E. W. Bliss Co. v. United States

70 Ct. Cl. 176, 1930 U.S. Ct. Cl. LEXIS 427, 1930 WL 2461
CourtUnited States Court of Claims
DecidedJune 2, 1930
DocketNo. C-1032
StatusPublished
Cited by4 cases

This text of 70 Ct. Cl. 176 (E. W. Bliss Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E. W. Bliss Co. v. United States, 70 Ct. Cl. 176, 1930 U.S. Ct. Cl. LEXIS 427, 1930 WL 2461 (cc 1930).

Opinion

Booth, Chief Justice,

delivered the opinion of the court:

This case was before this court in 1926. Plaintiff’s petition was dismissed (61 C. Cls. 777). The Supreme Court on December 12, 1927 (275 U. S. 509, 510), reversed our judgment and remanded the case under the following order:

“ This court is of opinion that the Secretary of the Navy had authority to make further contracts to pay the petitioner the increased cost resulting’ from the wage increases put into effect at the Secretary’s instance, in the course of the petitioner’s performance of the original contracts, and that the findings of the Court of Claims show that such further contracts were made and were based upon an adequate consideration, consisting of both advantage to the Government and detriment to the petitioner. The findings on other points are not such as to enable this court finally to dispose of the case. Accordingly the judgment of the Court of Claims is reversed and the cause is remanded to that court with directions (1) to make further findings (a) as to whether the instruments of release express the actual intention of the parties in respect of a settlement or release of the petitioner’s claim for increased cost resulting from putting into effect the increased wages, or whether through mutual mistake, duress, or other sufficient ground for reformation the instruments of release were so drawn and signed that they failed to express the actual intention of the parties in that respect, and (b) as to what amount of increased cost to the petitioner resulted from the wage increases as respects work done under the original contracts after the wage increases took effect; (2) to make these findings from the evidence already taken and any additional evidence which the Court of Claims may deem it proper to receive; (8) to allow any amendments of the pleadings which may be needed to present the question whether the instruments of release should be reformed to express the actual intention of the parties in the particular herein named; and (4) to render such judgment in the cause as may be appropriate in view of the amended pleadings and the supplemented findings.
“The mandate herein shall issue forthwith.”

Subparagraph (a) of the foregoing order of remand is the one now in issue.

The plaintiff, a West Virginia corporation, during the years 1915, 1917, and 1918 entered into eight written contracts to manufacture and deliver to the Government a specified number of torpedoes. The contracts were per[194]*194formed by the plaintiff to the satisfaction of the Government, and this litigation involves seven releases executed by the plaintiff at the time final payments were made by the Government of the consideration expressed in the contracts. The contracts exacted the execution of final releases of all claims arising under the contracts before final payment would be made. While the plaintiff was engaged in performing the contracts an acute situation with reference to the wages and working conditions of mechanics and laborers engaged in Governnment work arose, due to war conditions. The War and Navy Departments adopted a policy designed to stabilize wages and remove all causes for discontent and deal justly with laborers and mechanics, either in the employment of Government contractors or directly with the departments. Not only the urgent necessities of the times but the inclination of the officials themselves required a course of action to meet the abnormal economic conditions then prevailing. The adopted policy, hereafter discussed somewhat in detail, embraced a programme of uniformity and provided a stabilized wage scale applicable in its provisions to both skilled and unskilled labor. Wages were increased, and through investigations made by appointed boards were put into effect to the extent of reaching Government contractors generally. The plaintiff, notwithstanding its protest against the adoption of the advanced wage scales, was required to put them into effect, did so, paid the higher wages, has received an admitted award from a duly constituted board of the department of $715,-200, and it is riot disputed that under the decisions of the Supreme Court in this case a contract to pay the same arose, is valid, and that the amount awarded is correct.

The sole defense to the suit is predicated upon the conclusive and binding effect of seven of the eight releases executed by the plaintiff when it received the final payments of the stipulated contract price. One clause in each of the contracts involved provides as follows:

“ * * * that from the last payment or payments becoming due thereunder there shall be reserved the sum of not less than five thousand dollars ($5,000.00), to be paid after the acceptance of the last lot of material and upon [195]*195the execution by the party of the first part of a release to the United .States, in such tenor and form as shall be approved by the Secretary of the Navy of claims against the party of the second part arising under or by virtue of said contract * *

.The seven releases relied upon, executed upon different dates, were in part as follows:

Now, therefore, in consideration of the premises and of the sum of six thousand five hundred three and 51/100 dollars ($6,503.51) lawful money of the United States, the amount of the final payment due under said contract, being to it in hand paid by the United States, represented by the Chief of the Bureau of Ordnance, the receipt whereof is hereby acknowledged, the E. W. Bliss Company does hereby, for itself, its successors and assigns and legal representatives, remise, release, and forever discharge the United States of and from all manner of debts, dues, sum and sums of money, accounts, reckonings, claims, and demands whatsoever, in law and in equity, for or by reason of or on account of the manufacture and delivery of torpedoes, appurtenances, and spare parts under the contract aforesaid, and does hereby further guarantee to fulfill and comply in all respects with the requirements of paragraph numbered seventy-nine (79) of the specifications annexed to and forming part of said contract.”

The eighth release, given under contract #1228, contained, in addition to the above provisions, the following proviso:

Provided, That this release shall not be taken to include claims arising under the said contract other than those which the Secretary of the Navy has jurisdiction to entertain.”

The plaintiff seeks a reformation of the seven releases, predicating its contention upon a mutual understanding and intent of the parties that at the time of their execution the parties did not contemplate or intend them to embrace a settlement of the plaintiff’s claim for extra wages paid its laborers under the department’s orders and contract; that through mutual mistake, as now worded, they do not express their designed and intended purpose, which was to limit the releases to simply a conclusive settlement of all sums, claims, etc., due or which might arise under the express terms of the contracts. It is evident from this as well as other cases of a similar character that the Navy [196]*196Department in formulating and adopting its policy of increased wages to laborers, whereby an additional expense was imposed upon contractors, had neither the authority, power, nor inclination to do so without reimbursement to contractors where reimbursement was due. (Electric Boat Co. v. United States, 66 C. Cls.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

George Hyman Construction Co. v. United States
39 Cont. Cas. Fed. 76,601 (Federal Claims, 1993)
J. G. Watts Construction Co. v. United States
161 Ct. Cl. 801 (Court of Claims, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
70 Ct. Cl. 176, 1930 U.S. Ct. Cl. LEXIS 427, 1930 WL 2461, Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-w-bliss-co-v-united-states-cc-1930.