Nager Electric Company, Inc. And Keystone Engineering Corporation v. The United States

442 F.2d 936, 194 Ct. Cl. 835, 1971 U.S. Ct. Cl. LEXIS 127
CourtUnited States Court of Claims
DecidedMay 14, 1971
Docket348-64
StatusPublished
Cited by37 cases

This text of 442 F.2d 936 (Nager Electric Company, Inc. And Keystone Engineering Corporation v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nager Electric Company, Inc. And Keystone Engineering Corporation v. The United States, 442 F.2d 936, 194 Ct. Cl. 835, 1971 U.S. Ct. Cl. LEXIS 127 (cc 1971).

Opinion

PER CURIAM *

The basic facts and circumstances giving rise to this case are well known since on the lengthy road it has traveled to a merits determination after suit was instituted in this court by a petition filed on October 16, 1964, the case has been the subject of two Court of Claims decisions. 1

I

Preliminary Statement Outlining General Facts and Present Posture of Case

In view of the above, the facts in the ease will be restated in general terms only to the extent considered necessary for convenient reference in examining the matters now presented for review. It is sufficient to say at this point that the controversies between the parties arise out of a contract, No. AT (30-3)-260, entered into by plaintiffs (usually referred to in the administrative decisions under review here, and hereinafter sometimes referred to, as “Nager”), as joint venturers, and defendant, acting by and through the Atomic Energy Commission (hereinafter the “AEC” or the “Commission”), dated and executed October 16, 1956, for construction of a certain facility known and designated as “Second Phase Facility Construction, Project S3G,” at the Knolls Atomic Power Laboratory near West Milton, New York. The initial total base contract price was $2,195,000; but by five certain amendments, this amount was increased 2 A Notice to Proceed was issued to plaintiffs on October 30, 1956, the registered mail receipt therefor being signed on October 30, 1956. In due course, plaintiffs proceeded with contract performance and, thereafter, the disputes leading to this suit developed.

Plaintiffs’ petition (original and amended) asserts three causes of action, and the defendant’s answer (original and amended) asserts a counterclaim. Pur *939 suant to the previous decisions of this court, particularly its 1968 decision (n. 1), plaintiffs’ first cause of action, a breach of contract claim for improper partial termination and subsequent contract price reduction of $18,218, was severed for separate trial by order of the trial commissioner filed June 28, 1968, and said cause of action is not the direct subject of this opinion. The concern here is with plaintiffs’ motion and defendant’s cross-motion for summary judgment, and defendant’s counterclaim, regarding plaintiffs’ second and third causes of action, and a review, under Wunderlich Act 3 standards, of decisions made by the AEC with respect to two claims underlying said causes of action. 4

In brief, plaintiffs’ second cause of action arises from deductive Change Order No. 8, Addendum 4, issued April 12, 1957, which substituted a less expensive type and smaller number of emergency shutdown valves for those originally required by the contract specifications. Plaintiffs challenge the $170,796 Government credit for the deleted valves determined by the contracting officer and whose decision was sustained by the Commission below. Plaintiffs argue that no more than $45,168.35 (which would result in a net additional compensation to plaintiffs in the amount of $41,702.33), the price quoted for the original valves by the plaintiffs’ sub-subcontractor supplier, or, as a maximum, $110,000, the amount contracted for with the first tier subcontractor for installation of the entire emergency shutdown valve system including the valves, should be deducted from the total contract price. The issue was included among those tried before an AEC hearing examiner who issued a decision on September 26, 1963. (See n. 4.) By Memorandum and Order issued December 18, 1963, the Commission denied both the contracting officer’s and the plaintiffs’ petitions for review which relate to Change Order No. 3. Under regulations in effect at the time, a denial of a petition for review caused the AEC hearing examiner’s decision to become the final action of the Commission, thus making it ripe for review here. 10 C.P. R. jf 2.762(e) (1963).

In their third cause of action, plaintiffs challenge the reasonability of the amount to be deducted from the contract price and credited to the Government for valve installation and hydrostatic pipe testing work deleted from the contract by deductive Change Order No. 18, Addendum 15 issued March 17, 1958. This iss.ue also was tried before the AEC hearing examiner, this time with his decision of September 26, 1963, favoring the contractor. The contracting officer’s petition for review of said decision was granted but in a decision issued April 23, 1964, the Commission reversed the hearing examiner, holding that it was reasonable and correct for the Government to deduct $10,258.02 for the work eliminated from the contract by Change Order No. 18. As it did below, the Government here urges that its actual cost of having the deleted work completed by another contractor ($10,258.-02) was a reasonable sum to pay for the work and, therefore, a reasonable amount to be deducted from the contract price. Plaintiffs argue that the work could have been done for no more than $2,000, which price therefore becomes an upper dollar limit on price deductions which may be reasonably taken. They further argue that the holding of the Commission is arbitrary, capricious, and not based on substantial evidence.

In both its answer and amended answer, defendant asserts a counterclaim for alleged overpayment by the Government to plaintiffs in the total amount of *940 $25,743.26. As a preliminary matter, it should be noted that the briefs to the trial commissioner indicated some confusion as to the degree to which the defendant’s counterclaim is to be included in the decision on the parties’ respective motions for summary judgment. Defendant’s counterclaim alleges deductions due the Government for overpayment to the contractor by reason of (1) a claimed deduction in the amount of $170,796 relating to Change Order No. 3; (2) a claimed deduction in the amount of $10,258.02 relating to Change Order No. 18; (3) a claimed setoff in the amount of $18,218.80 for “Terminated Work”; and (4) a claimed setoff in the amount of $500 for “Snow Removal.” In a word, the counterclaim challenges all of plaintiffs’ three causes of action, since Change Orders 3 and 18 are the subject of plaintiffs’ second and third causes of action, and the claimed setoff for terminated work relates to plaintiffs’ first cause of action. The record does not readily disclose a connection between the claimed setoff for snow removal and any one of the three causes of action alleged by plaintiffs in their petition.

The June 28, 1968 order of the trial commissioner, mentioned hereinbefore, severing, for trial, plaintiffs’ first cause of action from their second and third causes of action, stated in pertinent part:

* * * It appears from plaintiffs’ petition, defendant’s answer and counterclaim, and plaintiffs’ reply thereto, that the parties are properly in agreement that the action of the court with respect to plaintiff’s second and third causes of action, and defendant’s counterclaim, should be limited to a review of the administrative record of the proceedings before the United States Atomic Energy Commission's Board of Review (Commission) to determine whether the decision meets the standards prescribed by the Wunderlich Act, 41 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meltech Corporation, Inc.
Armed Services Board of Contract Appeals, 2025
AICI-Archirodon JV
Armed Services Board of Contract Appeals, 2025
Korte Construction Company
Armed Services Board of Contract Appeals, 2023
Derian, Inc.
Armed Services Board of Contract Appeals, 2023
GSC Construction Incorporated
Armed Services Board of Contract Appeals, 2019
Kellogg Brown & Root Services, Inc.
Armed Services Board of Contract Appeals, 2018
Meridian Engineering Company v. United States
130 Fed. Cl. 147 (Federal Claims, 2016)
East Coast Repair & Fabrication, LLC v. United States
199 F. Supp. 3d 1006 (E.D. Virginia, 2016)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
PCL Construction Services, Inc. v. United States
53 Fed. Cl. 479 (Federal Claims, 2002)
W.G. Yates & Sons Construction Co. v. United States
53 Fed. Cl. 83 (Federal Claims, 2002)
M.J. Paquet, Inc. v. New Jersey Department of Transportation
794 A.2d 141 (Supreme Court of New Jersey, 2002)
MJ Paquet, Inc. v. Dept. of Transp.
761 A.2d 122 (New Jersey Superior Court App Division, 2000)
UMC Electronics Co. v. United States
43 Fed. Cl. 776 (Federal Claims, 1999)
Datalect Computer Services, Ltd. v. United States
42 Cont. Cas. Fed. 77,379 (Federal Claims, 1998)
District of Columbia v. Organization for Environmental Growth, Inc.
700 A.2d 185 (District of Columbia Court of Appeals, 1997)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
C. Sanchez and Son, Incorporated v. United States
6 F.3d 1539 (Federal Circuit, 1993)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
442 F.2d 936, 194 Ct. Cl. 835, 1971 U.S. Ct. Cl. LEXIS 127, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nager-electric-company-inc-and-keystone-engineering-corporation-v-the-cc-1971.