Meltech Corporation, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJuly 16, 2025
Docket61766, 61767, 61872
StatusPublished

This text of Meltech Corporation, Inc. (Meltech Corporation, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meltech Corporation, Inc., (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of - ) ) Meltech Corporation, Inc. ) ASBCA Nos. 61766, 61767, 61872 ) Under Contract No. W912DR-14-D-0021 )

APPEARANCES FOR THE APPELLANT: Leonard A. Sacks, Esq. Leonard A. Sacks & Associates, P.C. Rockville, MD

Fred A. Mendicino, Esq. Faughnan Mendicino PLLC Dulles, VA APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Adam J. Kwiatkowski, Esq. Engineer Trial Attorney U.S. Army Engineer District, Baltimore

OPINION BY ADMINISTRATIVE JUDGE CATES-HARMAN

These appeals are consolidated with fifteen (15) other appeals. 1 A previous decision was issued on summary judgment and cross-motions for summary judgment denying entitlement in ASBCA Nos. 61706 and 61768 (see Meltech Corp., ASBCA Nos. 61706, 61768, 22-1 BCA ¶ 38,117, aff’d 2023 WL 4503517 (Fed. Cir.)). This decision addresses entitlement in ASBCA Nos. 61766, 61767 and 61872. The disputes involve a United States Army Corps of Engineers (USACE) Multiple Award Task Order contract that included both Design-Build and Design-Bid-Build construction projects within the Baltimore District Area of Responsibility, including the renovation of Building 8609 at Fort Meade, MD. The Board has jurisdiction to hear these appeals pursuant to the Contract Disputes Act of 1978, 41 U.S.C. § 7105. We will address each of the three appeals separately. For the reasons stated below, we deny ASBCA No. 61766 (emergency lighting) and find for the appellant in ASBCA No. 61872 (day room shelf) and ASBCA No. 61767 (heat trace).

FINDINGS OF FACT

1 ASBCA Nos. 61766, 61767, and 61872 are consolidated with ASBCA Nos. 61694, 61706, 61762, 61763, 61764, 61765, 61768, 61869, 61870, 61871, 62091, 62987. The lead appeal is ASBCA No. 61694. (A decision on summary judgment resolved ASBCA Nos. 61706 and 61768). Contract and Task Order

1. On June 10, 2014, USACE issued a Request for Proposals (RFP) for a Multiple Award Task Order Contract (MATOC) that included design-build and design-bid-build construction projects within the Baltimore District area of Responsibility. This was Phase 1 of a two-phase construction procurement. (Joint Stipulations of Fact (JSOF) ¶ 1 at 1; R4, tab 2)

2. The MATOC included renovating several similar dormitory buildings at Fort Meade, including Building 8609 (JSOF ¶ 3 at 1).

3. Building 8609 is an approximately 39,000 square foot barracks facility built in 1954 “that is in need of major repairs and code compliance of major systems” as the building and systems were beyond serviceable life (app supp. R4, tab 351 at 4).

4. Previously, on May 15, 2014, USACE had contracted with Black and Veatch (B-V) (Contract No. W912DR 10 D 0018), to prepare “a partial criteria Design-Build Request for Proposal” package for the renovation of Building 8609, including barracks room renovation, bathroom renovation, hallway renovation, and sprinkler system (app supp. R4, tab 351 at 1, 4-5). The scope of B-V’s work was to “[d]evelop performance criteria for all design disciplines for the Request for Proposal [] Design-Build Package. Use tables, text, sketches, drawings and others to illustrate the performance criteria” and to “[i]dentify any work to be done by others for such items as furniture, equipment, utility connections (water, sanitary sewer, gas, electric, and telephone). . .” (App supp. R4, tab 351 at 6)

5. B-V’s contract with USACE required it to perform a field investigation of Building 8609, provide a structural analysis, and “provide all necessary services required for the preparation of a complete and biddable RFP Design-Build Package” (app supp. R4, tab 351 at 5, 7). B-V’s contract described the field investigation as, “The A-E shall . . . [v]isit the project site to determine existing and planned future conditions affecting the RFP. A-E will immediately advise the DM if any . . . situations are observed during the field investigations.” (App supp. R4, tab 351 at 11) B-V was to review drawings, “[d]etermine visible relevant exiting conditions not available on existing as-built drawings” and to “[i]ndicate presumed existing hidden conditions and include verification in the design-build RFP” (app supp. R4, tab 351 at 12). With respect to the final design-build RFP submittal by B-V, the contract provided that “[t]he level of detail shall reflect both prescriptive and performance requirements for the project” and include “as-built drawings showing existing conditions including any drawings for demolition . . . and necessary drawings, results of the field investigation . . . and the structural analysis” (app supp. R4, tab 351 at 12).

2 6. USACE’s Design Criteria for the MATOC RFP, , describe the renovation of Building 8609 as:

Building 8609 is a 38,490 SF three story, permanent barracks with a hammerhead shaped one story portion housing the main entry and administrative/community functions. The building was constructed circa 1955. The building was last renovated in 1975 when individual rooms and air conditioning were added. In 1982, the windows were replaced but do not meet current Anti-Terrorism Force Protection (AT/FP) requirements. Only limited maintenance and repair work has occurred since. The mechanical, plumbing and electrical systems are to be replaced. The roofs are to be replaced with a sloped, gabled roof assembly. Exterior walls are to be retrofitted or replaced with a complete brick veneer façade and masonry veneer base. New windows are to be installed throughout. The building envelope must prohibit water infiltration and mold must be remediated.

(R4, tab 2 at 1, tab 3 at 7)

7. Section 00100 of the Proposal Submission Requirements states that “The Contractor will provide all design, management, supervision, labor, materials, tools, and equipment necessary for the performance of the work. Task orders may be either Design-Build or Design-Bid-Build.” (R4, tab 2 at 5)

8. On August 14, 2014, USACE issued Amendment 0003 to RFP W912DR- 14-R-0003 for two seed projects under the MATOC to provide Design Criteria for the Design-Build renovation of Building 8609 at Fort Meade and Building 4501 at Aberdeen Proving Ground. Each task order was to be awarded separately. (JSOF ¶ 7 at 2)

9. USACE scheduled a pre-bid site visit for bidders to walk through Building 8609 on August 14, 2014 (R4, tab 355 at 1, 3).

10. On September 15, 2014, Meltech submitted its technical and cost proposals for the renovation of Building 8609. Meltech’s proposal included a preliminary schedule. According to this schedule, the design period would begin on November 18, 2014, and end on June 4, 2015. The construction period would begin on May 29, 2015, and end on April 26, 2016. (JSOF ¶¶ 11-12 at 2)

3 11. On September 29, 2014, USACE awarded Meltech Base Contract No. W912DR-14-D-0021. On September 30, 2014, USACE awarded Task Order Contract No. 0002 to Meltech for the renovation of Building 8609. CLIN 0002 included the renovation of Building 8609 and “[a]ll costs in connection with construction of the [Building] 8609 . . . complete as specified in this Request for Proposal [], and in accordance with approved design documents prepared by the Contractor” (R4, tab 7 at 1-2). The Task Order Contract provided Meltech with a 540-calendar day performance period beginning from the Notice to Proceed date. The Notice to Proceed was issued on November 17, 2014, and the original completion date was May 10, 2016. (JSOF ¶¶ 13-16 at 2-3)

Relevant Contract Clauses and Design Criteria Specifications

12.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Atlantic Dredging Co.
253 U.S. 1 (Supreme Court, 1920)
Hol-Gar Manufacturing Corp. v. The United States
351 F.2d 972 (Court of Claims, 1965)
Zinger Construction Co., Inc. v. The United States
807 F.2d 979 (Federal Circuit, 1986)
Stuyvesant Dredging Company v. The United States
834 F.2d 1576 (Federal Circuit, 1987)
Comtrol, Inc. v. United States
294 F.3d 1357 (Federal Circuit, 2002)
Ragonese v. United States
120 F. Supp. 768 (Court of Claims, 1954)
Lakeshore Engineering Services, Inc. v. United States
748 F.3d 1341 (Federal Circuit, 2014)
Neal & Co. v. United States
41 Cont. Cas. Fed. 77,003 (Federal Claims, 1996)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
Gulf & Western Industries, Inc. v. United States
32 Cont. Cas. Fed. 73,100 (Court of Claims, 1984)
H.H.O. Co. v. United States
34 Cont. Cas. Fed. 75,256 (Court of Claims, 1987)
Big Chief Drilling Co. v. United States
15 Cl. Ct. 295 (Court of Claims, 1988)
Ragonese & Scaravelli v. United States
120 F. Supp. 768 (Court of Claims, 1954)
S.T.G. Construction Co. v. United States
157 Ct. Cl. 409 (Court of Claims, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
Meltech Corporation, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/meltech-corporation-inc-asbca-2025.