Charles G. Williams Construction, Inc. v. Thomas E. White, Secretary of the Army

271 F.3d 1055, 2001 U.S. App. LEXIS 24073, 2001 WL 1388036
CourtCourt of Appeals for the Federal Circuit
DecidedNovember 8, 2001
Docket01-1074
StatusPublished
Cited by18 cases

This text of 271 F.3d 1055 (Charles G. Williams Construction, Inc. v. Thomas E. White, Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Charles G. Williams Construction, Inc. v. Thomas E. White, Secretary of the Army, 271 F.3d 1055, 2001 U.S. App. LEXIS 24073, 2001 WL 1388036 (Fed. Cir. 2001).

Opinion

FRIEDMAN, Senior Circuit Judge.

In determining a government contractor’s damages where the government has caused delay in the performance of the contract, one problem is determining what portion of the contractor’s home office overhead costs during the delay period is properly chargeable to the contract involved. The so-called Eichleay damages involve a formula by which to calculate the government’s liability for the contractor’s unabsorbed office overhead.

In this case the Armed Services Board of Contract Appeals (“Board”) rejected the appellant contractor’s claim for Eichleay damages. It ruled that the contractor’s “overhead for the entire period of extended contract performance was ‘fully absorbed by the basic contract, contract modifications, and other projects,’ ” that “in computing [its] average daily overhead rate” the contractor impermissibly used both variable and fixed overhead expenses, and that the contractor’s “Eichleay claim is not proven.” Because the Board did not adequately explain the reasons for its decision, we vacate and remand.

I

The basic facts, as found by the Board, are undisputed. In September 1992, the Army, after competitive bidding, awarded *1057 a fixed price contract to the appellant Charles G. Williams Construction, Inc. (“Williams”) to improve and repair building number 628 at its medical center in Colorado. The work was to be done in two phases: phase one was the south half of the building, and phase two was the north half. The work on phase one was to be completed within 190 days of the government’s notice to the contractor to proceed. There was a planned 10 day interval between the completion of phase one and the start of phase two. Williams “reasonably understood, and the Government ultimately agreed, that the contract required the Government to vacate each phase while that phase was under construction.” On October 16, 1992, Williams received notice to proceed on phase one, thereby establishing completion dates of April 24, 1993 for that phase, and October 11, 1993 for phase two.

Then followed a series of problems and disputes resulting from defects in the government’s specifications and deficiencies in Williams’ own performance and that of its subcontractors. The government failed to vacate the southern portion of the building as required, which caused substantial delays in Williams’ performance. The government issued a large number of change orders, many of which provided for additional payment.

There was discussion about extending the time for performance. At a meeting on October 20, 1993 (six months after the original April 24, 1993 completion date for phase one), the parties agreed that Williams would have until December 20, 1993 to complete phase one. On December 7,1993, the government terminated for convenience Williams’ work on phase two, except for those parts of the work that the government had directed Williams to complete as part of phase one. Williams did not complete phase one until April 26, 1994, 93 days later.

Williams filed claims with the contracting officer. After the contracting officer failed to rule on them within 60 days, Williams treated this as a deemed denial, see 41 U.S.C. § 605(c)(5), and appealed the adverse decision to the Board. Following an evidentiary hearing, the Board, in a detailed opinion, allowed certain of the claims (totaling $47,119). The Board, however, denied Williams’ Eichleay claim. It stated:

24. CGW [Williams] claims $98,642 for 330 days of “extended overhead/unabsorbed overhead” allegedly incurred as a result of the drawing defects, differing site conditions and Government occupancy of the work area. The claimed amount is an “Eichleay” calculation. (Gov’t supp. R4, Vol. B at 9; R4, tab 62 at 5-6) The DCAA [Defense Contract Audit Agency] auditor found that the overhead for the entire period of extended contract performance was “fully absorbed by the basic contract, contract modifications, and other projects.” He further found that CGW used both variable and fixed overhead expenses in computing the average daily overhead rate. (Gov’t supp. R4, Book 11, tab 2 at 003795-96; tr. 2/270-73) On this evidence, CGW’s Eichleay claim is not proven.

II

In West v. All State Boiler, Inc., 146 F.3d 1368 (Fed.Cir.1998), we explained the rationale of Eichleay damages. We pointed out that in addition to a contractor’s direct costs, which “arise solely because of and are attributable directly to performance of a specific contract,” “a government contractor incurs indirect costs which are not attributable to one contract in particular but arise because of its gener *1058 al operations. Indirect costs are usually those costs that are ‘incurred despite construction inactivity on a project, such as home office overhead including accounting and payroll services, general insurance, salaries of upper level management, heat, electricity, taxes, depreciation.’ ” Id. at 1372 (quoting Interstate Gen. Gov’t Contractors, Inc. v. West, 12 F.3d 1053, 1058 (Fed.Cir.1993)). “A contractor recovers its indirect costs by allocating them on a proportionate basis among all of its contracts.” Id. (citations omitted). We quoted the following statement from the Board’s Eichleay decision:

[Ojverhead costs, including the main office [or home office] expenses involved in this case, cannot ordinarily be charged to a particular contract. They represent the cost of general facilities and administration necessary to the performance of all contracts. It is therefore necessary to allocate them to specific contracts on some fair basis of proration.

Id. at 1372 (quoting Eichleay Corp., ASBCA No. 5183, 60-2 B.C.A. (CCH) ¶ 2688, 13,574, 1960 WL 538 (I960)) (second alteration in original). We further stated that “recovery under the Eichleay formula is an extraordinary remedy designed to compensate a contractor for unabsorbed overhead costs that accrue when contract completion requires more time than originally anticipated because of a government-caused delay.” Id. at 1377 (citations omitted). The contractor must of course “show that a government-imposed delay occurred.” Sauer Inc. v. Danzig, 224 F.3d 1340, 1348 (Fed.Cir.2000).

Eichleay damages involve a formula used to calculate a contractor’s daily unabsorbed overhead; the amount is then multiplied by the number of days of government-caused performance delay to determine the contractor’s damages. Eichleay Corp., ASBCA No. 5183, 60-2 B.C.A. (CCH) ¶ 2688, 13,568 (1960). In the present case Williams calculated its Eichleay

Free access — add to your briefcase to read the full text and ask questions with AI

Related

WECC, Inc.
Armed Services Board of Contract Appeals, 2021
Agility Public Warehousing Co. KSCP v. Mattis
852 F.3d 1370 (Federal Circuit, 2017)
KBJ, Inc.
Armed Services Board of Contract Appeals, 2016
SWR, Inc.
Armed Services Board of Contract Appeals, 2014
Jmr Construction Corp. v. United States
117 Fed. Cl. 436 (Federal Claims, 2014)
Chevron U.S.A., Inc. v. United States
116 Fed. Cl. 202 (Federal Claims, 2014)
OK's Cascade Co. v. United States
97 Fed. Cl. 635 (Federal Claims, 2011)
Nicon, Inc. v. United States
331 F.3d 878 (Federal Circuit, 2003)
Net Construction, Inc. v. C & C Rehab & Construction, Inc.
256 F. Supp. 2d 350 (E.D. Pennsylvania, 2003)
Pete Vicari, General Contractor, Inc. v. United States
53 Fed. Cl. 357 (Federal Claims, 2002)
Nicon, Inc. v. United States
51 Fed. Cl. 324 (Federal Claims, 2001)
Kanag'Iq Construction Co. v. United States
51 Fed. Cl. 38 (Federal Claims, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
271 F.3d 1055, 2001 U.S. App. LEXIS 24073, 2001 WL 1388036, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charles-g-williams-construction-inc-v-thomas-e-white-secretary-of-the-cafc-2001.