Harlan Fuel Co. v. Wiggington

262 S.W. 957, 203 Ky. 546, 1924 Ky. LEXIS 960
CourtCourt of Appeals of Kentucky
DecidedJune 3, 1924
StatusPublished
Cited by15 cases

This text of 262 S.W. 957 (Harlan Fuel Co. v. Wiggington) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harlan Fuel Co. v. Wiggington, 262 S.W. 957, 203 Ky. 546, 1924 Ky. LEXIS 960 (Ky. Ct. App. 1924).

Opinion

Opinion op the Court by

Commissioner Hobson

Reversing.

In the spring of 1920 the Harlan Fuel Company proposed to erect a tipple, coal conveyor -and head-house on its property, and to this end had procured blue print specifications of the work, and on May 1st J. E. Condra entered into a written contract with it by which he agreed to do the work according to the specifications for $3,-998.00, and to complete it within sixty days from the date the work was begun. The written contract provided that as a guarantee of his ability to perform the contract Condra should procure a bond in the sum of $2,500.00, to be executed by some good solvent bonding company; but afterwards, by consent of parties, this provision was waived upon the execution, by appellees, I. D. Wigging-ton and T. Gr. Wright, of the following bond:

“Whereas, Harlan Fuel Company has made and entered into a written contract with j. E. Condra to build and construct, ready for use and operation, one coal tipple, one coal conveyor, and headhouse and other things in connection therewith, named in said contract, at its mine on Slater fork in Harlan county, Kentucky, which contract was made and executed between the parties on the 1st day of May, 1920, and it is provided in said contract that J. E. Condra shall execute and deliver to Harlan Fuel Company a good and sufficient bond in the sum of [549]*549$2,500.00, which bond shall guarantee the full, complete and proper performance of said contract.
“Now, J. E. Condra, as principal, and we, I. D. Wiggington and T. Gr. Wright, as his sureties, do hereby undertake to and by these presents do guarantee that said J. E. Condra will completely, fully and properly execute said contract, and if the said J. E. Condra fails to properly execute said contract, we hereby agree to pay, and we are held and firmly bound unto the said Harlan Fuel Company, a corporation, in the sum of $2,500.00 to the payment of which to the said company we bind ourselves, our heirs, our executors and our administrators.
“However, if said J. E. Condra shall faithfully and fully perform all the obligations and duties imposed upon him by said contract and pay all debts for labor and other things in connection therewith, which he is bound to pay under said contract, then this obligation shall be void, otherwise it shall be and remain in full force and effect.
In witness whereof we have hereunto, set our hands this 1st day of May, 1920,
“J. E. Condra, Principal I. D. Wiggington, Surety T. Gr. Weight, Surety.”

Condra failed to complete the work and this action was brought against the sureties by the Harlan Fuel Company to recover on the bond. By their answer the defendants controverted the allegations of the petition. They pleaded that the plaintiff had failed to retain ten per cent of Condra’s pay roll as provided in the contract, and had failed to require Condra to file with the plaintiff written receipts from each employee showing that he had been paid by Condra for his labor. They also pleaded that by the contract the plaintiff was required to furnish all material and machinery necessary for the work and to place same on the ground near where the structures were to be erected and that this it failed to do, which had added $2,000.00' to Condra’s expense. A reply was filed controverting the allegations of the answer. The case was heard before a jury and at the conclusion of the evidence the court by instruction one told the jury, in substance, that if they believed from the evidence that the plaintiff furnished to the contractor the material mentioned in the contract as near as practi[550]*550cal to the place where the same was to be used, and further believed from the evidence that.Condra failed.to construct the things contracted for in- accordance with the plans and specifications and abandoned, the work before its completion, and that plaintiff was put to additional expense of. completing the work over and above the contract price, then they should find for the plaintiff for such excess, not to exceed, however, the sum of $2,500.00; and unless they so believed they should find for the defendant. This was the only material instruction given except No. 2, which is in these words :

“The court further instructs the jury that if they shall believe from the evidence in this case that the plaintiffs broke or failed to perform their part of the contract before the breach the plaintiffs sued for herein, and that the defendants were prejudiced or injured thereby, then you ought to find for. the .defendants.”

The jury found for the defendants and the plaintiff appeals.

On the trial of the case the- evidence offered by the defendants took a wide range ; they proved that the work was not done- according to the specifications, but that additional work was required to' be done not included in the specifications. . There-was also evidence showing that the plaintiff had not retained the ten per cent as required, by the contract and that some delay was caused in the work by the failure of the plaintiff to supply the material. Instruction No. 2 left to the jury both the- law and facts of the case. It left the jury to determine whether the. plaintiff broke its part of the contract, without telling the jury what breaches of the contract, did warrant a finding for the defendant The court instead of this general statement should have told the jury that if the plaintiff had done or failed to do certain things they should find for the defendants and should not have left to the jury to determine what in law was a breach of the contract. Citizens Trust Co. v. Ohio, etc., Tie Co., 138 Ky. 421.

. The interpretation of the contract is a question for the court. Whether under the evidence there has been a breach of the contract as interpreted by the court is a question for the jury. Frankfort Modes Glass Works v. Arbogast, 148 Ky. 4.

[551]*551The defendants did not plead in their answer that the contract had been changed after their bond was given or that the contractor had been required to do work not required by the specifications. This was an affirmative defense and could not be introduced under the general issue. It was error to allow the evidence of a change in the contract when this had not been pleaded. The object of pleading is to notify the opposite party of the facts relied on. It appears that the blue prints and specifications were burned in a house that had been destroyed by fire. This is the reason assigned for their not being produced on the trial, but no demand was made for them until the day of the trial and possibly other copies are in existence which can be obtained; for architects usually keep copies of these things. While the evidence of Oond-ra is to the effect that work was done not required by the plans and specifications and an additional expense was thus incurred by him, the evidence is not clear that the company made any change in the plans or that any additional work was done by its orders. The corporation is only bound by the act of its authorized agent, and its rights are not affected by. any deviation from the contract made by the contractor without its authority. But if after the bond was given it changed the contract and made material additions to the work not provided for in the specifications the sureties were released from liability on the bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leighann Blanton v. Jacques Wigginton
Court of Appeals of Kentucky, 2023
Commonwealth, Department of Highways v. Milby-Farmer, Inc.
494 S.W.2d 88 (Court of Appeals of Kentucky, 1973)
Commonwealth, Department of Highways v. Carson
398 S.W.2d 706 (Court of Appeals of Kentucky, 1966)
Thomas v. Thomas
379 S.W.2d 743 (Court of Appeals of Kentucky, 1964)
National Union Indemnity Co. v. Standard Oil Co.
90 S.W.2d 375 (Court of Appeals of Kentucky (pre-1976), 1936)
American Surety Co. of N.Y. v. Noe
53 S.W.2d 178 (Court of Appeals of Kentucky (pre-1976), 1932)
Young Men's Christian Association's Assignee v. Indemnity Insurance Co. of North America
51 S.W.2d 463 (Court of Appeals of Kentucky (pre-1976), 1932)
Life Casualty Co. of Tennessee v. Metcalf
42 S.W.2d 909 (Court of Appeals of Kentucky (pre-1976), 1931)
Henderson v. Phoenix Insurance Company
25 S.W.2d 359 (Court of Appeals of Kentucky (pre-1976), 1930)
Wright v. Harlan Fuel Company
283 S.W. 944 (Court of Appeals of Kentucky (pre-1976), 1926)

Cite This Page — Counsel Stack

Bluebook (online)
262 S.W. 957, 203 Ky. 546, 1924 Ky. LEXIS 960, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harlan-fuel-co-v-wiggington-kyctapp-1924.