Jindal Builders & Restoration Corp. v. Cincinnati Metro. Hous. Auth.

2020 Ohio 4043, 157 N.E.3d 279
CourtOhio Court of Appeals
DecidedAugust 12, 2020
DocketC-190217
StatusPublished
Cited by3 cases

This text of 2020 Ohio 4043 (Jindal Builders & Restoration Corp. v. Cincinnati Metro. Hous. Auth.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jindal Builders & Restoration Corp. v. Cincinnati Metro. Hous. Auth., 2020 Ohio 4043, 157 N.E.3d 279 (Ohio Ct. App. 2020).

Opinion

[Cite as Jindal Builders & Restoration Corp. v. Cincinnati Metro. Hous. Auth., 2020-Ohio-4043.]

IN THE COURT OF APPEALS FIRST APPELLATE DISTRICT OF OHIO HAMILTON COUNTY, OHIO

JINDAL BUILDERS & RESTORATION : APPEAL NO. C-190217 CORP., TRIAL NO. A-1704087 : Plaintiff-Appellant, : O P I N I O N. vs. :

CINCINNATI METROPOLITAN : HOUSING AUTHORITY,

Defendant-Appellee. :

Appeal From: Hamilton County Court of Common Pleas

Judgment Appealed From Is: Affirmed in Part, Reversed in Part, and Cause Remanded

Date of Judgment Entry on Appeal: August 12, 2020

Lindhorst & Dreidame Co., LPA, Barry F. Fagel and Elizabeth M. Mahon, for Plaintiff- Appellant,

Adams, Stepner, Woltermann & Dusing, PLLC, and Jeffrey C. Mando, for Defendant- Appellee. OHIO FIRST DISTRICT COURT OF APPEALS

BERGERON, Judge.

{¶1} Delays in construction projects are one of the banes of existence. In this case,

a contractor and owner fence over who bears the risk of loss for delay, and whether

overhead costs are recoverable as damages under the contract at hand. Although the trial

court denied the contractor any relief, we conclude that it erred by prohibiting overhead

damages, but that only part of the time period sought by the contractor is ultimately

recoverable. We therefore reverse in part and remand for further proceedings.

I.

{¶2} To fully appreciate the dispute in this case, we begin with an overview of the

Millvale North Development Project in Cincinnati. Originally, in 2014, defendant-appellee

Cincinnati Metropolitan Housing Authority (“CMHA”) undertook a rehabilitation project

for several public housing buildings in its Millvale North development, awarding the

entirety of this project to a third-party contractor. However, the original contractor proved

not up to the task and could not finish the entire project, prompting CMHA to divide the

contract into two phases—leaving the original contractor on Phase I, but searching for

another contractor to complete Phase II. According to CMHA, it planned to transfer Phase

II residents into the Phase I units upon its completion, thereby vacating the Phase II units

for rehabilitation. But, unfortunately for CMHA, even after the division, the original

contractor continued to struggle, leading CMHA to conclude that if you want something

done right, do it yourself, and thus it terminated that contractor and deemed itself the

general contractor of Phase I. In the meantime, CMHA hunted for a contractor for Phase II,

ultimately landing on plaintiff-appellant Jindal Builders & Restoration, Corp., (“Jindal”) in

December 2015.

{¶3} Two months later, in February 2016, Jindal and CMHA entered into a

contract for “construction and comprehensive modernization services at CMHA’s Millvale

2 OHIO FIRST DISTRICT COURT OF APPEALS

North Development – Phase II, Buildings[.]” Within this contract, CMHA delineated the

various aspects of Jindal’s obligations, including job responsibilities, payment, and the

period of performance, requiring Jindal to complete the project within 365 days from the

date established in the notice to proceed. Notably, nowhere within the contract did CMHA

condition Jindal’s start date on Phase II to the completion of Phase I units or mandate

Phase II residents relocate to Phase I units.

{¶4} The contract also incorporated several of the federal trappings ordinary to a

government construction contract, including the Housing and Urban Development (“HUD”)

general conditions for construction contracts awarded by public housing agencies. Relevant

to this appeal, section 30 of the general conditions allows a contractor to recover damages

for delays caused solely by the government-contracting officer—this section punctuated with

caveats addressed in more depth below. As will become apparent, this section assumes

significance since, after the parties signed the contract, a series of delays occurred resulting

in Jindal not starting work until months after the anticipated start date.

{¶5} In April 2016, just two months after signing the contract, CMHA issued a

notice to proceed, advising Jindal to begin work on April 18, 2016, and fixing the completion

date as July 26, 2017. But Jindal did not arrive at the Phase II work site, equipment in

hand, on April 18, and CMHA contends that both parties understood July 26 to be the true

start date. Consequently, April 18 came and went, with CMHA continuing to labor away on

Phase I until July 9 when CMHA discovered significant vandalism at those units. According

to CMHA, this threw a wrench in its plan, leaving the residents in Phase II unable to

decamp to Phase I until CMHA repaired and completed the Phase I units.

{¶6} As July 26 approached, Jindal’s project manager, Jeff Reams, reached out to

CMHA’s construction contract supervisor, Ronald Veley, on July 20 inquiring about the

3 OHIO FIRST DISTRICT COURT OF APPEALS

relocation of the Phase II residents. Mr. Veley optimistically, yet vaguely, responded that he

hoped to complete the other two buildings in Phase I by the next week, but failed to provide

an anticipated start date for Phase II. A few weeks elapsed, with Jindal still awaiting the

relocation of the Phase II residents and unable to begin its work. Growing ever more

concerned, Mr. Reams reached out again to CMHA, underscoring the urgency: “We bid this

project in early December 2015 with an anticipated spring 2016 start time and based our bid

numbers on that time frame. As of today August 16, 2016 we are still waiting on a start date

* * * causing time delays and extra cost to complete this project * * *. Please give us an

update on when we can expect to start this project so we can plan accordingly.” Reinforcing

this concern, Mr. Reams followed up on August 17 and 18, pleading with CMHA to provide a

start date, but to no avail—CMHA ignored these outreaches.

{¶7} Nearly a month passed before Mr. Reams and Anil Jindal, president of Jindal,

both simultaneously reached out to CMHA on September 12, begging for direction on when

the Phase II units would be vacated so Jindal could begin its work and emphasizing the

ramifications of this delay on Jindal’s billings and bond program. Again, based on the

record before us, CMHA offered nothing but silence as to the project’s status. Finally, on

October 17, CMHA informed Jindal that it vacated all Phase II units and Jindal therefore

could commence work. However, because Jindal had yet to acquire necessary permits for

the work, Jindal did not begin its work until November 10 (or November 17, a date later

claimed by Jindal).

{¶8} With the Phase II project finally underway, Jindal submitted various change

orders. The first of these arrived on December 2, 2016, with Jindal seeking an adjustment

for additional costs for the upcoming winter months (i.e., December, January, and

February) incurred because of the delay to the start of the project, which CMHA in turn

4 OHIO FIRST DISTRICT COURT OF APPEALS

denied. Jindal accordingly revised and resubmitted another change order on April 11, 2017,

this time pursuing, under section 30 of the contract, overhead damages suffered during the

delay between April and November 2016. A few weeks later, on April 29, Jindal revised the

change order one last time, seeking damages for the same time period in different amounts,

but this achieved the same result—CMHA denied both requests. In the wake of CMHA’s

Free access — add to your briefcase to read the full text and ask questions with AI

Related

N. Side Bank & Trust Co. v. Trinity Aviation, L.L.C.
2024 Ohio 590 (Ohio Court of Appeals, 2024)
Cagle v. Cagle
2022 Ohio 671 (Ohio Court of Appeals, 2022)
He v. Half Price Heating & Air
2021 Ohio 1599 (Ohio Court of Appeals, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
2020 Ohio 4043, 157 N.E.3d 279, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jindal-builders-restoration-corp-v-cincinnati-metro-hous-auth-ohioctapp-2020.