Ace Constructors, Inc. v. United States

499 F.3d 1357, 78 Fed. Cl. 1357, 2007 U.S. App. LEXIS 22309, 2007 WL 2713333
CourtCourt of Appeals for the Federal Circuit
DecidedSeptember 19, 2007
Docket2006-5093
StatusPublished
Cited by64 cases

This text of 499 F.3d 1357 (Ace Constructors, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ace Constructors, Inc. v. United States, 499 F.3d 1357, 78 Fed. Cl. 1357, 2007 U.S. App. LEXIS 22309, 2007 WL 2713333 (Fed. Cir. 2007).

Opinion

NEWMAN, Circuit Judge.

ACE Constructors, Inc. entered into a contract with the United States Army Corps of Engineers to build a structure *1360 designated the Ammo Hot-Load Facility, at Biggs Army Airfield at Fort Bliss in El Paso, Texas. Several disputes arose and, after a five-day trial, the Court of Federal Claims decided several issues in favor of ACE, awarded an equitable adjustment to ACE in the amount of $1,383,009 with statutory interest, and ordered the return of liquidated delay damages in the amount of $246,130. 1 On this appeal by the United States, we affirm the judgment of the Court of Federal Claims.

BACKGROUND

The facts are fully set forth in the trial court’s opinion. In brief, the project included construction of a loading area for cargo planes, various roadways, buildings, a storage pad, a loading apron, and a taxiway for airplanes. The site contained hills and other terrain that needed to be excavated, leveled, and filled. The bid solicitation materials included architectural drawings and engineering specifications prepared for the government by the engineering firm of Crawford, Murphy & Tilly, Inc., which plans were incorporated into the contract. The Court of Federal Claims found, and the government does not dispute, that certain drawings and specifications were incomplete and defective.

During performance ACE encountered numerous difficulties. ACE was required by the Corps of Engineers or by the actual conditions encountered to alter its construction procedures, and experienced significant additional costs. There were various contract modifications, delays, and changes to ACE’s roster of subcontractors. The project was ultimately completed to the government’s satisfaction, and ACE filed several claims for its additional costs based on the unforeseen conditions and defective specifications. The contracting officer granted some of ACE’s claims and denied others. ACE appealed to the Court of Federal Claims, as provided by the Contract Disputes Act, 41 U.S.C. § 605. That court provided additional relief. The government argues that ACE is not entitled to any additional recovery, and requests reversal of all of the relief granted by the Court of Federal Claims.

Standard of Review

Decisions of the Court of Federal Claims receive plenary review as to issues of law, and the court’s factual findings are reviewed for clear error. E.g., Adams v. United States, 350 F.3d 1216, 1221 (Fed. Cir.2003). The issues herein relate to contract interpretation, the role of the defective specifications, and the foreseeability of the problems encountered. In general the same contract law is applied when the government is party to a contract as applies to contracts between private parties. See Mobil Oil Exploration & Producing Southeast, Inc. v. United States, 530 U.S. 604, 607-08, 120 S.Ct. 2423, 147 L.Ed.2d 528 (2000) (“ ‘When the United States enters into contract relations, its rights and duties therein are governed generally by the law applicable to contracts between private individuals.’ ”) (quoting United States v. Winstar Corp., 518 U.S. 839, 895, 116 S.Ct. 2432, 135 L.Ed.2d 964 (1996)).

I

THE PROFILOGRAPH CLAIM

The contract set forth two methods of measuring the smoothness of the concrete paving, viz. straightedge testing and profilograph testing, the latter being the more expensive method. ACE testified to its belief that the use of profilographic testing was optional under the contract, and therefore that it used the straightedge method in calculating its bid. However, during contract performance the Corps required *1361 profilographic testing, which ACE performed under protest, until the Corps eventually agreed with ACE that the straightedge method was better suited to this project. The Court of Federal Claims awarded ACE its additional costs arising from use of the profilographic test method. The government presented three arguments as to why these costs should not be awarded: first, that the Court of Federal Claims lacked jurisdiction to review the contracting officer’s decision of this issue; second, that the contract required profilographic testing; and third, that ACE had not shown that it based its bid on straightedge testing. The government renews these arguments on this appeal.

A

With respect to jurisdiction of this issue, the government argues that ACE did not exhaust its administrative remedies before the contracting officer, and thus could not proceed in the Court of Federal Claims. The Contract Disputes Act, 41 U.S.C. § 605(a), requires that the contractor must have submitted the claim to a contracting officer, and that the contracting officer issued a final decision concerning that claim. See, e.g., England v. Swanson Group, Inc., 353 F.3d 1375, 1379 (Fed.Cir. 2004); Bath Iron Works Corp. v. United States, 20 F.3d 1567, 1578 (Fed.Cir.1994). The government argues that the claim as presented to the Court of Federal Claims was not identical to that before the contracting officer.

In Scott Timber Co. v. United States, 333 F.3d 1358 (Fed.Cir.2003) this court explained that the same claim must be presented to the Court of Federal Claims as was decided by the contracting officer, but that this standard “does not require rigid adherence to the exact language or structure of the original administrative CDA claim [when] they arise from the same operative facts, claim essentially the same relief, and merely assert differing legal theories for that recovery.” Id. at 1365. The Court of Federal Claims found, and we agree, that the claims before the contracting officer and the court did not differ significantly, for the claim concerning the use of profilograph testing was presented to the contracting officer based on the same contract provisions, the same requirements made by the Army Corps of Engineers, the same costs, the same requested relief, and the same legal theories. This claim was properly before the court.

B

As to the question of what the contract required, the Court of Federal Claims analyzed this issue in terms of “constructive change”; that is, whether the Army constructively altered the contract, either expressly or implicitly, by requiring performance at variance with that set forth in the contract. In contract interpretation, the plain meaning of the contract’s text controls unless it is apparent that some other meaning was intended and mutually understood.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
499 F.3d 1357, 78 Fed. Cl. 1357, 2007 U.S. App. LEXIS 22309, 2007 WL 2713333, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ace-constructors-inc-v-united-states-cafc-2007.