P.J. Maffei Building Wrecking Corporation v. The United States

732 F.2d 913, 32 Cont. Cas. Fed. 72,426, 5 Cl. Ct. 913, 1984 U.S. App. LEXIS 15001
CourtCourt of Appeals for the Federal Circuit
DecidedApril 19, 1984
DocketAppeal 83-1228
StatusPublished
Cited by167 cases

This text of 732 F.2d 913 (P.J. Maffei Building Wrecking Corporation v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P.J. Maffei Building Wrecking Corporation v. The United States, 732 F.2d 913, 32 Cont. Cas. Fed. 72,426, 5 Cl. Ct. 913, 1984 U.S. App. LEXIS 15001 (Fed. Cir. 1984).

Opinion

DAVIS, Circuit Judge.

This appeal is from a decision of the United States Claims Court, granting summary judgment for the appellee, the United States (the Government), and dismissing appellant P.J. Maffei Building Wrecking Corporation’s (Maffei’s) claim that the General Services Board of Contract Appeals (the Board) incorrectly held that Maffei was not entitled to an equitable adjustment for a shortfall of salvageable steel in its demolition contract with the Government. 1 We affirm, but partially for different reasons than those advanced by the Claims Court.

I

In June 1976 the Government issued an Invitation for Bids (IFB) for the demolition and removal of the United States Pavilion (and restoration of the grounds) in Flushing Meadow Park, New York. The Pavilion had been built for the 1964 World’s Fair. The IFB advised prospective contractors that the salvage value of the construction materials to be removed from the project site should be reflected in the bids, because those materials would become the property of the contractor. This appeal primarily concerns the proper construction and application of another IFB provision, found in the Special Conditions section:

1.2 Some drawings of some of the existing conditions are available for examination at the New York City Parks Department’s Administration Building at Flushing Meadow Park, Flushing, New York. These drawings are for information only and will not be part of the contract documents. The quantity, quality, complete *915 ness, accuracy and availability of these drawings are not guaranteed. Prospective bidders shall telephone Mr. S. Dubowy or Mr. S. Adler of the New York City Parks Department, at 212-699-4288, for an appointment to examine drawings of the existing conditions.

Maffei’s estimator, Laurence Brady, Jr., visited the site, reviewed drawings he obtained from a man named “Charlie” at the Parks Department, consulted a “steel book,” 2 and subsequently arrived at a bid based on his estimate of the amount of salvageable steel in the Pavilion. On October 7, 1976, the Government awarded Maffei the demolition contract.

Maffei recovered 1,075 tons of steel less (approximately 20%) than it had estimated it would salvage from the project. Contending that the Government owed it compensation for the shortfall under the Differing Site Conditions clause of its contract, Maffei submitted a claim to the Government for an equitable adjustment of the contract price. The Differing Site Conditions clause provides:

The Contractor shall promptly, and before such conditions are disturbed, notify the Contracting Officer in writing of: (1) Subsurface or latest [sic for latent] physical conditions at the site differing materially from those indicated in this contract, or (2) unknown physical conditions at the site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in this contract. 3 The Contracting Officer shall promptly investigate the conditions, and if he finds that such conditions do materially so differ and cause an increase or decrease in the Contractor’s cost of, or the time required for, performance of any part of the work under this contract, whether or not changed as a result of such conditions, an equitable adjustment shall be made and the contract modified in writing accordingly. (Emphasis added.)

The contracting officer denied Maffei’s claim on the ground that the Government had explicitly excluded the drawings upon which Maffei allegedly relied from the contract’s coverage and disclaimed their accuracy. See IFB provision 1.2, supra. He also said that the IFB required that prospective contractors estimate salvageable structural steel through on-site inspection and examination.

On appeal, the General Services Board of Contract Appeals affirmed the contracting officer’s denial of Maffei’s claim for an equitable adjustment for the steel shortfall. PJ. Maffei Building Wrecking Corporation, 80-2 B.C.A. (CCH) If 14,647 (August 1980). It decided that the contract contained no “indication” of the amount of steel in the Pavilion. The Board said:

... the contract provided the appellant with no information or estimate of the type or quantity of steel in the building. The Government was aware that some drawings pertaining to the structural steel were available at the Parks Department. The drawings were to serve as a source for providing potential bidders with leads to more reliable information, such as the as-built drawings or the contractor who installed the steel.

Id., at 72,259. The Board also held against Maffei on its claim that the Government had misrepresented by withholding pertinent information.

In 1981 Maffei sought review of the Board’s decision on these claims in the then United States Court of Claims under the Wunderlich Act, 41 U.S.C. §§ 321-322 (1976). 4 On October 1, 1982, the case was *916 transferred to the United States Claims Court by the Federal Courts Improvement Act of 1982, Pub.L. No. 97-164, 96 Stat. 25 (April 2, 1982). Both Maffei and the Government moved for summary judgment.

The Claims Court granted the Government’s cross-motion for summary judgment and dismissed Maffei’s claims. Although the court upheld the Board’s determination, it did so on the basis that Maffei had not shown that it actually relied on the information shown in the drawings. In contrast to the Board, the Claims Court ruled that the Government’s reference to the drawings in the IFB was sufficient to satisfy the requirement of a “contract indication” under the Differing Site Conditions clause. That reference, however, did not amount to a misrepresentation (in the Claims Court’s view) because it came replete with caveats. The Claims Court also found, like the Board, that Maffei had failed to show that the Government concealed any information. P.J. Maffei Building Wrecking Corp. v. United States, 3 Cl.Ct. 482 (1983).

II

We uphold the Claims Court’s grant of summary judgment for the Government and dismissal of Maffei’s claim for an equitable adjustment of the contract price. The ground for our decision, however, is the position rejected by the Claims Court. Unlike that court, we agree with the Board that the contract documents did not “indicate” the amount of steel recoverable from the Pavilion, within the meaning of the Differing Site Conditions clause. We also decide (as did the Claims Court) that Maffei failed to show that the Government misrepresented conditions at the Pavilion or that it possessed pertinent information regarding the Pavilion steel structure which it concealed.

Differing Site Conditions Claim

Success on a Type I Differing Site Conditions claim 5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meltech Corporation, Inc.
Armed Services Board of Contract Appeals, 2025
BCI Construction USA, Inc.
Armed Services Board of Contract Appeals, 2024
Hamp's Construction LLC
Armed Services Board of Contract Appeals, 2024
Trident Engineering & Procurement, P.C.
Armed Services Board of Contract Appeals, 2023
JAAAT Technical Services, LLC
Armed Services Board of Contract Appeals, 2021
APTIM Federal Services, LLC
Armed Services Board of Contract Appeals, 2020
Tidewater, Inc.
Armed Services Board of Contract Appeals, 2018
R.L. Persons Construction, Inc.
Armed Services Board of Contract Appeals, 2018
Asi Constructors, Inc. v. United States
129 Fed. Cl. 707 (Federal Claims, 2016)
Columbia State Bank (formerly Appeal of Castle-Rose, Inc.)
Armed Services Board of Contract Appeals, 2016
Precision Standard, Inc.
Armed Services Board of Contract Appeals, 2015
Old Veteran Construction, Inc. v. United States
121 Fed. Cl. 346 (Federal Claims, 2015)
Optimum Services, Inc.
Armed Services Board of Contract Appeals, 2015
Aegis Defence Services Ltd.
Armed Services Board of Contract Appeals, 2014
PBS&J Constructors, Inc.
Armed Services Board of Contract Appeals, 2014
weston/bean Joint Venture v. United States
115 Fed. Cl. 215 (Federal Claims, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
732 F.2d 913, 32 Cont. Cas. Fed. 72,426, 5 Cl. Ct. 913, 1984 U.S. App. LEXIS 15001, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pj-maffei-building-wrecking-corporation-v-the-united-states-cafc-1984.