New Pueblo Const., Inc. v. LAKE PATAGONIA REC. ASSOCIATION, INC.

467 P.2d 88, 12 Ariz. App. 13, 1970 Ariz. App. LEXIS 561
CourtCourt of Appeals of Arizona
DecidedMarch 31, 1970
Docket2 CA-CIV 781
StatusPublished
Cited by27 cases

This text of 467 P.2d 88 (New Pueblo Const., Inc. v. LAKE PATAGONIA REC. ASSOCIATION, INC.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New Pueblo Const., Inc. v. LAKE PATAGONIA REC. ASSOCIATION, INC., 467 P.2d 88, 12 Ariz. App. 13, 1970 Ariz. App. LEXIS 561 (Ark. Ct. App. 1970).

Opinion

HOWARD, Chief Judge.

On September 25, 1967 the appellee, hereinafter referred to as Lake Patagonia or the Owner, and the appellant, hereinafter referred to as New Pueblo or the Contractor, entered into a contract for the construction of a dam on Sonoita Creek in Santa Cruz County, Arizona.

Paragraph 26 of the contract provides in part as follows :

“ADJUSTMENT OF DISPUTE. All-questions or controversies which may arise between the Contractor and the Owner, under or in reference to this contract, shall be subject to the decision of some competent person to be agreed upon by the Owner and the Contractor, and his decision shall be final and conclusive upon both parties. Should the Owner and Contractor be unable to agree upon such person, a board of three arbitrators shall be chosen, one by the Owner, one by the Contratcor, and the third by the two so chosen, and the decision of any two of said arbitrators shall be-final and binding upon the parties. * * *»

In the fall of 1968, a dispute arose as to whether the dam had been completed by New Pueblo within the time specified by the contract, and whether Lake Patagonia was entitled to liquidated damages. In addition, New Pueblo contended that the-project engineer had miscalculated certain quantities of material supplied by New Pueblo to the project and therefore miscalculated, the amount of money due and owing to New Pueblo.

On January 29, 1969 the engineer certified that the work covered by the contract had been completed and accepted. The engineer certified what the total amount earned by the Contractor was and further certified that the sum of $81,972.52 was. then due to the Contractor. New Pueblo-filed a mechanics lien on January 10th and *15 17th, 1969 and claimed that over $124,800.-00 was due.

On April 18, 1969 New Pueblo, pursuant to paragraph 26 of the contract, sent a letter to Lake Patagonia requesting arbitration of the dispute as to the amount due. 1

On April 21, 1969 Lake Patagonia filed a complaint in the superior court and two days later counsel for Lake Patagonia refused to concur with the request for arbitration.

On April 25, 1969 Lake Patagonia filed an application in the Santa Cruz County Superior Court for an order to stay arbitration. New Pueblo filed a response to the application to stay arbitration and affirmatively moved for an order to compel arbitration. New Pueblo also moved the court for an order staying the action filed In the superior court. 2

Pursuant to A.R.S. § 12-1502 the court granted the stay of arbitration and refused to issue an order requiring arbitration. 3

Appellant presents the following questions for review: Whether the trial court erred in denying New Pueblo’s motion for an order compelling arbitration, erred further in denying New Pueblo’s motion to stay the action pending arbitration, and further erred in granting Lake Patagonia’s application to stay arbitration. The appel-lee, Lake Patagonia, contends that the above questions should be answered in the negative because 1) the superior court still retains jurisdiction over issues not related to the demand for arbitration and 2) the matter raised and the demand of New Pueblo is not subject to arbitration.

NO ARBITRABLE MATTERS

It is Lake Patagonia’s contention that the only matter as to which New Pueblo has sought arbitration by virtue of the letter of April 18, 1969 is the amount of money which New Pueblo claims to be due. It therefore reasons that any determination in this case as to the arbitrability of that is *16 sue has nothing to do with its quiet title action, the right of Lake Patagonia to sue for damages for malicious filing of the liens and its right to liquidated damages resulting from New Pueblo’s failure to complete the work covered by the contract. It contends that since none of these issues are within the demand for arbitration, then resolution of the said issues are completely beyond the authority of any arbitrator. Lake Patagonia cites no authority for this contention, and we have found none.

Referring to the theory of arbitration generally, our Supreme Court has stated:

“Broadly speaking, arbitration is a contractual proceeding, whereby the parties to any controversy or dispute, in order to obtain an inexpensive and speedy final disposition of the matter involved, select judges of their own choice and by consent submit their controversy to such judges for determination, in the place of the tribunals provided by the ordinary processes of law.” Gates v. Arizoná Brewing Co., 54 Ariz. 266, 95 P.2d 49 (1939).

Therefore, in order to accomplish this purpose, arbitration clauses should be construed liberally and any doubts as to whether or not the matter in question is subject to arbitration should be resolved in favor of arbitration. Metro Industrial Painting Corp. v. Terminal Construction Co., 287 F.2d 382 (2nd Cir. 1961) ; United Steelworkers of America v. Warrior and Gulf Navigation Co., 363 U.S. 574, 80 S.Ct. 1347, 4 L.Ed.2d 1409 (1960); Robert Lawrence Co. v. Devonshire Fabrics, Inc., 271 F.2d 402 (2nd Cir. 1959); Lundell v. Massey-Ferguson Services N. V., 277 F. Supp. 940 (N.D. Iowa 1967); Southern Bell Telephone & Telegraph Co. v. Louisiana Power and Light Co., 221 F.Supp. 364 (D.La.1963); Firestone Tire & Rubber Co. v. United Rubber Workers of America, Local Union No. 100, AFL-CIO, 168 Cal.App.2d 444, 335 P.2d 990 (1959); Bewick v. Mecham, 26 Cal.2d 92, 156 P.2d 757 (1945).

The federal courts have adopted what could be termed the “positive assurance” test which requires arbitration unless it can be said with “positive assurance” that the arbitration clause does not cover the dispute :

* * * * * *
“An order to arbitrate the particular grievance should not be denied unless it may be said with positive assurance that the arbitration clause is not susceptible of an interpretation that covers the asserted dispute. Doubts should be resolved in favor of coverage.” United Steelworkers of America v. Warrior and Gulf Navigation Co., supra. 4

Turning our attention to the contract in the instant case, we find that the parties agreed that:

“All questions or controversies which may arise between the Contractor and Owner, under or in reference to this contract, shall be subject to the decision of some competent person to be agreed upon by the Owner and the Contractor. * * * ” (Emphasis added.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Caliente v. Wildflower
Court of Appeals of Arizona, 2020
Tessler v. Progressive
Court of Appeals of Arizona, 2015
Carey v. K&M
Court of Appeals of Arizona, 2014
Wb, the Building Company, LLC. v. El Destino
257 P.3d 1182 (Court of Appeals of Arizona, 2011)
Saguaro Highlands Community Ass'n v. Biltis
229 P.3d 1036 (Court of Appeals of Arizona, 2010)
L. Harvey Concrete, Inc. v. Agro Construction & Supply Co.
939 P.2d 811 (Court of Appeals of Arizona, 1997)
Foy v. Thorp
920 P.2d 31 (Court of Appeals of Arizona, 1996)
Einhorn v. Valley Medical Specialists, P.C.
838 P.2d 1332 (Court of Appeals of Arizona, 1992)
Dusold v. Porta-John Corp.
807 P.2d 526 (Court of Appeals of Arizona, 1990)
Stevens/Leinweber/Sullens, Inc. v. Holm Development & Management, Inc.
795 P.2d 1308 (Court of Appeals of Arizona, 1990)
Norman v. Recreation Centers of Sun City, Inc.
752 P.2d 514 (Court of Appeals of Arizona, 1988)
U.S. Insulation, Inc. v. Hilro Construction Co.
705 P.2d 490 (Court of Appeals of Arizona, 1985)
State v. Stremick Construction Co.
370 N.W.2d 730 (North Dakota Supreme Court, 1985)
Rancho Pescado, Inc. v. Northwestern Mutual Life Insurance
680 P.2d 1235 (Court of Appeals of Arizona, 1984)
Payne v. Pennzoil Corp.
672 P.2d 1322 (Court of Appeals of Arizona, 1983)
Phillips v. Flowing Wells Unified School District No. 8
669 P.2d 969 (Court of Appeals of Arizona, 1983)
Brisco v. Meritplan Insurance
643 P.2d 1042 (Court of Appeals of Arizona, 1982)
Hampton v. Allstate Insurance
616 P.2d 78 (Court of Appeals of Arizona, 1980)
Exber, Inc. v. Sletten Construction Company
558 P.2d 517 (Nevada Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
467 P.2d 88, 12 Ariz. App. 13, 1970 Ariz. App. LEXIS 561, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-pueblo-const-inc-v-lake-patagonia-rec-association-inc-arizctapp-1970.