Gillespie Land & Irrigation Co. v. Hamilton

29 P.2d 158, 43 Ariz. 102, 1934 Ariz. LEXIS 231
CourtArizona Supreme Court
DecidedFebruary 12, 1934
DocketCivil No. 3314.
StatusPublished
Cited by8 cases

This text of 29 P.2d 158 (Gillespie Land & Irrigation Co. v. Hamilton) is published on Counsel Stack Legal Research, covering Arizona Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gillespie Land & Irrigation Co. v. Hamilton, 29 P.2d 158, 43 Ariz. 102, 1934 Ariz. LEXIS 231 (Ark. 1934).

Opinion

LOCKWOOD, J.

E. L. Hamilton, hereinafter called plaintiff, brought suit against Gillespie Land & Irrigation Company, a corporation, hereinafter called defendant, on two causes of action. Defendant answered and cross-complained. The. case was tried to a jury, which returned verdicts on both of plaintiff’s causes of action in his favor and on the cross-complaint in favor of defendant, and judgment was rendered in accordance with the verdicts. After a motion for new trial was made by defendant and overruled, this appeal was taken by it.

The complaint sets up two causes of action, the first alleging that there was a written contract between the parties for the construction of a canal at an agreed price of 10y2 cents per cubic yard, and that *105 in accordance with the terms thereof plaintiff excavated a certain amount of earth, for which work there was still due him, under the contract, the sum of $8,300.06. The second cause alleged that, at the completion of the work done under the contract, the parties entered into an oral contract for further work at the same price, and that plaintiff had done excavation thereunder, for which there was still due him the sum of $12,313.45.

The answer of the defendant, in substance, was that it had entered into a certain written contract with plaintiff for the construction of a canal, according to plans, specifications and surveys to be furnished by the defendant, and that in pursuance of such contract the plaintiff entered upon the work and continued therein until the fourth day of December, 1931, at which time he abandoned it without completing it as provided by the contract. It further alleges that the plaintiff in the doing of such work as he did finish had incurred various indebtednesses for materials and labor which had become liens against the property of defendant and which it would be obliged to pay, and that what work was done was not according to the specifications of the contract, either in manner or amount, and that no vouchers showing the work free from lienable claims had been furnished by plaintiff from time to time, as required by the contract, and that the work had never been completed or a certificate of completion issued by defendant’s engineer, as also required by the contract. As a counterclaim it set up that the work was not done according to the plans, specifications and terms of the contract; that it failed by 800 feet of reaching the place where it was to be finished; that it was not completed within the time provided by the contract, or at all, and that to complete it according to the contract would cost $4,000; that the failure to complete in time had caused defendant to lose crops worth *106 some $10,000; and that it had been compelled .to pay the sum of $644.50 in satisfaction of a judgment obtained by a lienholder against it. Under its counterclaim defendant prayed judgment for the sum of $14,644.54.

The plaintiff did not reply to any of the allegations of the answer regarding engineer’s certificate of completion or failure to furnish vouchers, but denied the failure to perform in the time limit, or to finish the canal to the point required, or to build it according to the plans and specifications. He further alleged that, if the work was stopped it was because defendant had informed plaintiff’s workmen that it would not pay any more money on account of the construction, and that, if they did any more work, they did so at their own risk; the effect being to make it impossible for plaintiff to construct the canal any farther. We think this sufficiently recites the pleadings upon which the case was tried.

The defendant has stated in its brief some thirty-one assignments of error, and has attempted to group these, as required by our rules, under propositions of law. We find it, however, somewhat difficult to determine from the grouping exactly what legal propositions defendant thinks are involved in the appeal, and shall therefore consider the case as best we may on the whole record.

The first issue is whether or not the work, which it is admitted was actually done, was performed under one written contract or under two contracts, one' of which was written and the other of which was oral. The written contract admittedly executed by the parties is to the effect that plaintiff should construct certain drainage canals, “as shown by plans ... as specifically described in the specifications and plans hereinafter referred to.” It was further agreed therein that “the work hereby contracted for should be performed in accordance with the true intent and *107 meaning of the plans and specifications therefor which are hereby referred to and made a part of this contract.” It was to be paid for at the rate of 10% cents per cubic yard on monthly estimates of defendant’s engineer, 50 per cent, immediately on such estimates and the balance after the work was completed and accepted by the engineer. The contractor was to furnish vouchers showing that all materials, labor and equipment had been paid for at the time each estimate was made, or the company would be entitled to withhold payment thereof, and the final payment was to be made when the engineer of defendant certified in writing that the work was finished according to the terms of the contract. Finally it was provided that, if the contractor failed or refused to continue the prosecution of the work diligently, the defendant had the right to take over and complete it and pay therefor from the 50 per cent, of the monthly estimate retained as provided by the contract.

There can be no doubt that any work done under the terms of the written contract had to be approved by the engineer on estimates made by him, and that no portion of the payments needed to be made until it appeared that there were, to the date of the estimate, no lienable claims for labor or material outstanding, and that the final payment should not be made until the engineer certified that the work was completed in accordance with the terms of the contract. Provisions of this nature are common in construction contracts and are held to be valid and binding (Guarantee Title & Trust Co. v. Willis, 38 Ariz. 33, 297 Pac. 445; Elliott v. Missouri etc. R. Co., (C. C. A.) 74 Fed. 707; Hathaway v. Stone, 215 Mass. 212, 102 N. E. 461; Williams v. Mount Hood R. Co., 57 Or. 251, 110 Pac. 490, 111 Pac. 17, Ann. Cas. 1913A 177), unless it appears that the engineer has acted arbitrarily and capriciously or unreasonably (Guarantee *108 Title (& Trust Co. v. Willis, supra; Ripley v. United States, 223 U. S. 695, 750, 32 Sup. Ct. 352, 56 L. Ed. 614; American-Hawaiian Engineering Co. v. Butler, 165 Cal. 497, 133 Pac. 280, Ann. Cas. 1916C 44; Hebert v. Dewey, 191 Mass. 403, 77 N. E. 822; Piper v. Murray, 43 Mont. 230, 115 Pac. 669), or that the parties have waived such provisions (Blethen v. Blake, 44 Cal. 117; Lavanway v. Cannon, 37 Wash. 593, 79 Pac. 1117;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Myers v. Western Realty & Construction, Inc.
635 P.2d 867 (Court of Appeals of Arizona, 1981)
Lincoln Construction, Inc. v. Thomas J. Parker & Associates, Inc.
602 P.2d 676 (Court of Appeals of Oregon, 1979)
Knight Bros., Inc. v. State
199 N.W.2d 720 (Nebraska Supreme Court, 1972)
Wahl v. Southwest Savings & Loan Association
467 P.2d 930 (Court of Appeals of Arizona, 1970)
New Pueblo Const., Inc. v. LAKE PATAGONIA REC. ASSOCIATION, INC.
467 P.2d 88 (Court of Appeals of Arizona, 1970)
Blecick v. School District No. 18 of Cochise County
406 P.2d 750 (Court of Appeals of Arizona, 1965)
Kerr-McGee Oil Industries, Inc. v. McCray
361 P.2d 734 (Arizona Supreme Court, 1961)
United States ex rel. T. M. Page Corp. v. Hensler
125 F. Supp. 887 (S.D. California, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
29 P.2d 158, 43 Ariz. 102, 1934 Ariz. LEXIS 231, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gillespie-land-irrigation-co-v-hamilton-ariz-1934.