Bates & Rogers Construction Co. v. United States

56 Ct. Cl. 49, 1921 U.S. Ct. Cl. LEXIS 250, 1921 WL 1238
CourtUnited States Court of Claims
DecidedFebruary 7, 1921
DocketNo. 33958
StatusPublished
Cited by3 cases

This text of 56 Ct. Cl. 49 (Bates & Rogers Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bates & Rogers Construction Co. v. United States, 56 Ct. Cl. 49, 1921 U.S. Ct. Cl. LEXIS 250, 1921 WL 1238 (cc 1921).

Opinion

Campbell, Chief Justice,

delivered the opinion of the court:

The plaintiff made a contract to do all the work and furnish the material for the construction of Lock and Dam No. 29 in the Ohio-River, at unit prices. Among other requirements was certain excavation or dredging, for which the prices were fixed in the contract at 65 cents per cubic yard for “common excavation” and $8.60 per cubic yard for “ rock excavation.” The specifications provided for the classification of excavation into these two kinds and that “ common excavation shall include all material that can be removed with pick or shovel or by dipper dredge without blasting,” and that “ rock excavation shall include bowlders exceeding 9 cubic feet in volume and material requiring blasting for removal.” Logs, snags, and stumps were encountered in the early stages of the work, which were paid for as “common excavation” and were so classified in the monthly estimates made by the officer in charge, upon which the payments were predicated. The plaintiff claims that this classification was erroneous and seeks to recover the alleged cost of removing the logs, stumps, and snags, the excavation of which it is claimed was more . difficult and expensive than either “ common excavation,” properly considered, or “ rock excavation.”

The specifications provide that “ in all cases of disagreement on matters relating to material or work, the decision of the contracting officer shall be final.”

Section 8 of the contract provides:

‘‘No claim whatever shall at any time be made upon the United States by the contractor for or on account of any extra work or material performed or furnished, or alleged to have been performed or. furnished under or by virtue of this contract, and not expressly bargained for and specifically included therein, unless such extra work or material shall have been expressly required in writing by the [57]*57contracting officer, the prices and quantities thereof having been first agreed upon by the contracting parties and approved by the Chief of Engineers.”

The contract was awarded to plaintiff, under competitive bidding, in March, 1911. It became effective upon approval by the Chief of Engineers, in April, 1911. Work was begun in June, 1911, and was prosecuted actively for six months or more in 1911, for about the same period of time in each of the years 1912 and 1913, and for some months in 1914, being completed in October of the last-named year. For the work done during each of these months estimates were prepared, a retained percentage of 10 per cent of the several estimates was deducted, until the aggregate of the retentions amounted to the $40,000 mentioned in the contract, and payments were made accordingly. During all of that period the plaintiff received the payments without protest or objection, so far as the record discloses. When the final estimate was prepared in 1915, which included the amount of $40,000 that had been retained under section 20 of the specifications, the plaintiff insisted he was entitled to the additional sum here sued for, and he accepted the final voucher under protest with the announced purpose of suing for the amount claimed.

No bad faith is imputed to the officer making the classification, no objection to his classification was asserted when it was made, and if the material was not properly to be classed as either common or rock excavation there should have been a timely objection to the officer’s action. This would have enabled the parties to consider what course was to be taken in view of section 8, above quoted, of the contract. All of the work was upon the basis of unit prices, and when a character of excavation was found which plaintiff thought was not comprehended within the defined terms of the contract it became his duty to assert his claim to the end that the officer of the Government, acting for it, could consider what, if anything additional, should be paid, or what, if any, reclassification should be made. If the plaintiff did work which he did not contract to do it is too late to assert the fact after receiving payments based upon contract prices without objection or protest, and without an [58]*58observance of positive provisions of the contract. Plumley Case, 226 U. S., 545, 547; Wells Brothers Case, 254 U. S., 83; Gleason Case, 175 U. S., 588, 602.

While claiming, in the alternative, the alleged expense of removing the logs, snags, and stumps, the plaintiff’s claim is based upon a different theory than that suggested above, and states the question upon his brief as follows:

“ There is but a single issue: The right of the contractor to payment on a fair basis for the excavation or removal of certain snags, logs, and stumps not shown on the contract drawings or in the specifications, although the existence of same was known to the defendant.”

The proposition thus stated would apparently pretermit any inquiry into the question of plaintiff’s knowledge ot conditions, or of the means of knowledge, open alike to both parties, or of any duty upon the plaintiff to investigate for himself or to seek information or even to inquire of the defendant as to the extent of its knowledge or information; but without admitting the accuracy of a rule so broadly stated as it is by plaintiff, we think the evidence fails to show any misrepresentation by defendant or any warranty of conditions to be encountered, or a concealment that could be a misrepresentation or the basis of an action.

As already stated, the plaintiff’s contract was let in March, 1911. Prior thereto, in September, 1909, Government engineers had made certain borings — 36 in number — preliminary to the location of the proposed lock and dam, and for the purpose of determining tentatively upon an advantageous site. These are known as “preliminary borings,” and are to be distinguished from the final borings subsequently made. A record was kept of what these preliminary borings disclosed. At one of them, the location of which can not be determined, the record disclosed that a “ log next to rock ” was found. Having decided upon the location the engineers, in November, 1909, made what was called final borings, 42 in number, extending along the proposed lines of the two walls and guide walls of the lock and the upper and lower sides of the dam and abutment. The lock was located on the Kentucky side of the river. The dam extended across the river, and there were abutment walls on the Ohio side. The [59]*59land wall of the lock and its guide walls together extended about 1,800 feet up and down the river, the river wall of the lock was about 600 feet long, the dam proper was about 1,100 feet long, and the abutment wall was several hundred feet long. The borings were approximately 100 feet apart, except along the upper line of the dam they were 200 feet apart, and similarly along its lower line, but so “ staggered ” that they were approximately 100 feet apart, the distance between the two lines being about 29 feet. The results of these final borings were shown upon drawings. There can be no question that the drawings accurately portrayed all that these borings disclosed. A slight exception to this latter statement may be made in the fact that one of the final bor-ings disclosed “ wood and coal ” for about 6 inches, not shown on the drawings. But that fact is immaterial, because the boring was in the line of the dam several hundred feet from the places of which complaint is made, and does not appear to have caused any trouble.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Knight Bros., Inc. v. State
199 N.W.2d 720 (Nebraska Supreme Court, 1972)
The Len Company and Associates v. The United States
385 F.2d 438 (Court of Claims, 1967)
Kansas City Bridge Co. v. State
250 N.W. 343 (South Dakota Supreme Court, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
56 Ct. Cl. 49, 1921 U.S. Ct. Cl. LEXIS 250, 1921 WL 1238, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bates-rogers-construction-co-v-united-states-cc-1921.