Mw Builders, Inc. v. United States

134 Fed. Cl. 469
United States Court of Federal Claims·Decided October 18, 2017·No. 13-1023 C·Published·Cited by 7 cases

Opinion

Anti-Deficiency Act, 31 U.S.C. § 1350; Breach of Contract; Contract Disputes Act, 41 U.S.C. §§ 7101-7109; Counterclaims, 28 U.S.C. § 2508; False Claims Act, 31 U.S.C. §§ 3729-3733; Federal Acquisition Regulation, 48 C.F.R. §§ 52.211-12 (Liquidated Damages), 52.242-14 (Suspension of Work), 52.’249-10 (Contract Default); Good Faith and Fair Dealing; Special Plea In Fraud, 28 U.S.C. § 2514; Tucker Act Jurisdiction, 28 U.S.C. § 1491; Unreasonable Delay; Waiver.

POST-TRIAL MEMORANDUM OPINION AND FINAL ORDER 1

SUSAN G. BRADEN, Chief Judge

This case concerns the United States Army Corps of Engineers (“Army Corps”) attempt to shift its contractual responsibility to make arrangements for permanent electrical utility services that MW Builders, Inc. (“MW Builders”) needed to build an Army Reserve Center in Sloan, Nevada. This imposed unnecessary construction delay and costs on MW Builders that the Contracting Officer (“CO”) refused to pay. When MW Builders filed a Complaint in the United States Court of Federal Claims, the Government alleged that the contractor’s claim was fraudulent.

As discussed herein, the court has determined that the Army Corps breached a September 10, 2010 Contract with MW Builders and violated the duty of good faith and fair dealing for which $418,961.90 is awarded, as compensable delay damages, together with statutory interest, The Government’s counterclaims for fraud are dismissed, but the Government’s affirmative defense of waiver concerning one of MW Builders’ subcontractors’ alleged pass-through claim is granted.

To facilitate review of this Post-Trial Memorandum Opinion And Final Order, the court has provided the following outline,

I.RELEVANT FACTUAL BACKGROUND.

A. In 2008, The United States Army Corps Of Engineers Began Designing An Army Reserve Center To Be Built In Sloan, Nevada.
B. On June 11, 2010, The United States Army Corps Of Engineers Issued Solicitation No. W912QR-09-R-0104Re-questing Proposals For A Firm, Fixed-Price Contract To Build The Army Reserve Center In Sloan, Nevada.
C. On September 10, 2010, The United States Army Corps Of Engineers Awarded Contract No. W912QR-10-C-0078To MW Builders, Inc.
D. On December 6, 2010, MW Builders, Inc. Entered Into A Subcontract With Bergelectric Corporation To Provide An Electrical System.
E. In 2011, MW Builders, Inc. Executed A Third Party Authorization Form And Design Approval Agreement With NV Energy.
F. In March 2012, MW Builders, Inc. And The United States Army Corps Of Engineers Had A Dispute Over The Execution Of A Line Extension Agreement With NV Energy.
G. On April 6, 2012, MW Builders, Inc. Notified The United States Army Corps Of Engineers That The Construction Schedule Would Be Delayed, Because The Line Extension Agreement With NV Energy Was Not Executed.
H. On April 19, 2012, The United States Army Corps Of Engineers Began To Negotiate A Line Extension Agreement With NV Energy.
I. On July 12, 2012, The United States Army Corps Of Engineers Signed A Line Extension Agreement With NV Energy.
J. On December 27, 2012, MW Builders, Inc. Submitted A Certified Claim To The Contracting Officer For Costs Incurred As A Result Of The United States Army Corps Of Engineers’ Failure To Timely Execute A Line Extension Agreement With NV Energy.
K. On June 10, 2013, The Contracting Officer Issued A Final Decision Denying MW Builders, Ine.’s Monetary Claim, But Granting A Non-Compen-sable Time Extension Of 146 Days For MW Builders, Inc. To Complete Construction Of The Army Reserve Center In Sloan, Nevada.
L. On December 13, 2013, The Completed Army Reserve Center in Sloan, Nevada Was Accepted By The United States Army Corps Of Engineers.

II. PROCEDURAL HISTORY.

III. DISCUSSION.

A. Subject Matter Jurisdiction.
B. Standing.
C. Plaintiffs Claims Against The Government.
1. The September 10, 2010 Contract Required The United States Army Corps Of Engineers To Sign The Line Extension Agreement With NV Energy.
a. Plaintiffs Argument.
b. The Government’s Response.
c. The Court’s Resolution.
i. The September 10, 2010 Contract Contains A Latent Ambiguity Regarding Which Party Was Responsible For Signing The Line Extension Agreement With NV Energy,
ii. Extrinsic Evidence Of Intent Demonstrates That The United States Army Corps Of Engineers Was Responsible For Signing The Line Extension Agreement With NV Energy.
2. The United States Army Corps Of Engineers Violated The Duty Of Good Faith And Fair Dealing Causing An Unreasonable Delay To The Project.
a. Plaintiffs Argument.
b. The Government’s Response.
c. Plaintiffs Reply.
d. The Government’s Sur-Reply.
e. The Court’s Resolution.
i. The United States Army Corps Of Engineers Violated The Duty Of Good Faith And Fair Dealing.
ii. The United States Army Corps Of Engineers’ Conduct Caused An Unreasonable Delay.
D. The Government’s Affirmative Defense And Counterclaims.
1. The Government’s Affirmative Defense Of Waiver.
a. The Government’s Argument.
b. Plaintiffs Response.

Free access — add to your briefcase to read the full text and ask questions with AI

Mw Builders, Inc. v. United States, 134 Fed. Cl. 469 (uscfc 2017).

134 Fed. Cl. 469 (Mw Builders, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related