Mw Builders, Inc. v. United States

CourtUnited States Court of Federal Claims
DecidedMarch 5, 2018
Docket13-1023
StatusPublished

This text of Mw Builders, Inc. v. United States (Mw Builders, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mw Builders, Inc. v. United States, (uscfc 2018).

Opinion

In the United States Court of Federal Claims No. 13-1023C Filed: March 5, 2018

**************************************** * * MW BUILDERS, INC. f/n/a/ * Rules Of The United States Court Of MW BUILDERS OF TEXAS, INC., * Federal Claims 52(b) (Amended Or * Additional Findings); 59(a) Plaintiff, * (Grounds For New Trial Or * Reconsideration; Further Action v. * After Trial); 59(e) (Motion To * Alter Or Amend Judgment); THE UNITED STATES, * Tucker Act Jurisdiction, 28 U.S.C. * § 1491 (2012). Defendant. * * * ****************************************

Paul Harvey Sanderford, Sanderford and Carroll, P.C., Temple, Texas, Counsel for Plaintiff.

Alexander Orlando Canizares, United States Department of Justice, Civil Division, Washington, D.C., Counsel for the Government.

MEMORANDUM OPINION AND ORDER DENYING PLAINTIFF’S MOTION FOR RECONSIDERATION

BRADEN, Chief Judge.

On September 29, 2017, the court issued a Post-Trial Memorandum Opinion And Final Order that granted partial judgment in favor of MW Builders, Inc. (“MW Builders”), but determined that the claims of MW Builders’ subcontractor, Bergelectric, were waived. See MW Builders, Inc. v. United States, 134 Fed. Cl. 469, 531 (Fed. Cl. 2017). On October 27, 2017, MW Builders filed a Motion For Reconsideration And To Alter Or Amend Judgment, pursuant to Rules of the United States Court of Federal Claims (“RCFC”) 52(b) and 59(a), requesting that the court reconsider the determination that Bergelectric’s pass-through claims were waived.1 ECF No. 141. Although a detailed factual history of this case can be found in the court’s September 29, 2017 1 The October 27, 2017 Motion For Reconsideration And To Alter Or Amend Judgment is captioned as one filed, pursuant to RCFC 59(e) and 52(b). RCFC 59(e) refers only to the timing for filing a motion to alter or amend a judgment. Because the October 27, 2017 Motion For Reconsideration And To Alter Or Amend Judgment cites RCFC 59(a), that governs motions for reconsideration, the court considers the motion as one for reconsideration or, in the alternative, to amend the judgment. Post-Trial Memorandum Opinion And Final Order, MW Builders, Inc., 134 Fed. Cl. at 476–88, the court provides a brief overview of the factual findings relevant to MW Builders’ Motion For Reconsideration And To Alter Or Amend Judgment, below.

I. BACKGROUND.

As discussed in the September 29, 2017 Post-Trial Memorandum Opinion And Final Order, MW Builders entered into a subcontract with Bergelectric to “provide a complete Electrical System in accordance with [the Contract] plans and specifications.” MW Builders, 134 Fed. Cl. at 479. The subcontract also required Bergelectric to provide temporary power to the project site, prior to the installation of permanent power. Id. (citing JX 9 at 14). To receive payment under the subcontract, Bergelectric was required to sign periodic lien waivers and releases and submit them to MW Builders, together with applications for payment. Id. (citing DX 124; TR 672).

The lien waivers and releases that Bergelectric signed and executed when it requested progress payments from MW Builders stated:

NOW, THEREFORE, effective as of receipt of the payment referenced in this Application, the undersigned [Bergelectric] irrevocably and unconditionally releases and waives any and all mechanic’s liens or other liens against the Realty or any other claims on any bonds or any other claims whatsoever in connection with this Contract and with the Realty through the end of the period covered by this Application, reserving however, all lien rights for materials and labor furnished or performed after said period and hold the Beneficiaries and their respective successors and assigns harmless against any lien, bond, claims or suits in connection with the materials, labor, and everything else in connection with this Contract, except with respect to the retainages to date, if any.

Id. at 511 (quoting DX 124 at 2) (emphasis added).

The lien waiver and release language, however, contains no express reservation authorizing Bergelectric to pass through claims for payment against the Government and Bergelectric signed waivers covering the entire period of permanent power delay, i.e., from March 13, 2012 to September 26, 2012. See id. (citing DX 124 at 2, 4, 6, 8, 10, 16, 18).

Therefore, in the September 29, 2017 Post-Trial Memorandum Opinion and Final Order, the court determined that the lien waivers contained a general release whereby Bergelectric “irrevocably and unconditionally” waived “any . . . claims whatsoever in connection with th[e] Contract” through the end of “the period covered by this Application.” Id. As a matter of law, the United States Court of Appeals for the Federal Circuit has held that, “absent special vitiating circumstances, a general release bars claims based upon events occurring prior to the date of the release.” Augustine Med., Inc. v. Progressive Dynamics, Inc., 194 F.3d 1367, 1373 (Fed. Cir. 1999). At trial, MW Builders and Bergelectric proffered extrinsic evidence to demonstrate that they did not intend to include the pass-through claims in the release. See MW Builders, 134 Fed. Cl. at 512. The court, however, did not consider the extrinsic evidence relevant in construing the release language. Id. (citing Augustine Med., 194 F.3d at 1373).

2 On reconsideration, MW Builders argues that the court’s determination that Bergelectric waived pass-through claims was “a manifest error,” because “the [c]ourt failed to consider the applicable case law requiring consideration of the evidence offered at trial regarding Bergelectric and MW Builders’ lack of intent to waive Bergelectric’s pass-through claim in the progress releases.” ECF No. 141 at 1.

II. STANDARD OF REVIEW.

Pursuant to RCFC 59, the court may reconsider and alter or amend its judgment, if the movant can show: (1) that there has been an intervening change in controlling law; (2) that previously unavailable evidence is now available; or (3) that the motion is necessary to prevent manifest injustice. See RCFC 59; see also Dairyland Power Co-op v. United States, 106 Fed. Cl. 102, 104 (Fed. Cl. 2012). A motion for reconsideration is not intended to give an “unhappy litigant an additional chance to sway” the court. See Matthews v. United States, 73 Fed. Cl. 524, 526 (Fed. Cl. 2006). Nor may a party prevail on such a motion by raising an issue for the first time on reconsideration, when the issue was ripe for adjudication at the time the complaint was filed. Id. Although the court has considerable discretion in ruling on a motion for reconsideration, granting relief requires “a showing of extraordinary circumstances.” Caldwell v. United States, 391 F.3d 1226, 1235 (Fed. Cir. 2004) (citation omitted), cert. denied, 546 U.S. 826 (2005); Yuba Natural Res., Inc. v. United States, 904 F.2d 1577, 1583 (Fed. Cir. 1990).

III. DISCUSSION.

A. MW Builders’ Argument.

MW Builders argues that the court’s reliance on Augustine is misplaced, because “that case was decided based on very different facts[,]” i.e., the parties in that case were disputing a settlement agreement. ECF No. 141 at 3–4. In this case, Bergelectric and MW Builders agree that the release language at issue “was never intended to bar Bergelectric’s pass-through claim, and the parties’ subsequent conduct validates that intent.” ECF No. 141 at 4. Therefore, the court should have considered the extrinsic evidence proffered by MW Builders and Bergelectric to demonstrate that the parties did not intend to waive Bergelectric’s pass-through claims. ECF No. 141 at 5–6.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Caldwell, Iii v. United States
391 F.3d 1226 (Federal Circuit, 2004)
Metric Constructors v. United States
314 F.3d 578 (Federal Circuit, 2002)
Barron Bancshares, Inc. v. United States
366 F.3d 1360 (Federal Circuit, 2004)
Colonial Navigation Company v. United States
181 F. Supp. 237 (Court of Claims, 1960)
NIPPON HODO COMPANY v. United States
160 F. Supp. 501 (Court of Claims, 1958)
Winn-Senter Const. Co. v. United States
75 F. Supp. 255 (Court of Claims, 1948)
Mw Builders, Inc. v. United States
134 Fed. Cl. 469 (Federal Claims, 2017)
George Hyman Construction Co. v. United States
39 Cont. Cas. Fed. 76,601 (Federal Claims, 1993)
Matthews v. United States
73 Fed. Cl. 524 (Federal Claims, 2006)
Dairyland Power Cooperative v. United States
106 Fed. Cl. 102 (Federal Claims, 2012)
L. W. Packard & Co. v. United States
66 Ct. Cl. 184 (Court of Claims, 1928)
E. W. Bliss Co. v. United States
70 Ct. Cl. 176 (Court of Claims, 1930)
Severin v. United States
99 Ct. Cl. 435 (Court of Claims, 1943)
J. G. Watts Construction Co. v. United States
161 Ct. Cl. 801 (Court of Claims, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
Mw Builders, Inc. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mw-builders-inc-v-united-states-uscfc-2018.