Massman Construction Co. v. Lake Lotawana Ass'n

210 S.W.2d 398, 240 Mo. App. 469, 1948 Mo. App. LEXIS 281
CourtMissouri Court of Appeals
DecidedFebruary 9, 1948
StatusPublished
Cited by17 cases

This text of 210 S.W.2d 398 (Massman Construction Co. v. Lake Lotawana Ass'n) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Massman Construction Co. v. Lake Lotawana Ass'n, 210 S.W.2d 398, 240 Mo. App. 469, 1948 Mo. App. LEXIS 281 (Mo. Ct. App. 1948).

Opinion

*472 BLAND, J.

This is an action for the balance claimed to be due under-an excavation contract. There was a verdict and judgment in favor of plaintiff in the sum of $8521.56, and in favor of defendant in the sum of $700 on its counterclaim based upon plaintiff’s delay in performing the work. Defendant appealed to the Supreme Court and that court transferred the cause here.

The facts show that on July 14, 1944 the parties hereto entered into a written contract in which plaintiff undertook to make certain improvements to the spillway in the dam at Lake Lotawana in Jackson County, consisting of .the construction of a sluiceway approximately. 7 feet deep, 13 feet wide and 400 feet long, whereby the water level of the lake could be lowered 7 feet to enable repairs to be made at the top of the dam which impounds the water making the lake. The work consisted of breaking the concrete.floor of the existing spillway for the length and width of -the sluiceway, excavating the material found thereunder for the required depth, length and width, concreting the sides and bottom of the excavation and installing a gate to control the flow of water. It also involved the excavation of an approach channel between the lake and the entrance to said concrete sluiceway.

The contract-provided: “EXCAVATION: Borings along the spillway indicate that the excavation will be in material classified as shale. Bidders should -satisfy themselves as to the class of material which will be encountered and its method of removal. It is believed that the rock will not be found but a unit price is requested for rock excavation for use in calculating payments if rock is found. * * *

“ROCK EXCAVATION: It is believed that no rock excavation will be encountered but if material is required to be removed which meets this description, it will be classed and paid for as rock excavation :

“Rock shall be interpreted to include all solid rock ledge formation which can be removed properly only by means of explosives, barring or wedging, 'or by some other recognized method for quarrying solid -rock. It shall also include boulders of one-half cubic yard or more in volume. ’ ’

The contract also provided that plaintiff should furnish the tools, labor, material and machinery necessary to do the work required at the following prices: ‘ ‘ Excavation and grading for sluiceway, including removal of any and all materials encountered except solid rock per cubic yard One Dollar $1.00. * * * For rock excavation in *473 either sluiceway or approach channel, per cubic yard Eight Dollars $8.00”. It also provided: “ ‘Consulting Engineer’ or ‘Engineer’ shall mean Charles A. Haskins, the Consulting- Engineer for Lake Lotawana Association. - ‘ Resident Engineer ’ shall mean- the Resident Engineer for Lake Lotawana Association, acting personally or through assistants duly authorized by the Consulting Engineer” It further provided that it shall be the duty of the engineers to see that the contract is carried out in accordance with- the- plans, specifications and contract provisions, “inspect materials and workmanship, interpret plans and specifications, make such measurements as will determine payments to the contractor, and generally represent the Association on the work”. ■ • • '

The contract further provided: “PAYMENT: Not later than the 15th day of each calendar month, the Association will make partial payment to the Contractor on the basis of a duly certified approved estimate of the work performed during the preceding, calendar month by the Contractor, but the Association will retain 10 percent of the amount of each such estimate until the final completion and acceptance of all work covered by this contract. * * * FINAL' ESTIMATE : The Engineer shall, as soon as possible after the completion of the work under this contract, make a final estimate of the amount of work done and the Association shall, within thirty (30) days (subject to its approval and acceptance) after such final estimate is made, pay the entire sum as found to be due, after déducting therefrom all previous. payments. All prior estimates and payments shall be subject to correction in the final estimate and payment”.

F. M. Dozier was the resident engineer on the job during the performance of the work. He -made two preliminary measurements and estimates under the supervision of Charles A. Haskins, engineer, assisted by George F. James, plaintiff’s superintendent, and $12,883.26 was paid by defendant to plaintiff on these estimates. This amount was 90% of 'the contract value of the work done up to that time. On April 14,1945, a final estimate was made by Dozier, assisted by Henry Daley, representing the plaintiff, under the supervision of Haskins, which showed a balance due plaintiff of $2474.68. Plaintiff refused to accept payment on this estimate. All of the estimates were based on a charge of only $1.00 per cubic yard for the 787.3 yards of excavation in controversy, the estimate showing that no rock'excavating was done. The controversy between the parties is over whether this 787.3 cubic yards of the excavation done is to be classified as rock excavation to be paid for'at the rate of $8.00 per cubic yard instead of $1.00 per cubic yard, for which plaintiff would be paid under the estimates.

Over the objection of defendant plaintiff was permitted'to show that the 787.3 cubic yards in .controversy was rock excavation-. According to the contract and plans the depth of the excavation varied according to the ground elevation, the bottom and sides of which were to be *474 brought to an exact grade and alignment by trimming and shaping so that the same could be lined with concrete. Hence it was required that the “lines must be held straight and in true alignment”. Plaintiff would not be paid for any material excavated outside of the lines and, if it did so, would be required to fill the same at its own expense.

On account of the excavation of the sluiceway being" only 13.2 feet in width it was impossible to use a power shovel with a larger than a 3/8 cubic yard bucket.on account-of the fact that any larger shovel would be equipped with a boom that would come in contact with the sides of the excavation as the shovel was being operated. The power shovel used was equipped with projecting teeth or prongs with sharp edges with which to dig into and lift the materials to be excavated. Very little excavating was done until (according to plaintiff’s evidence) the material uncovered was such as to require drilling and blasting. A solid ledge was encountered going the full depth of the excavation. One of plaintiff’s witnesses referred to this material as rock. One called it soapstone and others shale. . Various witnesses testified to its laying in solid, compact ledges or ledge formation. All witnesses testified that it was blue or blue-gray in color, entirely different in color and character from the yellowish material encountered near the surface. In one or two instances where the teeth of the shovel were able to catch on to a projected material the shovel raised, not material the width of the bucket, but a part of the ledge extending far beyond the lines of the 13.2 foot trench, and destroying the side walls of the trench. If the rest of it could have been so elevated and excavated it “would have opened up a wide, ragged trench-difficult to say how wide it would be-just a big, wide, ragged hole in the ground”.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weitz Co. v. MH WASHINGTON
631 F.3d 510 (Eighth Circuit, 2011)
INGRASSIA CONST. CO. v. Vernon Tp. Bd. of Educ.
784 A.2d 73 (New Jersey Superior Court App Division, 2001)
McCarthy Bros. Construction Co. v. Pierce
832 F.2d 463 (Eighth Circuit, 1987)
McCARTHY BROTHERS CONSTRUCTION COMPANY v. PIERCE
832 F.2d 463 (Eighth Circuit, 1987)
Bernard McMenamy Contractors, Inc. v. Missouri State Highway Commission
582 S.W.2d 305 (Missouri Court of Appeals, 1979)
Sides Construction Co. v. Arcadia Valley R-II School District
565 S.W.2d 761 (Missouri Court of Appeals, 1978)
New Pueblo Const., Inc. v. LAKE PATAGONIA REC. ASSOCIATION, INC.
467 P.2d 88 (Court of Appeals of Arizona, 1970)
Southwest Engineering Co. v. Reorganized School District R-9
434 S.W.2d 743 (Missouri Court of Appeals, 1968)
Pat J. Murphy, Inc. v. Drummond Dolomite, Inc.
214 F. Supp. 496 (E.D. Wisconsin, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
210 S.W.2d 398, 240 Mo. App. 469, 1948 Mo. App. LEXIS 281, Counsel Stack Legal Research, https://law.counselstack.com/opinion/massman-construction-co-v-lake-lotawana-assn-moctapp-1948.