Louisville Metro. Sewer v. T+C Contracting

570 S.W.3d 551
CourtMissouri Court of Appeals
DecidedDecember 13, 2018
Docket2017-SC-000274-DG
StatusPublished
Cited by11 cases

This text of 570 S.W.3d 551 (Louisville Metro. Sewer v. T+C Contracting) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Louisville Metro. Sewer v. T+C Contracting, 570 S.W.3d 551 (Mo. Ct. App. 2018).

Opinion

OPINION OF THE COURT BY CHIEF JUSTICE MINTON

The Kentucky Fairness in Construction Act ("KFCA"),1 which became effective over a decade ago, made dramatic changes in our existing law by voiding, as a matter of public policy, a host of what were then customary provisions in construction contracts. On discretionary review of this case, we hold that the Court of Appeals erred when it applied provisions of the KFCA to void the entire dispute-resolution process contained in the parties' sewer-construction contract. The KFCA nullifies contract provisions that prohibit the parties from asserting preserved claims to a neutral third-party adjudicator, but it does not nullify claim-preservation requirements in a contract. And the Court of Appeals further erred by failing to apply the applicable severability provisions of the KFCA that nullify only the nonconforming contract provisions, leaving the remaining provisions intact. Accordingly, we reverse the decision of the Court of Appeals on this point and reinstate the summary judgment entered in the trial court. We affirm the Court of Appeals on all remaining issues.

I. BACKGROUND.

The Louisville and Jefferson County Metropolitan Sewer District ("MSD") hired T+C Contracting, Inc. ("T+C") for its Board Run Interceptor, a sewer project in southeast Louisville, for approximately $2.3 million. The contract governing the parties' relationship consists of 20 pages of detailed terms, including the timeframe for performance, the process for dispute resolution (referred to as "Article 13"), and liquidated damages for delayed completion. As provided in the contract, T+C began work on February 1, 2011. T+C was supposed to substantially complete the project by January 31, 2012, but that did not happen.

II. ANALYSIS.

Before this Court for resolution are three issues: (1) whether the trial court correctly awarded summary judgment to MSD on one of T+C's claims for extra work, (2) whether the trial court properly handled MSD's liquidated damages claim, and (3) whether the trial court properly denied MSD's motions for directed verdict and judgment notwithstanding the verdict ("JNOV") on one of MSD's breach of contract claims against T+C. We address each issue and their subparts in turn.

A. The trial court properly granted summary judgment in favor of MSD on T+C's claim for extra work undertaken to repair and replace damaged pipes associated with the project.

MSD first challenges the Court of Appeals' reversal of the trial court's grant *556of summary judgment in favor of MSD, clearing MSD of any liability on T+C's claim for costs incurred in repairing and replacing piping used in the construction of the project. A trial court may grant summary judgment only if the evidence before it "show[s] that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law."2 "Appellate review of a summary judgment involves only legal questions and a determination of whether a disputed material issue of fact exists. So we operate under a de novo standard of review with no need to defer to the trial court's decision."3

1. Factual and Procedural Background.

Under the contract, T+C agreed to install more than 9,400 linear feet of sewer pipe. In early 2012, T+C advised MSD that it had completed work on the project and requested that MSD declare the project substantially complete. On March 5, 2012, MSD notified T+C that it had inspected the pipe system and had discovered leaks. Because of the leaks, MSD refused to declare the project substantially complete. On March 16, T+C notified MSD that the known leaks had been repaired and again requested that MSD declare the project to be substantially complete. On March 22, an MSD representative removed a manhole cover and saw water in the pipe invert. On April 2, MSD responded to the March 16 letter, stating that it had not accepted the piping and refused to declare the project substantially complete.

Before T+C began further repairs, T+C notified MSD in a letter dated June 6, 2012: "If MSD continues to require that T+C Contracting perform work outside the scope of its contract, T+C Contracting will require that a change order be issued for an equitable adjustment to the contract." MSD responded to T+C's notification in a letter dated June 14, 2012, by inquiring, in part, about whether T+C would perform further work on the project. T+C responded in a letter dated June 15, 2012: "T+C is not refusing to perform any further work.... If the work you identify is beyond the scope of our contract, we will submit a proper change order request for that work."

Beginning on June 27, 2012, T+C conducted exfiltration testing to locate the remaining leaks. On July 11, 2012, T+C sent the following email to MSD, claiming that the failure of the pipes was due to a design defect in the pipes that MSD mandated T+C use:

We again state that this exfiltration testing and repairs are being done under protest since the line had previously passed air testing as required by the specifications. T+C will submit a change order request for an equitable adjustment to the contract price and the contract time as the result of the duplicative testing and the work required as the result of the design deficiency.4 However, we are proceeding in good faith in an attempt to get this line open for accepting sewer flow.

The testing revealed cracks, which allowed groundwater to infiltrate the pipes under *557four creek crossings. T+C repaired the pipe at three of the four locations, having to replace the pipe at the fourth location because it was beyond repair, incurring additional costs for labor, materials, and equipment.

Before replacing the pipe at the fourth location, T+C retained independent consultants to observe its work and inspect the cracked pipe and concrete encasement as they were removed. The consultants could not determine what generated the large lateral forces that would have caused the cracks in the concrete pipe and encasement, but they indicated that they were not caused by an installation failure on the part of T+C.

On August 24, 2012, MSD certified in writing that substantial completion was achieved on August 17, 2012. On September 7, 2012, T+C reaffirmed that it intended to file a claim for the costs of the repairs and replacement of the pipes, pending a determination of those costs. On October 16, 2012, T+C submitted a claim for $108,542.41 incurred because of additional testing and the repair and replacement of the cracked concrete pipe and encasements that failed for reasons beyond its control. MSD denied this claim, citing T+C's alleged failure to comply with the contract's dispute-resolution process, Article 13. T+C then requested submission of its claim to MSD senior representatives for executive negotiations under Article 13, but MSD did not respond.

T+C to filed suit against MSD. Among other claims, T+C alleged breach of contract for MSD's failure to pay the $108,542.41 for the work it performed to test, repair, and replace the concrete pipes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth of Kentucky v. Darrell Strunk
Kentucky Supreme Court, 2025
Joel Franklin v. Emery Law Office, Inc.
Court of Appeals of Kentucky, 2024
Shannon Ashcraft-Evans v. Allison Lied, M.D.
Court of Appeals of Kentucky, 2024
David Ramler v. William Birkenhauer
Court of Appeals of Kentucky, 2024
Nicholas J. Pendergrast v. Nicklaus Design, LLC
Court of Appeals of Kentucky, 2022
Bobby Brandenburg v. Thorobred Automotive, Inc.
Court of Appeals of Kentucky, 2020
Lynne E. Jones v. Rickey Shive
Court of Appeals of Kentucky, 2020
Dequisha Jackson v. State
Court of Appeals of Texas, 2015

Cite This Page — Counsel Stack

Bluebook (online)
570 S.W.3d 551, Counsel Stack Legal Research, https://law.counselstack.com/opinion/louisville-metro-sewer-v-tc-contracting-moctapp-2018.