ACE Constructors, Inc. v. United States

70 Fed. Cl. 253, 2006 U.S. Claims LEXIS 87, 2006 WL 950201
CourtUnited States Court of Federal Claims
DecidedMarch 31, 2006
DocketNo. 04-299C
StatusPublished
Cited by36 cases

This text of 70 Fed. Cl. 253 (ACE Constructors, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ACE Constructors, Inc. v. United States, 70 Fed. Cl. 253, 2006 U.S. Claims LEXIS 87, 2006 WL 950201 (uscfc 2006).

Opinion

OPINION AND ORDER

LETTOW, Judge.

In this contract ease, the court conducted a 5-day trial on October 17 through 21, 2005, in El Paso, Texas. Plaintiff ACE Constructors, Inc. (“ACE”) contracted with the United States Army Corps of Engineers (“the Corps”) to construct the Ammo Ho1>-Load Facility at Biggs Army Airfield, Fort Bliss, El Paso, TX. That facility consists primarily of a roadway, a storage pad, a loading apron, and a taxiway that is connected with the main runway at Biggs Army Airfield, and it enables munitions to be transferred onto cargo aircraft for transport. ACE claims that it was required to perform work not envisioned in the Contract due to unexpected site conditions resulting from an inaccurate survey of the site, errors and omissions in the contract drawings and specifications, and the Corps’ failure properly to administer the Contract. ACE seeks equitable adjustments to recover the costs associated with this extra work. ACE also seeks to recover additional costs that were incurred by its paving subcontractor, Cambro Construction Company, Inc. (“Cambro”), as a result of alleged defects in the contractual documents and the Corps’ failure properly to administer the Contract. In addition, ACE seeks to recover liquidated damages that were imposed by the Corps as a result of delays in project completion caused by the extra work. ACE avers that the government, not ACE, was responsible for the delays and therefore ACE should not have been required to pay the liquidated damages. ACE seeks an award of $1,822,146.39 in total compensation and return of liquidated damages, together with interest on this sum, in accord with the Contract Disputes Act (“CDA”), 41 U.S.C. §§ 601-613. Additionally, ACE seeks to recover attorney’s fees and costs under the Equal Access to Justice Act, 28 U.S.C. § 2412.

Liability, entitlement to equitable adjustments, and damages remain unresolved in this contract case. To adjudicate the issues of fact respecting liability and calculation of equitable adjustments and damages, the court conducted a trial in El Paso and in that connection visited and examined the Ammo Hot-Load Facility. Post-trial briefs were filed thereafter, and a closing argument was held on February 2, 2006. The case is now ready for disposition.

For the reasons set forth below, the court finds the government liable for differing site conditions, defective specifications, and a constructive change to the Contract, and also finds that the government wrongfully assessed liquidated damages against ACE. The court finds that ACE is entitled to an equitable adjustment to the Contract in the amount of $1,383,009.97 and to recovery of liquidated damages assessed by the government in the amount of $246,130. ACE is entitled to recover interest on these awarded amounts pursuant to Section 12 of the CDA, 41 U.S.C. § 611. Furthermore, the court concludes that ACE may be entitled to costs and attorney’s fees under the Equal Access to Justice Act, 28 U.S.C. § 2412, but reserves a final determination in that regard pending completion of further proceedings under Rules 54(d) and 58(c) of the Rules of the Court of Federal Claims (“RCFC”). See also RCFC Appendix of Forms, Form 5.

FACTS1

1. The Solicitation.

On July 14, 2000, the Corps issued Solicitation No. DACA63-00-B-0023 for construction of the Ammo Hot-Load Facility. The Solicitation consisted of the primary solicitation document as well as two packets of architectural and engineering plans. See PX 177 (Contract No. DACA63-00-C-0025, Specifications for Ammo Hot-Load Area, Project No. 44921 (July 2000)); PX 178 (Plans for Solicitation No. DACA63-00-B-0023 (June 13, 2000) (“Original Plans”)); PX 179 (Amendment Number 2 Drawings (July [258]*25831, 2000) (“Amended Plans”)).2 Upon the award of the Contract to ACE, the solicitation documents were incorporated into the Contract. See PX 177 (Contract No. DACA63-00-C-0025 (Sept. 27, 2000) (“ACE Contract” or “Contract”)). The plans, PX 178 and PX 179, were prepared by the engineering firm of Crawford, Murphy, and Tilly, Inc. (“Crawford Murphy”) for the Corps.

The project entailed construction of a concrete loading apron approximately 9.5 acres in size where munitions are loaded onto large cargo aircraft (primarily C-5As). To the south of the loading apron, construction of a concrete aircraft taxiway approximately 1,500 feet in length was required to connect the loading apron with the main runway at Biggs Army Airfield. PX 178 Seq. Nos. 1-3, 45; see also Stipulations of Fact (“Stip.”) H 2. To the north, the apron is connected by a short roadway to a concrete pallet storage area approximately two acres in size bearing a substantial shelter where munitions can be stored after delivery via trucks while awaiting loading onto aircraft. Tr. 214:23 to 215:2 (Test, of John Fulkerson, President of ACE). To the north of the pallet storage area, construction of an asphalt road approximately 1.3 miles in length enables vehicular traffic to reach the storage pad from a preexisting access road to the north. In addition to building the taxiway, loading apron, storage pad, and access road, the project required the contractor to reconstruct a segment of the main runway to join the taxiway, excavate and grade drainage ditches and two drainage impoundments running along each side of the access road and around the storage pad and loading apron, Stip. 112, and install water and electrical lines and light poles. Tr. 215:4-6 (Test, of Fulkerson).

The Solicitation was designated as a “100% Small Business Set-Aside Solicitation.” PX 177. ACE, which qualified as a small business, submitted its bid on the project on August 23, 2000. Id.; see id. at 00010-3 to 00600-7.

The plans provided by the Corps for the Ammo Hot-Load Facility superimposed the elevations that would be required for the finished project over an aerial topographical survey of the site. See PX 178 (Original Plans) Seq. Nos. 24-29 (overlaying the grading plan onto the aerially-surveyed contours of the site), 34-41 (comparing aerially-surveyed grades with the planned level of the finished subgrades), 54-57 (comparing aerially-surveyed grades with finished grades), 66-88 (showing cross-sections of the site at 20-meter intervals, and indicating the amount of cut or fill that would be needed at each cross-section based upon the aerial survey and planned finished elevations). These plans provided potential contractors with the magnitude of cutting and filling that would be required to reach the final elevations shown on the plan documents. From the plans, bidders could project whether the project would generate excess soil or would require importation of fill from off-site. Based on the plans provided by the Corps and on the aerial survey, ACE estimated in preparing its bid that the project would approach being a “balanced” job,3 producing a moderate excess of excavated dirt. Tr. 234:1-5, 527:5 to 528:9 (Test, of Fulkerson).4

The loading apron, storage area, and taxiway were to be constructed of concrete poured in lanes, surrounded on the perimeter by asphalt shoulders.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harry Pepper and Associates, Inc.
Armed Services Board of Contract Appeals, 2020
Nussbaum v. United States
Federal Claims, 2019
ABS Development Corporation
Armed Services Board of Contract Appeals, 2019
Gazpromneft-Aero Kyrgyzstan LLC v. United States
132 Fed. Cl. 202 (Federal Claims, 2017)
Montano Electrical Contractor v. United States
114 Fed. Cl. 675 (Federal Claims, 2014)
Kellogg Brown & Root Services, Inc. v. United States
728 F.3d 1348 (Federal Circuit, 2013)
Parker Excavating, Inc. v. City & County of Denver
2012 COA 180 (Colorado Court of Appeals, 2012)
Kellogg Brown & Root Services Inc. v. United States
103 Fed. Cl. 714 (Federal Claims, 2012)
Metcalf Construction Co. v. United States
102 Fed. Cl. 334 (Federal Claims, 2011)
Redland Co. v. United States
97 Fed. Cl. 736 (Federal Claims, 2011)
Scott Timber Co. v. United States
97 Fed. Cl. 685 (Federal Claims, 2011)
Pch Mut. Ins. Co., Inc. v. Casualty & Surety, Inc.
750 F. Supp. 2d 125 (District of Columbia, 2010)
Wisconsin Electric Power Co. v. United States
90 Fed. Cl. 714 (Federal Claims, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
70 Fed. Cl. 253, 2006 U.S. Claims LEXIS 87, 2006 WL 950201, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ace-constructors-inc-v-united-states-uscfc-2006.