M.J. Paquet, Inc. v. New Jersey Department of Transportation

794 A.2d 141, 171 N.J. 378, 2002 N.J. LEXIS 361
CourtSupreme Court of New Jersey
DecidedApril 4, 2002
StatusPublished
Cited by101 cases

This text of 794 A.2d 141 (M.J. Paquet, Inc. v. New Jersey Department of Transportation) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M.J. Paquet, Inc. v. New Jersey Department of Transportation, 794 A.2d 141, 171 N.J. 378, 2002 N.J. LEXIS 361 (N.J. 2002).

Opinion

The opinion of the Court was delivered by

ZAZZALI, J.

This appeal requires the Court to determine whether an equitable adjustment should be awarded to a successful bidder of a public contract whose performance is rendered impracticable during the course of the contract. M.J. Paquet, Inc. (Paquet) submitted an unbalanced bid for a contract with the New Jersey Department of Transportation (DOT) to rehabilitate several highways and bridges in New Jersey. The DOT awarded Paquet the contract. Nearly one year later, the Occupational Safety and Health Administration (OSHA) issued revised regulations substantially affecting Paquet’s performance of the bridge painting work. After the parties could not agree on an increased amount for the bridge painting work, the DOT deleted that work from the con *382 tract. Thereafter, Paquet commenced this action seeking legal and equitable relief.

The trial court found that the DOT properly had deleted the bridge-painting work from the contract, but nonetheless awarded Paquet an equitable adjustment for the other tasks that the contractor had completed. The Appellate Division upheld the DOT’s right to delete the bridge-painting work, but denied Paquet any equitable adjustment. M.J. Paquet v. New Jersey Dep’t of Transp., 335 N.J.Super. 130, 144, 761 A.2d 122 (App.Div.2000). The panel reasoned that such an adjustment was not warranted because DOT specifications prohibited unbalanced bids and purportedly barred recovery in this setting. Ibid.

We affirm the Appellate Division’s ruling that the DOT properly deleted the bridge painting portion of the contract. However, we reverse the decision denying Paquet an equitable adjustment of the contract price, and remand the matter to the trial court for a determination of the amount of that adjustment.

I

In October 1992, the DOT solicited bids for a contract to rehabilitate highways in northern New Jersey. The project included highway resurfacing, safety improvements, and the restoration and painting of twelve bridges along various routes. Several days before submitting its bid, Paquet received an estimate from a potential subcontractor for the bridge painting work included in the project. Paquet used that estimate to calculate the forty-four individual pay items contained in its bid pertaining to the bridge painting. After adding its customary thirty percent mark-up for costs, overhead, and profit to the bridge painting pay items, Paquet’s total bid for the bridge painting work amounted to $826,473.50. Shortly before the bid submission deadline, Paquet received a significantly lower estimate of $450,414 for the bridge painting work from subcontractor O.J. Painting.

*383 According to Paquet, because “it was impracticable and highly risky to redo all the prices for the [forty-four] bridge structure items,” Paquet did not amend the $826,473.50 figure it originally entered on the bid for the bridge painting work. Rather, Paquet lowered the price of several of the other “common” items, including mobilization and construction layout costs, to offset the now inflated price for the bridge painting work. Accordingly, Paquet submitted an “unbalanced” bid to the DOT. An “unbalanced” bid is one “in which one or more of the pay items fails to carry its share of the cost of the work and the contractor’s profit.” Paquet, supra, 335 N.J.Super. at 132, 761 A.2d 122.

Paquet’s bid of $17,906,324 was the lowest presented to the DOT, which subsequently awarded Paquet the contract. At that time, the DOT was unaware that Paquet had submitted an unbalanced bid. Before the work commenced, Paquet submitted and received approval of the O.J. Painting subcontract from the DOT. The record does not indicate whether the DOT compared the subcontract price with the amount in Paquet’s bid for the bridge painting work.

After the DOT awarded Paquet the contract, OSHA issued revised regulations in respect of the cleaning and painting of existing bridges containing lead-based paint. Those regulations directly affected the bridge painting work in the Paquet DOT contract. Paquet asserted that the new OSHA regulations “significantly increased the nature and the magnitude of procedures governing [the] cleaning and painting [of] existing structural steel” containing lead-based paint. Accordingly, Paquet informed the DOT that compliance with the new regulations would result in Paquet’s incurring substantial and unanticipated costs. Paquet made several requests to the DOT to increase the original contract price, culminating in a final request of $1,280,267.50 to cover costs precipitated by the new regulations.

After considering Paquet’s proposal, the DOT informed Paquet that the DOT had decided to excise the bridge painting from the contract. Paquet insisted that the DOT did not have the right to *384 remove the bridge painting work, and that any such removal would be a modification of the contract that would entitle Paquet to compensation. Subsequently, Paquet received a change order from the DOT indicating that the bridge painting work had been deleted because “[negotiations with [Paquet] ... [were] not successful.” The amount deleted, $826,473.50, represented the amount Paquet provided in its bid for the forty-four bridge painting pay items.

Paquet responded by filing a Contractual Notice Form objecting to the DOT’s removal of the bridge painting work. Specifically, Paquet alleged that an item of work could be eliminated from the contract only if the item was unnecessary. According to Paquet, the painting work was necessary to rehabilitate the bridges. Further, if Paquet did not complete the work the DOT eventually would be required to commission another contractor to do the work. Finally, Paquet insisted that “even if the [DOT were] entitled to eliminate the majority of the painting work, under the contract, equity[,] and case law, the [DOT] would only be entitled to a deduction for the actual cost of the work, not a deduction based on the original contract unit prices.”

The parties unsuccessfully attempted to settle the dispute pursuant to the alternative dispute resolution procedure set forth in the contract. Paquet then filed this action against the DOT. Paquet claimed that the DOT was not authorized to delete the painting work from the contract and, alternatively, that the DOT could not delete the entire amount of $826,473.50 listed in the contract for the bridge painting work. The trial court found that the DOT properly deleted the bridge painting work, holding that because the new OSHA regulations had “significantfly] alter[ed]” the circumstances surrounding the parties’ contract, the contract was impossible to perform. The court also held that the entire $826,473.50 should not have been deleted because Paquet was entitled to an equitable adjustment. The trial court reasoned that Paquet had deleted approximately $376,000 from the non-bridge painting portion of the contract to reflect the difference between *385

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Claremont Construction Group, Inc. v. Arc Nj, LLC
New Jersey Superior Court App Division, 2025
Paul Sobotor v. Mt. Arlington Holdings, LLC
New Jersey Superior Court App Division, 2025
Main Street Neal, LLC v. Jm40, LLC
New Jersey Superior Court App Division, 2025
101 Hudson Properties, LLC v. Birch Real Estate Services, LLC
New Jersey Superior Court App Division, 2025
Roma Pizzeria, Etc. v. Harbortouch
New Jersey Superior Court App Division, 2025
Park Road Development, LLC v. Akgg, LLC
New Jersey Superior Court App Division, 2024
Nc Community Center Associates v. Bmaawad Enterprises, LLC
New Jersey Superior Court App Division, 2024
Thomas Kiely v. William C. Iler
New Jersey Superior Court App Division, 2024
ORP Surgical v. Howmedica Osteonics Corp.
92 F.4th 896 (Tenth Circuit, 2024)
Global Logistics & Distribution, LLC v. 14 Burma Road Associates
New Jersey Superior Court App Division, 2024
Louisiana Boil LLC v. Hortense Associates, Lp
New Jersey Superior Court App Division, 2023
Holtec International v. New Jersey Economic Development Authority
New Jersey Superior Court App Division, 2023
In the Matter of the Estate of Michael D. Jones
New Jersey Superior Court App Division, 2023

Cite This Page — Counsel Stack

Bluebook (online)
794 A.2d 141, 171 N.J. 378, 2002 N.J. LEXIS 361, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mj-paquet-inc-v-new-jersey-department-of-transportation-nj-2002.