Nussbaum v. United States

CourtUnited States Court of Federal Claims
DecidedSeptember 20, 2019
Docket19-376
StatusPublished

This text of Nussbaum v. United States (Nussbaum v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nussbaum v. United States, (uscfc 2019).

Opinion

3Jn tbe Wniteb ~tates C!Court of jfeberal C!Claims No. 19-376C (Filed: September 20, 2019)

) THOMAS NUSSBAUM, ) Contract dispute subject to the Contract ) Disputes Act, 41 U.S.C. §§ 7101-7109; Plaintiff, ) timeliness; equitable tolling ) v. ) ) UNITED STATES, ) ) Defendant. ) --------------)

Thomas Nussbaum, prose, Millbrae, California.

Sonia Orfield, Trial Attorney, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, D.C., for defendant. With her on the briefs were Joseph H. Hunt, Assistant Attorney General, Civil Division, Robert E. Kirschman, Jr., Director, and Deborah A. Bynum, Assistant Director, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, D.C.

OPINION AND ORDER

LETTOW, Senior Judge.

Plaintiff Thomas Nussbaum has brought suit against the United States acting through the Federal Bureau of Prisons ("Bureau" or "Bureau of Prisons"), alleging that the Bureau failed to pay him in full for work done to replace boilers at the Federal Correction Institution, Victorville, California ("Victorville"). Comp!. at 5. Mr. Nussbaum seeks $201,735 in damages and lost profits, plus interest and attorneys' fees and costs. Comp!. at 19-20.

Mr. Nussbaum filed his complaint in March 2019. He alleges four counts against the Bureau of Prisons: (1) fraudulent and intentional misrepresentation when Victorville induced him to believe his bid was accepted or that he would be a sub-contractor on a bonded construction contract but was instead made a sub-supplier without a bond on an impermissible purchase order, Comp!. at 15-16; (2) negligent misrepresentation on the same premise, Comp!. at 16; (3) a breach of the implied covenant of good faith and fair dealing for the misrepresentations and for engaging in improper procurement practices, Comp!. at 16; and (4) unjust enrichment for not paying for labor and parts supplied by Mr. Nussbaum, Comp!. at 17. Mr. Nussbaum's damages consist of $45,000 for being induced improperly by the Bureau and prime contractor, Cal Inc., to lower his bid, $62,113 for uncompensated work requested and performed by the Bureau that was outside the original contract, $80,375 for costs incurred due to actions of the prime contractor that necessitated Mr. Nussbaum to perform extra work and bring lawsuits against several subcontractors and the prime contractor, and $14,247 for lost profit at a rate of 15% on the $63,133 in change orders and $37,806 in extra work necessitated by actions of the prime contractor. Comp!. at 17-19. Mr. Nussbaum provided 19 exhibits, which consisted of, among other things, the solicitation, the contract, various letters sent by Mr. Nussbaum to the contractor, Cal Inc., and the Bureau of Prisons disputing work performance or payments, invoices for Mr. Nussbaum's expenses for the project, and an investigation by the Bureau of Prisons into Mr. Nussbaum 's allegations of improper procurement practices by the Bureau relating to his work. Comp!. Exs. 1-19 .1

Pending before the court is the government's motion to dismiss Mr. Nussbaum's complaint for lack of subject-matter jurisdiction. Def. 's Mot. to Dismiss ("Def. 's Mot."), ECF No. 12. The government contends that Mr. Nussbaum's complaint is barred by the six-year statute of limitations prescribed under 28 U.S.C. § 2501 and that Mr. Nussbaum, as a sub- supplier, lacks standing to sue the government. See generally Def. 's Mot. Mr. Nussbaum has responded in opposition, see Pl.'s Opp'n to Def.'s Mot. to Dismiss ("Pl.'s Opp'n."), ECF No. 15, and defendant has filed a reply, see Def.'s Reply to Pl.'s Response ("Def.'s Reply"), ECF No. 17. A hearing was held on August 29, 2019. See Hr' g Tr. 3 :4 to 29:3 (Aug. 29, 2019). 2

The court concludes that Mr. Nussbaum's complaint falls outside the statute of limitations imposed on claims arising under the Contract Disputes Act ("CDA''), 41 U.S.C. §§ 7101-7109. But because the statute of limitations under that Act does not go to jurisdiction and may be equitably tolled, the court addresses the standard for equitable tolling. In that respect, the court finds that Mr. Nussbaum has not satisfied the exacting standard for equitable tolling, and thus the court dismisses his suit for failure to state a claim upon which relief can be granted under the CDA.

BACKGROUND 3

A. Contract Solicitation Process

Mr. Nussbaum supplied Victorville with two central plant boilers in 2000. Comp!. at 9. At that time, Mr. Nussbaum had quoted $200,000 to change the burners to comply with certain nitrogen oxide emission requirements, but Victorville opted instead to implement a Selective Catalytic Reduction ("SCR") system, which Mr. Nussbaum alleges cost over $1 million. Comp!. at 9. Despite its cost, the SCR system failed to meet the emission standards, requiring Victorville to implement upgrades that would. Comp!. at 9.

Accordingly, during the fall of 2001, Victorville solicited bids for a construction project to upgrade the two existing boilers and install a new, third boiler. Comp!. Ex. 1 at 2. Mr. Nussbaum and two other companies submitted bids. See Comp!. Ex. 1 at 2. The lowest of the three, Mr. Nussbaum offered to complete the project for $320,000. Comp!. Ex. 12 at 2. The

1 Some of Mr. Nussbaum's exhibits are individually numbered, but because others are not individually paginated, citations to page numbers refer to the page markings as assigned by the court's Electronic Filing System. 2 The date will be omitted from further citations to the hearing transcript. 3 This background does not constitute findings of fact by the court. Rather, its sole purpose is to provide context for an analysis of the government's motion to dismiss. 2 other bidders were Southern California Boiler, Inc. and Automatic Boiler Company, which had bid $331,130 and $343,386, respectively. Comp!. Ex. 14 at 2-7.

Mike Fief, Victorville's General Foreman, informed Mr. Nussbaum on November 21, 2001 that he "would really like to see the bid go to Cal Inc." because he had an ongoing working relationship with them. Comp!. Ex. 11 at 2. Cal Inc. had not bid on the project but it did have a preexisting Schedule Contract with General Services Administration ("GSA") to provide environmental services. Comp!. at 6. Consequently, Mr. Nussbaum's quote was forwarded to Cal Inc., which, upon receipt of the bid, made some modifications to his proposals and requested that he re-quote his price based on those changes. See Comp!. at 17. Mr. Nussbaum did not think the alterations would meet the required emission standards, but he lowered his price from $320,000 to $275,000 on the understanding that Cal Inc. had Victorville's authority to make the changes. See Comp!. at 17.

Victorville then arranged for Cal Inc. to "broker" the project under its Schedule Contract while Mr. Nussbaum supplied materials and performed the actual construction work. Comp!. at 6. To that end, Victorville's Contracting Officer, Contigny Arakaki, issued a purchase order to Cal Inc. for a total price of$398,141. Comp!. at 6. The use ofa purchase order for this project was "improper," Mr. Nussbaum alleges, because purchase orders are disallowed for construction work. Comp!. at 6, 8. Moreover, the amount of the purchase order issued to Cal Inc. exceeded Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sheldon v. Sill
49 U.S. 441 (Supreme Court, 1850)
Ex Parte McCardle
74 U.S. 506 (Supreme Court, 1869)
United States v. Testan
424 U.S. 392 (Supreme Court, 1976)
Hughes v. Rowe
449 U.S. 5 (Supreme Court, 1980)
Papasan v. Allain
478 U.S. 265 (Supreme Court, 1986)
Christianson v. Colt Industries Operating Corp.
486 U.S. 800 (Supreme Court, 1988)
Irwin v. Department of Veterans Affairs
498 U.S. 89 (Supreme Court, 1991)
Arbaugh v. Y & H Corp.
546 U.S. 500 (Supreme Court, 2006)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Henderson v. Shinseki
131 S. Ct. 1197 (Supreme Court, 2011)
Cambridge v. United States
558 F.3d 1331 (Federal Circuit, 2009)
Ace Constructors, Inc. v. United States
499 F.3d 1357 (Federal Circuit, 2007)
McZeal v. Sprint Nextel Corp.
501 F.3d 1354 (Federal Circuit, 2007)
Richard L. Thoen v. The United States
765 F.2d 1110 (Federal Circuit, 1985)
Donna Kelley v. Secretary, U.S. Department of Labor
812 F.2d 1378 (Federal Circuit, 1987)
Trusted Integration, Inc. v. United States
659 F.3d 1159 (Federal Circuit, 2011)
Donald A. Henke v. United States
60 F.3d 795 (Federal Circuit, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
Nussbaum v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nussbaum-v-united-states-uscfc-2019.