Terminal Construction Corp. v. Bergen County Hackensack River Sanitary Sewer District Authority

113 A.2d 787, 18 N.J. 294, 1955 N.J. LEXIS 256
CourtSupreme Court of New Jersey
DecidedApril 25, 1955
StatusPublished
Cited by75 cases

This text of 113 A.2d 787 (Terminal Construction Corp. v. Bergen County Hackensack River Sanitary Sewer District Authority) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Terminal Construction Corp. v. Bergen County Hackensack River Sanitary Sewer District Authority, 113 A.2d 787, 18 N.J. 294, 1955 N.J. LEXIS 256 (N.J. 1955).

Opinions

The opinion of the court was delivered by

Burling, J.

This civil action arose out of contract. The specific contract involved was entered into between Terminal Construction Corporation, a corporation of the State of New Jersey (hereinafter referred to as Terminal), and Young Foundation Corporation, a corporation of the State of New Jersey (hereinafter referred to as Young), on the one hand, and the Bergen County Hackensack River Sanitary Sewer District Authority, now the Bergen County Sewer Authority (hereinafter referred to as the authority). The contract, designated as Contract No. 1, was entered into by the parties thereto on August 12,1949, as a result of competitive bidding. Young subsequently (September 22, 1952) assigned all its rights therein to Terminal, in accordance with their independent agreement of July 5, 1949. Contract No. 1, ante, was part of an immense sewage disposal project, known as the Joint Sewage Works for the Overpeck Valley. In the information to bidders 14 contracts were described. Of these 14 contracts, 12 were for various trunk and interceptor sewers together with manholes, meter chambers and appurtenances, and one was for alteration and refitting of the Tenafly, New Jersey, pumping station. Contract No. 1, ante, which appears to have been the principal contract of the project, provided for all equipment, materials and work necessary for the construction of the authority’s sewage treatment plant in Little Ferry, New Jersey, and its acceptance by the authority in complete operating condition. The structures to be built under Contract No. 1, ante, included pump and blower house, screen chamber, grit collector and ejector, primary settling tanks, aeration tanks, final settling tanks, chlorine contact tank, chlorine building and monorail system, “Parshall [301]*301Plume,” sludge digestion tanks, digester control house, primary sludge pumping station, return sludge pumping station, and pumping station in sludge lagoon, together with garage, underdrains, pipe galleries and piping, open channels, outfall sewer and headwall, landscaping, roadways and walks, outdoor lighting and fencing. It also included all structural steel, electrical, plumbing, and heating and ventilating work in the various structures above described. The bid on Contract No. 1, ante, was submitted under date of July 5, 1949, giving an “approximate” total price of $4,246,715.46 (not a binding figure, but expressly described as being merely for the purposes of comparing the bids). The form of contract recited this total price as the “estimated contract amount” and provided for the contractor to “accept as payment in full the summation of products of the actual quantities as determined by the Engineer’s estimate, by the unit prices and lump sums bid.”

The Overpeck Valley sanitary sewer system and sewage disposal plant were to provide sanitary sewerage disposal for a large area of Bergen County, one of the most populous counties of the State of New Jersey.

As is customary in a major enterprise such as this, detailed and meticulous specifications and terms form part of the contract. Such provisions are usually recommended and drafted by an experienced engineer at the instance of the owner, or sponsor, of the project.

The work to be performed is grounded in the principles of free enterprise and competition. The scope of such an undertaking requires those who accept the invitations to bid to be well versed, or advised, in contract law and forms together with comparable efficiency in accounting and engineering departments. Otherwise their financial doom is spelled. It is common knowledge that the owner, or sponsor, “writes its own ticket” and the competing market of contractors is obliged to bid and perform in conformity thereto, or to avoid that field of endeavor.

However, this does not mean that a contractor is not entitled to enjoy just treatment within the terms of the con[302]*302tract. If it were otherwise the construction of vital public and municipal projects would suffer by the failure of qualified bidders to enter the field for fear of risks beyond those which are foreseeable. It is grave enough to meet calculated risks in good business practice. The public authority which chooses the contract terms is not exempt from the operation of the basic principle of construction of contracts, that where ambiguities exist they are to be taken most strongly against the draftsman. Jennings v. Pinto, 5 N. J. 562, 569 (1950); Moses v. Edward H. Ellis, Inc., 4 N. J. 315, 323 (1950).

With this in mind we approach the present controversy. The principal disputes herein arise out of the functioning of the site engineer (i. e., the on-site representative of the engineering firm which was the contract designated engineer), and a meticulous study of the engineer’s status, duties and jurisdiction is of infinite importance here.

Contract No. 1, ante, including the invitations to bid, clearly contemplated cooperation between contractors engaged on various contract segments of the project. Mutual responsibilities required timing of different phases of the overall operations to mesh the completion of the several elements of the construction most economically and efficiently in the Authority’s interests. To keep the work rolling is the objective of the project engineer.

Good and fair engineering practice required definition and classification of the work upon the order for action without waiting until “settlement .day.” To define or classify the various items of work arbitrarily or grossly negligently to the detriment of a cooperative contractor who desired to expedite and synchronize the performance of his scope of the work with that of other contractors would result in unjust enrichment of the sponsor.

In the last amended complaint filed, and in the answer thereto, it was claimed and admitted that the contract in question was entered into on August 12, 1949. On September 28, 1949, Terminal was ordered by the authority to commence work within ten days as required by Article 34 of the [303]*303contract (namely “at such point or points as the Engineer may designate”). The work progressed. There was dispute in the pleadings as to the date or dates of completion. It appears that much of the work was completed by September 1951; but Terminal in Eebruary 1952 was still proceeding with the work. The Authority’s answer to the last amended complaint filed alleged that Terminal “had by the 11th day of June, 1952, substantially performed most of the physical work specified” in the contract and that on August 1, 1952 the engineer “issued to plaintiff a certificate of substantial completion which was revised August 6, 1952.”

Terminal filed its initial complaint herein in the Superior Court, Law Division, on September 10, 1951, but subsequently filed amended complaints. The authority’s answer to the last amended complaint was filed September 22, 1952. The Superior Court, Law Division, entered a pretrial order on September 29, 1952. Trial began October 15, 1952. The trial proceedings occupied 19 days, terminating on November 20, 1952, with the verdict of the jury, rendered in favor of Terminal in the aggregate sum of $454,444.32. Judgment was entered on the verdict on November 24, 1952. During the trial, however, the trial court had granted the authority’s motion to dismiss two counts of the complaint. Judgment of dismissal of these counts was entered on November 22, 1952.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Henry v. New Jersey Department of Human Services
9 A.3d 882 (Supreme Court of New Jersey, 2010)
Highland Lakes Country Club & Community Ass'n v. Franzino
892 A.2d 646 (Supreme Court of New Jersey, 2006)
Driscoll Const. Co., Inc. v. State
853 A.2d 270 (New Jersey Superior Court App Division, 2004)
M.J. Paquet, Inc. v. New Jersey Department of Transportation
794 A.2d 141 (Supreme Court of New Jersey, 2002)
AXA Assurance, Inc. v. Chase Manhattan Bank
770 A.2d 1211 (New Jersey Superior Court App Division, 2001)
Mayles v. Wentlejewski
767 A.2d 526 (New Jersey Superior Court App Division, 2001)
Great Atl. & Pac. Tea Co. v. Checchio
762 A.2d 1057 (New Jersey Superior Court App Division, 2000)
SMC Corp. v. NJ WATER SUPPLY AUTH.
759 A.2d 1223 (New Jersey Superior Court App Division, 2000)
Whalen v. Schoor, Depalma & Canger Group, Inc.
702 A.2d 1311 (New Jersey Superior Court App Division, 1997)
Brett v. Great American Recreation, Inc.
677 A.2d 705 (Supreme Court of New Jersey, 1996)
Kass v. Great Coastal Exp., Inc.
676 A.2d 1099 (New Jersey Superior Court App Division, 1996)
New York State Higher Education Services Corp. v. Lucianna
666 A.2d 173 (New Jersey Superior Court App Division, 1995)
Fisch v. Bellshot
640 A.2d 801 (Supreme Court of New Jersey, 1994)
Saxon Const. & Management Corp. v. Masterclean of North Carolina
641 A.2d 1056 (New Jersey Superior Court App Division, 1994)
Feldman v. Lederle Laboratories
625 A.2d 1066 (Supreme Court of New Jersey, 1993)
SAXON CONST. & MANAGEMENT CORP. v. Masterclean
641 A.2d 1129 (New Jersey Superior Court App Division, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
113 A.2d 787, 18 N.J. 294, 1955 N.J. LEXIS 256, Counsel Stack Legal Research, https://law.counselstack.com/opinion/terminal-construction-corp-v-bergen-county-hackensack-river-sanitary-nj-1955.