Knight Bros., Inc. v. State

199 N.W.2d 720, 189 Neb. 64, 1972 Neb. LEXIS 657
CourtNebraska Supreme Court
DecidedAugust 4, 1972
Docket38376
StatusPublished
Cited by12 cases

This text of 199 N.W.2d 720 (Knight Bros., Inc. v. State) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Knight Bros., Inc. v. State, 199 N.W.2d 720, 189 Neb. 64, 1972 Neb. LEXIS 657 (Neb. 1972).

Opinion

Clinton, J.

This action originated with a claim arising out of a contract of the plaintiffs with the Department of Roads of the State of Nebraska, which claim was filed under the provisions of section 77-2406, R. R. S. 1943. The claim was disallowed. Appeal was then made under section 77-2407, R. R. S. 1943, to the district court for Lancaster County which found for the defendant. The plaintiffs then perfected their appeal to this court.

The plaintiffs, a corporation and a partnership, respectively, were as joint venturers the successful bidders for the construction of work under Federal Aid Interstate Project No. I 80-4(26) in Lincoln County, Nebraska, and on February 18, 1965, entered into the contract with the State of Nebraska. Insofar as is here *66 immediately pertinent the plaintiffs under the provisions of the contract were to place and compact approximately 2,560,000 cubic yards of embankment material for a 7.902-mile segment of Interstate 80 southeast of North Platte, Nebraska, at a price of 29.5 cents for each cubic yard of such materials, measured in the embankment. The plaintiffs completed the work and were paid for the placement of the material in the embankment at the contract price.

This cause of action is founded upon certain purportedly false representations allegedly 'knowingly or negligently made by the State in the contract documents as to the quantity and quality of the material available in certain borrow pits referred to' in the specifications. Plaintiffs alleged in their petition that the claimed representations were made by the State with the intent that the bidders rely thereon and that the plaintiffs did in making their bid and in entering into the contract rely thereon. The plaintiffs further claim that the quantities, were insufficient and the material in one certain pit did not meet specifications.

The position of the plaintiffs may be succinctly stated by the following quotations from their brief: “On the quantity issue, it is the Plaintiffs’ position that it was the intent of the State and the understanding of the Plaintiffs that the five pits shown on the plans would provide sufficient material to complete the project; and that if they did not, the contract documents, contemplated and required that the State pay the Plaintiffs the extra costs incurred in procuring the necessary additional material from other sources. A subsidiary issue is the Plaintiffs’ claim that it was also the intent and understanding that material from certain of the designated pits would be utilized for specific segments of the embankment. . . .

“On the issue of the substandard quality of the material in one of the pits, ... it is the Plaintiffs’ position that the proper test to be applied in determining whether *67 the material in that pit was ‘acceptable in general’ and, hence, fulfilled the State’s representations, was not whether the State ultimately authorized and directed its use in the embankment, but rather, whether the material that was ,so used, in fact, met (or could be made to meet) the quality standards prescribed by the specifications; and that the testimony of the State’s own witnesses established that the difficult to excavate and manipulate material from that pit that was used in the embankment was cohesive rather than granular in character, and did not meet, and could not be made to meet, the quality standards upon which the Plaintiffs’ bid was based and the contract awarded. -
“It is also the Plaintiffs’ position that when the substandard character of that pit was discovered, it was the State’s duty, under Paragraph 5 of Article 6.02 of the Standard Specifications, to authorize the Plaintiff to abandon it, and procure material that would meet the specifications from other sources, and to reimburse the Plaintiffs, for the extra costs incurred in so doing. It is the Plaintiffs’ position that the State’s refusal to authorize the abandonment was also a breach of the contract for which the Plaintiffs are entitled to recover their resultant damages.”

The State denied making false representations as to quality or quantity; denied reliance by 'the plaintiffs- and alleged full knowledge on the part of the plaintiffs; and alleged that the quantities and qualities were sufficient, that the plaintiffs, did only what the contract provided, and that the prolongation of the work was caused-by the plaintiffs’ improper procedures.

The trial court found generally for the defendant and against the plaintiffs; that there were no misrepresentations; that paragraph 4 of Article 6.02 of the Standard Specifications was the governing provision of the contract; that the joint venture suffered substantial loss in the performance of the contract but it was unnecessary to determine the amount of loss because the defendant *68 was not liable; and then dismissed the plaintiffs’ petition. We affirm the order of the trial court.

In order to convey an adequate understanding of the issues and the contentions of the parties it is necessary to set forth by quotation, or in summary, pertinent contract provisions. The contract consists of a 2-page executed agreement which incorporates numerous documents. Included among these is the proposal. The proposal provides: “We have carefully examined the plans and specifications for the work contemplated in this proposal and we have made a personal examination of the site and have inquired into the local conditions affecting the work. We propose to furnish all the necessary equipment, machinery, tools, apparatus, and other means of construction and to do all the work and to furnish all the materials to complete the work in accordance with the plans and specifications on file for the schedule of prices listed in this proposal.” (Emphasis supplied.)

Also included are the State of Nebraska 1965 Standard Specifications for Highway Construction. Article 2.07 provides: “Article 2.07 — Examination of Plans, Specifications, Special Provisions, and Site of Work

“The bidder is required to examine carefully the site, and the proposal, plans, specifications, special provisions, and contract form, for the work contemplated, and it will be assumed that the bidder has investigated and is satisfied as to the conditions to be encountered, as to the character, quality, and quantities of work to be performed and materials to be furnished, and as to the requirements of these specifications, the special provisions, and contract. It is mutually agreed that the submission of a proposal shall be considered prima facie evidence that the bidder has made .such examination.” (Emphasis supplied.)

Article 6.02 of that document is in part as follows: “Article 6.02 — Designated Local Material Sources

“1. Sources of local materials may be designated and *69 described in the plans and special provisions. The quality of material in such deposits will be acceptable in general, but the contractor shall determine for himself the amount of selective excavation, blending, screening, mixing, and other work required to provide a finished product meeting the specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pawnee Plastics, Inc. v. American Savings Co.
313 N.W.2d 262 (Nebraska Supreme Court, 1981)
Rieschick Drilling Co. v. American Casualty Co.
303 N.W.2d 264 (Nebraska Supreme Court, 1981)
Lovelace v. Stern
297 N.W.2d 160 (Nebraska Supreme Court, 1980)
Hansen v. Circle Lake Development Corp.
260 N.W.2d 609 (Nebraska Supreme Court, 1977)
Don J. McMurray Co. v. Wiesman
260 N.W.2d 196 (Nebraska Supreme Court, 1977)
Spencer-O'Neill House, Inc. v. Denbeck
243 N.W.2d 767 (Nebraska Supreme Court, 1976)
Frank McGill, Inc. v. Nucor Corp.
238 N.W.2d 894 (Nebraska Supreme Court, 1976)
Burhoop v. Pegram
234 N.W.2d 828 (Nebraska Supreme Court, 1975)
Rutherford v. Chief Industries, Inc.
223 N.W.2d 838 (Nebraska Supreme Court, 1974)
Hays v. County of Douglas
223 N.W.2d 143 (Nebraska Supreme Court, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
199 N.W.2d 720, 189 Neb. 64, 1972 Neb. LEXIS 657, Counsel Stack Legal Research, https://law.counselstack.com/opinion/knight-bros-inc-v-state-neb-1972.