Granite Construction Co. v. United States

37 Cont. Cas. Fed. 76,240, 24 Cl. Ct. 735, 1991 U.S. Claims LEXIS 584, 1991 WL 273649
United States Court of Claims·Decided December 18, 1991·No. No. 601-86C·Published·Cited by 5 cases

Opinion

OPINION

BRUGGINK, Judge.

This is an action brought pursuant to the Contract Disputes Act of 1978.1 Plaintiff, Granite Construction Co., seeks an equitable adjustment based on an asserted Type I or Type II differing site condition, on failure to disclose superior knowledge about the difficulty of doing the work, and on improper acceleration of the work. At the conclusion of plaintiff’s trial presentation, the court granted a motion pursuant to RUSCC 41(b) as to the Type I and Type II differing site condition claims, and denied the motion in other respects. The reasons for granting the motion were stated on the record. After the conclusion of trial presentation, and for the reasons set out below, the court concludes that the plaintiff is not entitled to recover on its claims of superior knowledge and acceleration.

BACKGROUND FACTS AND PROCEDURAL HISTORY

The subject of the litigation is Granite’s construction of a salmon fingerling bypass in the John Day Dam, an existing dam on the Columbia River. The river historically has supported a large migratory run of salmon. With the construction of a series of dams along the Columbia and its tributaries by the U.S. Army Corps of Engineers (“Corps”) and the Bureau of Reclamation, salmon fingerling mortality rose as they were required to pass over spillways or through turbines as they traveled downstream.

In an effort to reduce fingerling mortality, the Corps and others began to develop plans for various bypass systems to be incorporated into new dams being constructed and retrofitted into existing dams. These bypass systems were intended to divert the fingerlings from powerhouse intakes and direct them into a bypass tunnel and outfall sluice leading back to the river below the dam.

The John Day Dam is a multipurpose facility that is comprised of, among other things, a powerplant, non-overflow portions, a series of service, powerhouse and skeleton bays, a spillway, a navigation lock, and fish passage facilities. The service and powerhouse bays are composed of mass concrete. There are expansion joints between each of the bays, at intervals of approximately 90 feet.

A fingerling bypass tunnel, comprised of a steel conduit, was incorporated into the John Day Dam when it was built, but experience revealed that it was ineffective. As a replacement for the original system, the Corps determined to pursue the project at issue, which was a barrier screen system that diverted fingerlings from powerhouse intakes toward orifices leading to a transportation conduit and outfall sluice that returned them to the river below the dam. The transportation conduit portion of the project required the excavation of a tunnel through the mass concrete of John Day Dam.

The present litigation arises out of a contract between the United States, acting through the Corps, and Granite for the construction of this bypass system. The contract was awarded on January 5, 1984 in the amount of $7,898,465.00. There were four principal items of work: vertical barrier screens and guides, excavation and lining of the transportation conduit, outfall chute, and evaluation facility for a juvenile bypass.

The dispute concerns only one element of this work, the transportation conduit. Approximately 1000 feet of this tunnel had to be excavated out of the existing mass concrete that comprises, principally, the nine [737] bays of the dam. The tunnel was not uniform in shape. The profile was rectangular, but the floor sloped down to the north end to induce water flow, and the squared sides tapered from north to south. Not including the wedge added by the sloping floor, the shape at the large end was approximately ten feet (high) by twelve feet.

The tunnel thus went through the length of the dam, perpendicular to the flow of the river. At several points along the roof of the tunnel small holes were to be punched through to the gate slots. Fish would be attracted to the holes by light, and then would be drawn to the tunnel and then through a separate, much shorter tunnel that had to be excavated through monolith 14, to the outfall chute and eventually to the river below.

In order to provide a proper chronological background for Granite’s claim of superior knowledge, the discussion has to be diverted to a prior Corps project. The Walla Walla District of the Corps in July of 1978 contracted with S.J. Groves and Sons Company (“Groves”) to construct a fingerling bypass system at the existing Little Goose Dam along the Snake River in Washington. This project, in part, called for the excavation of a tunnel through mass concrete. Groves attempted to complete at least part of the tunnel excavation at Little Goose Dam with a machine called a road-header. This is a large piece of mining equipment which uses a rotating cutting head, attached to a long arm. In bidding the Little Goose project, Groves proposed to use an Alpine Equipment Company Model F16 roadheader, weighing 40,000 pounds. However, in performing the work, Groves actually attempted to excavate the tunnel with a modified Alpine Model F6A, weighing about 26,400 pounds.

The specifications for the Little Goose work contained the following paragraph:

1.3 The existing concrete in the path of mining may be expected to range in strength from about 3000 psi to over 8000 psi. Maximum coarse aggregate size is approximately 3 inches. Additional information on the existing concrete can be found in the publication ‘Report of Concrete Operations and Tests, Little Goose Dam’, available for review from the Army Corps of Engineers District Office in Walla Walla, Washington. It is expressly understood that interpretations, conclusions and deductions made on the basis of this report are solely the responsibility of the Bidder.

Contrary to the specification, Groves in fact encountered substantial quantities of coarse aggregate or cobble ranging in size up to six inches or more. The F6A initially put on the project proved to be totally inadequate. It was modified with a larger cutting arm, cutting head, and cutting head motor. Although it was eventually able to excavate a substantial part of the tunnel, its performance was not considered to be satisfactory. Groves submitted a differing site condition claim to the Corps, asserting that its difficulties in excavating the tunnel were attributable to the presence of significant quantities of six-inch aggregate in the mass concrete when the contract specifications indicated that the maximum aggregate size would be only three inches.

By letter dated February 28, 1979 the Corps’ Contracting Officer (“CO”) issued a final decision denying Groves’ differing site conditions claim upon the ground that its difficulties were attributable to the inadequacies of the modified F6A Alpine road-header. The Corps took the position, based in part on expert reports prepared for it and attached to the decision, that the size of the aggregate was not a factor in the difficulty of the work. The CO final decision reflects that the Alpine roadheader was frequently not operating; that it milled2 the concrete when it did operate; [738] and that the machine was ultimately pulled out and the work completed by hand-mining techniques. The matter was ultimately tried before the Armed Services Board of Contract Appeals, and, based on the trial judge’s indication that Groves’ claim was valid, the parties settled.

Free access — add to your briefcase to read the full text and ask questions with AI

Granite Construction Co. v. United States, 37 Cont. Cas. Fed. 76,240, 24 Cl. Ct. 735, 1991 U.S. Claims LEXIS 584, 1991 WL 273649 (cc 1991).

37 Cont. Cas. Fed. 76,240 (Granite Construction Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Caddell Construction Co. v. United States
78 Fed. Cl. 406 (Federal Claims, 2007)
Daewoo Engineering & Construction Co. v. United States
73 Fed. Cl. 547 (Federal Claims, 2006)
Northrop Grumman Corp. v. United States
63 Fed. Cl. 12 (Federal Claims, 2004)
TLT Construction Corp. v. United States
60 Fed. Cl. 187 (Federal Claims, 2004)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)