The Len Company and Associates v. The United States

385 F.2d 438, 181 Ct. Cl. 29, 1967 U.S. Ct. Cl. LEXIS 133
CourtUnited States Court of Claims
DecidedOctober 13, 1967
Docket257-63
StatusPublished
Cited by72 cases

This text of 385 F.2d 438 (The Len Company and Associates v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Len Company and Associates v. The United States, 385 F.2d 438, 181 Ct. Cl. 29, 1967 U.S. Ct. Cl. LEXIS 133 (cc 1967).

Opinion

DAVIS, Judge:

This is another Government contract case in which the key question is whether the trial of the contractor’s claims *440 shall be held administratively or in court. Cf. New York Shipbuilding Corp. v. United States, 385 F.2d 427, 180 Ct.Cl. - (June 1967); Universal Ecsco Corp. v. United States, Ct.Cl. 385 F.2d 421, decided this day. In August 1958 the Len Company entered into a Capehart Act housing contract with the Navy for 650 housing units at Pearl Harbor. As was customary for such projects, the work was divided into separate mortgage areas, the contract was made severable as to each area, and mortgagor-builders were appointed. 1 ******During the progress of construction on the seven units, periodic inspections were made and certificates of acceptable work and materials issued. When the work was well advanced, the Navy’s contracting officer was replaced. The new official called for various reinspections and then found that several elements of the job did not conform, in his view, with the plans and specifications. The result tyas that plaintiff had to alter considerable portions of completed work.

Fifteen of the seventeen counts in the petition relate to the work done pursuant to these reinspection orders. Counts I-XIII and XVI (the reinspection claims) broadly urge that this work was not required by the contract but was extra. Count XVII, the most significant financially (amounting to almost one-half of the total relief requested), is a conventional “delay-damages” claim for detriment occurring because of this allegedly extra work. The remaining claims, Counts XIV and XV, are not directed to the reinspection but involve disputes as to the correct equitable adjustment on account of two separate formal changes in the contractual requirements.

The parties acknowledge that Counts XIV and XV are redressable under the “Changes and Changed Conditions” clause (Article 9 of the general provisions) and, taken alone, would ordinarily be subjected to the administrative procedure established by that provision. It is also agreed that Count XVII for delay damages is a breach-of-contract demand which, to the extent its facts differ from previously-litigated claims arising under the contract, should be tried in this court. 2 See United States v. Utah Constr. & Mining Co., 384 U.S. 394, 418-422, 86 S.Ct. 1545, 16 L.Ed.2d 642 (1966); Morrison-Knudsen Co. v. United States, 345 F.2d 833, 837-838, 170 Ct.Cl. 757, 764 (1965); J. D. Hedin Constr. Co. v. United States, 347 F.2d 235, 241, 171 Ct.Cl. 70, 77 (1965). The real controversy is over the disposition of the reinspection claims (Counts I-XIII and XVI), and whether the hair (Counts XIV, XV, and XVII) should follow the hide.

Each of the reinspection claims concerns work accomplished, but assertedly not paid for, during construction in the seven mortgage areas. As each of these units was completed, the contractor sought releases with permission to except its claims for additional work. The contracting officer (the Navy District Public Works Officer) refused to allow exceptions as to any one unit until all seven were finished. In August 1960, upon completion of the housing in the last mortgage area, plaintiff presented its claims for extra compensation. The contracting officer held that these claims *441 could be processed only under the change-request procedure detailed in General Provision No. 9 of the contract, “Changes and Changed Conditions”. The claims were thus submitted, processed, and denied by the Public Works Officer in November 1960.

Shortly thereafter, the contracting officer initiated eleven “change requests” for deductive change orders — work which varied from the contract terms and which, in the Government’s view, called for a price reduction. Plaintiff submitted its countering estimates and argument. In December the contracting officer determined that the Government was entitled to a credit. Under the “Changes” clause procedure, the contracting officer forwarded both sets of requests with his “recommendations” (denying all of the company’s requests and granting partial relief on the deductive requests he had initiated) to the Federal Housing Administration. That Administration’s District Director acknowledged that his review of the change requests was limited by “outstanding instructions” — agreed to by his agency and the Defense Department — “whereby FHA accepts the amounts recommended and certified by the contracting officer.” 3 Accordingly, he accepted the contracting officer’s recommendation with respect to each claim, thereby denying all but three of the change-requests. Of the three confirmed changes, two resulted in decreases in the contract price (i. e., credits to the Government) and the other in an increase, but not as substantial as sought by plaintiff. After the FHA’s action, the last mortgage area was closed and the contractor received the remaining portion of the proceeds from the seven mortgages.

Prior to the FHA decision, the contractor, which had learned of the District Public Works Officer’s unfavorable recommendation, filed an appeal with the Secretary of the Navy. The case was referred to the Armed Services Board of Contract Appeals, where the Government moved to dismiss for lack of jurisdiction. The motion was granted and the appeal dismissed in September 1962. Len Co. & Associates, 1962 B.C.A. ¶ 3498 (No. 7151). The Board concluded that it could not hear the merits of the dispute because the contractor had already received a decision from the FHA in accordance with the contract’s terms.

In September 1963 plaintiff filed its petition in this court. The defendant, in March 1966, moved to suspend proceedings to allow the parties to return to the ASBCA or the FHA for complete administrative determination of disputed factual questions on the reinspection claims. The trial commissioner first denied the motion, without prejudice, on the authority of Anthony Grace & Sons, Inc. v. United States, 345 F.2d 808, 170 Ct.Cl. 688 (1965). After the Supreme Court’s reversal of that decision (384 U.S. 424, 83 S.Ct. 1539, 16 L.Ed.2d 662 (1966)), the denial was rescinded and the motion restored to the docket. The parties sought to agree upon removal of the case to the Armed Services Board without a formal order. Attempts to amend the “Disputes” clause or to enter into a stipulation failed. The trial commissioner then denied the Government’s motion, holding that in the circumstances a de novo trial in this court would be proper. The case is before us on the defendant’s request to review that ruling.

I

Free access — add to your briefcase to read the full text and ask questions with AI

Related

OSC Solutions, Inc.
Armed Services Board of Contract Appeals, 2023
Trade West Construction, Inc.
Armed Services Board of Contract Appeals, 2020
weston/bean Joint Venture v. United States
123 Fed. Cl. 341 (Federal Claims, 2015)
Retirement Communities LLC v. United States
92 Fed. Cl. 587 (Federal Claims, 2010)
LB&B Associates Inc. v. United States
91 Fed. Cl. 142 (Federal Claims, 2010)
Metric Construction Co. v. United States
81 Fed. Cl. 804 (Federal Claims, 2008)
Information Systems & Networks, Corp. v. United States
81 Fed. Cl. 740 (Federal Claims, 2008)
M.A. DeAtley Construction, Inc. v. United States
71 Fed. Cl. 370 (Federal Claims, 2006)
ACE Constructors, Inc. v. United States
70 Fed. Cl. 253 (Federal Claims, 2006)
Engineered Demolition, Inc. v. United States
70 Fed. Cl. 580 (Federal Claims, 2006)
Tecom, Inc. v. United States
66 Fed. Cl. 736 (Federal Claims, 2005)
Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)
Flink/Vulcan v. United States
63 Fed. Cl. 292 (Federal Claims, 2004)
P.R. Burke Corp. v. United States
58 Fed. Cl. 549 (Federal Claims, 2003)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
Navcom Defense Electronics, Inc. v. England
53 F. App'x 897 (Federal Circuit, 2002)
Doninger Metal Products, Corp. v. United States
50 Fed. Cl. 110 (Federal Claims, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
385 F.2d 438, 181 Ct. Cl. 29, 1967 U.S. Ct. Cl. LEXIS 133, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-len-company-and-associates-v-the-united-states-cc-1967.