Hudson Motor Car Co.
82 F. Supp. 8 (W.D. Kentucky, 1949)
Cook's Adm'r v. the Bank Josephine
191 S.W.2d 209 (Court of Appeals of Kentucky (pre-1976), 1945)

Cite This Page — Counsel Stack

Bluebook (online)
161 S.W.2d 920, 290 Ky. 553, 1942 Ky. LEXIS 426, Counsel Stack Legal Research, https://law.counselstack.com/opinion/business-mens-assur-co-of-america-v-eades-kyctapphigh-1942.