H.L.C. & Associates Construction Company, Inc. v. The United States

367 F.2d 586, 176 Ct. Cl. 285, 1966 U.S. Ct. Cl. LEXIS 46
CourtUnited States Court of Claims
DecidedJune 10, 1966
Docket317-64
StatusPublished
Cited by49 cases

This text of 367 F.2d 586 (H.L.C. & Associates Construction Company, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H.L.C. & Associates Construction Company, Inc. v. The United States, 367 F.2d 586, 176 Ct. Cl. 285, 1966 U.S. Ct. Cl. LEXIS 46 (cc 1966).

Opinion

PER CURIAM *

On January 17,1961, plaintiff, a North Carolina corporation, entered into a contract with the Department of the Navy to construct a Capehart Act housing project of 450 units at Quantieo, Virginia. Pursuant to instructions from the Navy via the Federal Housing Administration (FHA), plaintiff caused the site to be divided into three mortgage areas, each of which was given a separate FHA project number and which became known as mortgage areas A, B, and C. Each of the projects was to be financed by a separate loan, and the contract contained a specific clause for the “severability of contract as to each project.” 1

Tenants were expected to furnish their own air-conditioning appliances. Some of these appliances operate on 110 volts; others operate on 220 volts. The contract specifications, anticipating the need for flexibility, called for 3-wire conductors to the air-conditioning outlets.

Throughout mortgage area C, the first segment to be completed, the electrical subcontractor installed 2-wire conductors and was proceeding with the same wiring in areas A and B when, on May 18, 1962, a tenant in area C connected a 110-volt appliance to a 220-volt receptacle and blew a fuse. The contracting officer thereupon required plaintiff to replace all 2-wire conductors in mortgage areas A and B with 3-wire conductors. The subcontractor complied with the order at some extra expense for tearing out and replacing finished surfaces and wire.

Plaintiff presented a claim to the contracting officer for an equitable adjustment for a change under the changes article of the contract and, when this was denied, pursued its administrative remedy before the Armed Services Board of Contract Appeals (ASBCA) under the disputes clause.

Meanwhile, plaintiff had executed a release and received final payment for mortgage area C, and while his administrative appeal was pending, likewise executed separate releases as to mortgage areas B and A, in that order.

When the appeal came before the AS-BCA, the contracting agency pleaded the releases in bar of plaintiff’s claim; the ASBCA upheld the plea as to both mortgage areas; and noted its further conclusion that the claim was without merit.

Plaintiff thereupon filed the present action as a claim “on behalf of and for the benefit of its subcontractors” for an alleged breach of contract resulting from *588 the refusal of the contracting officer to grant an equitable adjustment under the changes article as for a change inherent in the replacement of 2-wire conductors with 3-wire conductors, pleading that— * * * in * * * refusing to

recognize petitioner’s interpretation of the contract as reasonable, and in holding that the claim was barred by releases, the Board’s decision was not supported by substantial evidence and was arbitrary, capricious, and so grossly erroneous as to necessarily imply bad faith.

In its answer to plaintiff’s petition, defendant denied substantially all of the material allegations and asserted four complete affirmative defenses and a fifth, partial affirmative defense, as follows:

(1) That the decision of the ASBCA is final, conclusive, and binding.

(2) That the claims asserted in the petition are barred by releases.

(3) That there was no privity of contract between the subcontractor and defendant, wherefore the court lacks jurisdiction to adjudicate the claim.

(4) That plaintiff is not the real party in interest.

(5) That if plaintiff be deemed entitled to recover, the amount may not exceed $17,600, because of the statutory ceiling imposed by the Capehart Act.

Three months after filing its answer, defendant moved for summary judgment, asserting that “there is no genuine issue of material fact.” Plaintiff duly responded with its opposition to defendant’s motion and its cross motion for summary judgment, likewise asserting that “there is no genuine issue of material fact.” Defendant has replied to plaintiff’s opposition and cross motion.

With its initial motion for summary judgment, defendant filed the documentary record of the appeal before the AS-BCA, which the plaintiff “adopts” in its opposition and cross motion. 2

The issues in the case are (1) whether the releases executed by plaintiff operate as a bar to its claim with respect to mortgage area B or mortgage area A or both; and (2) if the claim is not so barred as to either or both, whether the wiring claim is meritorious as to the area or areas not released.

I

The contract contained the following provision: 3

Upon completion and acceptance of all work required hereunder, the amounts due the eligible builder under this Housing Contract from mortgage proceeds will be paid by the respective mortgagor-builders. Final amounts shall be payable after the eligible builder shall have furnished such mortgagor-builders and the Department with a release, if required, of all claims against the Department and/or such mortgagor-builders arising under and by virtue of this Housing Contract, other than such claims, if any, as may be specifically excepted by the eligible builder from the operation of the release in amounts stated therein. * * *

On March 1, 1962, plaintiff executed the following release concerning area C:

The work * * * having been satisfactorily completed and accepted * * * the undersigned hereby remise, release and forever discharge the United States * * * of and from any and all claims and demands whatsoever arising out of or by virtue of said contract except as follows: See Exhibit “A”.

Exhibit “A” summarized the terms of an escrow agreement for delayed completion of specified items not here material. *589 Since defendant did not require the contractor to make corrections of the wiring in area C, that area is not in controversy in this action.

On July 9, 1962, the contracting officer denied plaintiff’s claim for an equitable adjustment on account of the wiring replacements in mortgage areas A and B.

On July 30, 1962, plaintiff executed a release as to mortgage area B which was in all respects identical to its release of mortgage area C, except for minor variations in the reservation of escrow claims for delayed completion.

On August 1, 1962, plaintiff appealed the contracting officer’s decision of July 9 to the ASBCA.

On August 30, 1962, plaintiff executed a release concerning mortgage area A which was identical to the other releases except as to the reservations in Exhibit “A”.

Exhibit “A” attached to the foregoing release contained the following reservation : 4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JAAAT Technical Services, LLC
Armed Services Board of Contract Appeals, 2021
Cubic Defense Applications, Inc.
Armed Services Board of Contract Appeals, 2018
Ingham Regional Medical Center v. United States
126 Fed. Cl. 1 (Federal Claims, 2016)
Dick Pacific Construction Co., Ltd.
Armed Services Board of Contract Appeals, 2015
Imprimis Investors LLC v. United States
83 Fed. Cl. 46 (Federal Claims, 2008)
Metric Construction Co. v. United States
81 Fed. Cl. 804 (Federal Claims, 2008)
Smart Business Machines v. United States
72 Fed. Cl. 706 (Federal Claims, 2006)
Turner Construction Co. v. United States
54 Fed. Cl. 388 (Federal Claims, 2002)
Cavalier Clothes, Inc. v. United States
51 Fed. Cl. 399 (Federal Claims, 2001)
Northrop Grumman Corp. v. United States
47 Fed. Cl. 20 (Federal Claims, 2000)
Fort Myer Construction Corp. v. United States
43 Cont. Cas. Fed. 77,425 (Federal Claims, 1999)
SIPCO Services & Marine Inc. v. United States
42 Cont. Cas. Fed. 77,277 (Federal Claims, 1998)
Blinderman Construction Co. v. United States
42 Cont. Cas. Fed. 77,210 (Federal Claims, 1997)
Kenbridge Construction Co. v. United States
39 Cont. Cas. Fed. 76,549 (Federal Claims, 1993)
Elastomeric Roofing Associates, Inc. v. United States
26 Cl. Ct. 1106 (Court of Claims, 1992)
Granite Construction Company v. The United States
962 F.2d 998 (Federal Circuit, 1992)
Granite Construction Co. v. United States
37 Cont. Cas. Fed. 76,080 (Court of Claims, 1991)
Transtechnology Corp. v. United States
36 Cont. Cas. Fed. 75,953 (Court of Claims, 1990)
Troise v. United States
36 Cont. Cas. Fed. 75,904 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
367 F.2d 586, 176 Ct. Cl. 285, 1966 U.S. Ct. Cl. LEXIS 46, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hlc-associates-construction-company-inc-v-the-united-states-cc-1966.