SMC Corp. v. NJ WATER SUPPLY AUTH.

759 A.2d 1223, 334 N.J. Super. 429
CourtNew Jersey Superior Court Appellate Division
DecidedSeptember 28, 2000
StatusPublished
Cited by2 cases

This text of 759 A.2d 1223 (SMC Corp. v. NJ WATER SUPPLY AUTH.) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SMC Corp. v. NJ WATER SUPPLY AUTH., 759 A.2d 1223, 334 N.J. Super. 429 (N.J. Ct. App. 2000).

Opinion

759 A.2d 1223 (2000)
334 N.J. Super. 429

SMC CORPORATION, INC., Plaintiff-Appellant,
v.
NEW JERSEY WATER SUPPLY AUTHORITY, Defendant/Third-Party Plaintiff-Respondent,
v.
Bergmann Associates i/p/a Donald J. Bergmann & Associates, Inc., Third-Party Defendant-Respondent.

Superior Court of New Jersey, Appellate Division.

Argued September 13, 2000.
Decided September 28, 2000.

Bruce R. Demeter, Trenton, argued the cause for appellant (Simon & Demeter, attorneys; Mr. Demeter, on the brief).

*1224 Emily H. Armstrong, Deputy Attorney General, argued the cause for respondent New Jersey Water Supply Authority (John J. Farmer, Jr., Attorney General, attorney; Susan R. Roop and Mary C. Jacobson, Assistant Attorneys General, of counsel; Ms. Armstrong, on the brief).

Before Judges D'ANNUNZIO, KEEFE, and EICHEN.

The opinion of the court was delivered by D'ANNUNZIO, P.J.A.D.

This is a public contract case. At issue is the allocation of the risk of unknown subsurface conditions. Appellant, SMC Corporation (SMC), sued a public entity, New Jersey Water Supply Authority (Authority), for additional expenses incurred in SMC's performance of its contract with the Authority. SMC appeals from a summary judgment in favor of the Authority.

SMC was the low bidder, at $311,000, for the contract to reconstruct the Moores Creek culvert in Hopewell Township, Mercer County. The work had to be done in the stream bed, and water had to be removed from the work area during construction. SMC was responsible for dewatering the site, and the specifications called for it to use cofferdams.[1] As SMC was about to begin work, it discovered a "scour hole" approximately 9 feet deep where Moores Creek empties into the Delaware River. The scour hole was much deeper than the bed of the river shown on the Authority's plans.

SMC advised the Authority's representatives that the position of the scour hole prevented construction of the cofferdams where indicated on the plans and that additional work and expense would be required to solve the problem. Although the record suggests that the Authority's representatives accepted the fact that the existence of the scour hole would require additional work, they rejected SMC's estimate of an additional $190,000. Thereafter, SMC performed the work and completed the job in a timely manner. SMC commenced this action to recover additional costs.

The Supreme Court of New Jersey, in an opinion by Justice O'Hern, addressed the issue of risk allocation in P.T. & L. Constr. Co., Inc. v. Department of Transp., 108 N.J. 539, 531 A.2d 1330 (1987). The Court noted that the federal government uses a changed conditions clause in its contracts. Id. at 547, 531 A.2d 1330. It permits a contractor to make a claim for additional work caused by subsurface or latent physical conditions at the site "differing materially from those indicated" in the contract or for "unknown physical conditions at the site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in this contract." Foster Constr. C.A. & Williams Bros. Co. v. United States, 193 Ct.Cl. 587, 435 F.2d 873, 876 (1970); see generally N.O. Harlow, Annotation, Construction and Effect of "Changed Conditions" Clause in Public Works or Construction Contract with State or Its Subdivision, 56 A.L.R.4th 1042 (1987). The federal changed conditions clause allocates the risk of unknown conditions to the government, thereby, theoretically, generating lower-priced initial bids from contractors. Foster Constr. C.A. & Williams Bros. Co., supra, 435 F.2d at 887; see Hazel Glenn Beh, Allocating the Risk of Unforeseen, Subsurface and Latent Conditions in Construction Contracts: Is There Room for the Common Law?, 46 University of Kansas L.Rev. 115, 131-34 (1997).

The contract used by the New Jersey Department of Transportation in P.T. & L. allocated the risk of the unknown to the *1225 contractor. P.T. & L., supra, 108 N.J. at 551-52, 531 A.2d 1330.[2] Nevertheless, the Court held that if the contract specifications made "positive averments which purported to actually describe the land" but which were not correct, then the contractor had a claim for additional expenses generated by the work. Id. at 554, 531 A.2d 1330. If the contract, however, "`made no mention of whether such conditions would be encountered,'" the contractor had no claim under the contract utilized in P.T. & L. Ibid. (quoting Golomore Assocs. v. New Jersey Highway Auth., 173 N.J.Super. 55, 59, 413 A.2d 361 (App.Div. 1980)); see Ell-Dorer Contracting Co. v. State, 197 N.J.Super. 175, 484 A.2d 356 (App.Div.1984); Sasso Contracting Co. v. State, 173 N.J.Super. 486, 414 A.2d 603 (App.Div.), certif. denied, 85 N.J. 101, 425 A.2d 265 (1980).

The contract in the present case does not contain the strong clause imposing the risk of subsurface conditions on the contractor as did the contract in P.T. & L., nor does it contain an explicit changed conditions clause as in federal contracts. The SMC contract does contain the following, which we refer to hereafter as paragraph 9:

9. Site Investigation and Representation:

The contractor acknowledges that he has satisfied himself as to the nature and location of the work, the general and local conditions particularly those bearing upon transportation, disposal, handling and storage of materials, availability of labor, water, electric power, roads and uncertainties of weather, floods or similar physical conditions at the site, the topography and conditions of the ground, the character of equipment and facilities needed preliminary to and during the execution of the work, and all other matters upon which information is reasonably obtainable and which can in any way affect the work or the cost thereof under this Contract. The Contractor further acknowledges that he has satisfied himself as to the character, quality and quantity of information regarding the above that is reasonably ascertainable from an inspection of the site, including all exploratory work done by the Authority or the Engineer, as well as information contained in the Drawings and Specifications forming a part of this Contract. The Contractor further acknowledges that he has satisfied himself as to the availability of timber, stone, fill material, etc. both as to quality and quantity required to execute the work. Any failure by the *1226 Contractor to acquaint himself with all the available information will not relieve him from the responsibility for estimating properly the difficulty or cost to successfully perform the work.
The Contractor's attention is drawn to the fact that As-Built Drawings of existing work do not exist and some dimensions shown on the Contract Drawings have been estimated. All dimensions shall be field checked by the Contractor.
[Emphasis added.]

In granting summary judgment, the trial court ruled that the Authority made no "affirmative misrepresentation" regarding existing conditions. We agree and affirm that ruling.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
759 A.2d 1223, 334 N.J. Super. 429, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smc-corp-v-nj-water-supply-auth-njsuperctappdiv-2000.