Triton Services, Inc. v. Century Construction, Inc.

CourtDistrict Court, E.D. Kentucky
DecidedMarch 14, 2022
Docket2:19-cv-00135
StatusUnknown

This text of Triton Services, Inc. v. Century Construction, Inc. (Triton Services, Inc. v. Century Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Triton Services, Inc. v. Century Construction, Inc., (E.D. Ky. 2022).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF KENTUCKY NORTHERN DIVISION AT COVINGTON

CIVIL ACTION NO. 2:19-CV-135 (WOB-CJS)

TRITON SERVICES, INC. PLAINTIFF

VS. MEMORANDUM OPINION AND ORDER

CENTURY CONSTRUCTION, INC. DEFENDANT

Plaintiff Triton Services, Inc. (Triton) brought this action against Defendant Century Construction, Inc. (Century) for violations of the Kentucky Fairness in Construction Act (KFICA), breach of contract, and unjust enrichment. (Doc. 1). Triton specifically claims that Century is improperly holding a retainage under a construction subcontract between them, amounting to a violation of the KFICA and breach of contract, and that Century is responsible for delay and labor inefficiency, also amounting to breach of contract. (Id.). Century filed a Motion for Summary Judgment on all claims asserted by Triton. (Doc. 39). Having reviewed the parties’ pleadings, the Court now issues the following Memorandum Opinion and Order. I. BACKGROUND On October 15, 2016, Century contracted with the Boone County Board of Education (“the Owner”) for $25,498,800 for the construction of a new middle school (“the Project”). (Doc. 46-8, General Contract, at 3). On October 24, 2016, Triton entered into a subcontract (“the Contract”) with Century to complete the HVAC system for the school, (Doc. 1-1, Century-Triton Subcontract), and later amended by change order to include the installation of the plumbing system, as well, (Doc. 1-2, Change Order). The general

contract provided that the Project was to take 20 months in total, to be ready for occupation by June 1, 2018, and ending completely on July 1, 2018, (See Doc. 46-8 at 3). The subcontract between Century and Triton would be completed in accordance with a separate schedule of Century’s design that was yet to be finalized. (Doc. 1-1 at 2). Other than the general 20-month timeframe for the Project, Triton’s own time of performance was not otherwise specified in the Contract with Century. (See id.). The total price of the Contract between the parties after several change orders was $4,532,923.00. (Doc. 1 at ⁋ 8).

Triton’s work on the Project began in March 2017 and was not completed until September 2018. (Doc. 1 at ⁋⁋ 11, 17). As the school was scheduled to be open for the 2018 school year, Century had Triton work overtime to complete the Project sooner. (Id. at ⁋ 12). As mentioned, Triton claims that since completion, Century has improperly held $226,646.15 as retainage, which happens to be 5% of the Contract price, even after Triton completed its work on the Project. (Doc. 46 at 10). Century raises two main points justifying its “retainage”: first, that the Owner has yet to disburse the same funds to Century, relieving it of its obligation to pay the balance; and, second, the amount retained is exactly 5% of the total contract price, which is the amount the KFICA allows Century to withhold in such situations. (Doc. 40 at 1–2). Then, as to Triton’s breach of contract and unjust enrichment claims for

allegedly uncompensated overhead and labor costs, Century argues the Contract already provides for the costs and services between the parties—accounted for in the contract price, a lump sum already firmly agreed to, and the overtime premiums it paid—and that Triton gave untimely notice of its delay claim. II. ANALYSIS For Defendant Century to prevail on its Motion for Summary Judgment, it must establish that there is no genuine dispute of material fact as to whether it violated the KFICA, breached its Contract with Triton, or was unjustly enriched. Summary judgment is appropriate “if the pleadings, depositions, answers to

interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” FED. R. CIV. P. 56(c). Under this standard, the Court views the evidence and draws all reasonable inferences in the light most favorable to the non-moving party. Lanman v. Hinson, 529 F.3d 673, 679 (6th Cir. 2008). Still, the “mere existence of some alleged factual dispute between the parties will not defeat an otherwise properly supported motion for summary judgment; the requirement is that there be no genuine issue of material fact.” Id. (citing Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247–48 (1986)). After the moving party shows that there is an absence of evidence to support the non-moving party’s case,

the non-moving party must present “significant probative evidence” to demonstrate that “there is [more than] some metaphysical doubt as to the material facts.” Moore v. Philip Morris Companies, Inc., 8 F.3d 335, 340 (6th Cir. 1993). A federal court sitting in diversity must apply the law of the forum state, including its law governing contracts. See City of Wyandotte v. Consol. Rail Corp., 262 F.3d 581, 585 (6th Cir. 2001). “The interpretation of a contract, including determining whether a contract is ambiguous, is a question of law.” Superior Steel, Inc. v. Ascent at Roebling’s Bridge, LLC, 540 S.W.3d 770, 783 (Ky. 2017). Contract interpretation, therefore, is a question

for the Court, and not for a jury. See id. See also City of Wyandotte, 262 F.3d at 585 (citing Sault Ste. Marie Tribe of Chippewa Indians v. Engler, 146 F.3d 367, 373 (6th Cir. 1998)). Whether a breach of contract occurred given the evidence, however, is a question of fact for the jury, in this instance subject to the just-described summary judgment standard. See Schmidt v. Schmidt, 343 S.W.2d 817, 819 (Ky. 1961); Harlan Fuel Co. v. Wiggington, 262 S.W. 957, 958 (Ky. 1924). Where the contract language is unambiguous, the Court is to interpret the contract in accordance with the plain meaning of the words used by the parties, with a mind to effectuating the manifest intent of the parties. Kentucky Shakespeare Festival, Inc. v.

Dunaway, 490 S.W.3d 691, 694 (Ky. 2016). Even where the contract is ambiguous, the Court’s primary purpose will be to discern and apply the intention of the parties. See id. A. KFICA 1. Retainage Amount The KFICA was created to “help level the playing field between contractors and owners.” Louisville & Jefferson Cty. Metro. Sewer Dist. v. T+C Contr. Inc., 570 S.W.3d 551, 558 (Ky. 2018). Under the Act, “retainage held after fifty-one percent (51%) of the construction project has been completed shall not be more than five percent (5%) of the total contract amount.” KRS § 371.410(1).

Triton argues that Century violated the KFICA by withholding more than 5% of the total contract amount, whereas Century claims that it has withheld exactly 5% as the KFICA allows. (Docs. 1 at ⁋ 39; 40 at 11). Triton offers no rebuttal to this point. (Doc. 46). The total contract amount is $4,532,923.00, and Century has withheld $226,646.15, which is an exact 5% balance. (Doc. 40 at 11). Because Century has not exceeded the 5% allowed by the KFICA, the amount of retainage itself does not violate state law. 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Day v. United States
245 U.S. 159 (Supreme Court, 1917)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Lanman v. Hinson
529 F.3d 673 (Sixth Circuit, 2008)
United States v. Leigh
515 F. Supp. 405 (S.D. Ohio, 1981)
JJ Brown Co., Inc. v. JL Simmons Co., Inc.
118 N.E.2d 781 (Appellate Court of Illinois, 1954)
The Kentucky Shakespeare Festival, Inc. v. Brantley Dunaway
490 S.W.3d 691 (Kentucky Supreme Court, 2016)
Schmidt v. Schmidt
343 S.W.2d 817 (Court of Appeals of Kentucky, 1961)
County of Galveston v. Triple B Services, LLP
498 S.W.3d 176 (Court of Appeals of Texas, 2016)
A.H.A. General Construction, Inc. v. New York City Housing Authority
699 N.E.2d 368 (New York Court of Appeals, 1998)
Moore v. Philip Morris Companies, Inc.
8 F.3d 335 (Sixth Circuit, 1993)
Harlan Fuel Co. v. Wiggington
262 S.W. 957 (Court of Appeals of Kentucky, 1924)
Superior Steel, Inc. v. Ascent at Roebling's Bridge, LLC
540 S.W.3d 770 (Missouri Court of Appeals, 2017)
Louisville Metro. Sewer v. T+C Contracting
570 S.W.3d 551 (Missouri Court of Appeals, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Triton Services, Inc. v. Century Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/triton-services-inc-v-century-construction-inc-kyed-2022.