Bath Iron Works Corporation v. United States

20 F.3d 1567, 1994 WL 73993
CourtCourt of Appeals for the Federal Circuit
DecidedJune 6, 1994
Docket93-5119
StatusPublished
Cited by71 cases

This text of 20 F.3d 1567 (Bath Iron Works Corporation v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bath Iron Works Corporation v. United States, 20 F.3d 1567, 1994 WL 73993 (Fed. Cir. 1994).

Opinion

MICHEL, Circuit Judge.

The United States appeals from the November 12, 1992 order of the United States Court of Federal Claims (CFC), 27 Fed.Cl. 114 (1992), 1 denying its motion to dismiss Bath Iron Works Corporation’s (BIWs) claims for price adjustments under two shipbuilding contracts either for lack of subject matter jurisdiction, or, alternatively, for failure to state a claim upon which relief can be granted, because the claims were not submitted to the Contracting Officer (CO) within the 18-month time period of 10 U.S.C. § 2405 (1988). The CFC concluded that the time period of 10 U.S.C. § 2405 applied only to administrative proceedings before a Service Secretary. Consequently, the CFC held, the statute created no jurisdictional bar or statute of limitations to BIWs de novo suit under the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 601-613 (1988). Because we construe 10 U.S.C. § 2405 as applying only to the Secretary of a military department and administrative proceedings conducted under the Secretary’s authority, we hold that the statute creates neither a jurisdictional bar nor an affirmative defense to de novo adjudication of a CDA suit by the CFC. We therefore affirm.

BACKGROUND

A full account of the facts is set out in the opinion of the CFC in Bath Iron Works Corp. v. United States, 27 Fed.Cl. 114. Only those facts necessary for our disposition are recited herein.

A. The Dispute Between the Parties

BIW entered into a series of shipbuilding contracts with the Department of the Navy (Navy) in connection with the AEGIS Cruiser Program. The two contracts in dispute here, N00024-84-C-2005 (also known as the “CG 58 contract”) and N00024-85-C-2036 (also known as the “CG 60 contract”), were awarded to BIW on December 27, 1983 and November 26, 1984, respectively.

These contracts were subject to a number of engineering change proposals (ECPs) during their performance. The procedure employed in administrating the contracts up until August 1986 provided that after issuance of each ECP, an agreed price would be negotiated for each design change to be followed by the issuance of an Engineering Change Notice (ECN). The ECNs contained revisions to drawings and other information necessary to implement each ECP. BIW alleged that in a number of instances, the ECNs and drawings indicated a scope of work greater than that set out in the corresponding ECPs, and thus performance of the ECPs involved additional work and costs to BIW in excess of the negotiated price. Therefore, BIW asserted that it was entitled to price adjustments in the two contracts.

BIW first submitted a Request for Equitable Adjustment (REA) on November 3, 1986, seeking “an overall ■ increase in contract prices for the Cruiser Program resulting from various actions and inactions by the Navy which affected BIWs performance.” 27 Fed.Cl. at 118 (emphasis in original). Following negotiations with the Navy, BIW submitted a revised REA to the CO on May 18, 1987, which specifically identified the ECN issue, claiming increased costs of $4,166,000 for CG 58 and $1,167,000 for CG 60. Id. This revised REA did not include the certification required under the CDA, 41 U.S.C. § 605(c)(1), however. BIW submitted a second revised REA to the CO on February 17, 1988, claiming extra costs of $4,414,-634 for CG 58 and $1,182,358 for CG 60. Id. This second revised REA included the required certification language and was signed by William E. Graham, BIWs Vice President for Contracts. The government objected to this certification as defective under the statute because the vice president lacked the *1571 requisite authority to certify the claim. BIW then submitted a final revised claim on November 13, 1989, requesting costs of $4,052,-769 for CG 58 and $1,523,230 for CG 60. Id. at 119. The final revised claim was certified by D.D. Fitzgerald, the President and Chief Operating Officer of BIW.

B. Contracting Officer’s Decision

On July 20, 1990, the CO issued a final decision denying Biffs claim in its entirety. On the merits, the CO found that BIW had failed to demonstrate that the amounts of the claimed price adjustment arose from ECNs/drawings that extended the scope of work set out in the related ECPs, and that BIW actually incurred those amounts in performing the changes in question. Therefore, the CO concluded that BIW was not entitled to the requested price adjustments.

The CO also found that BIWs claims were time barred under 10 U.S.C. § 2405. Section 2405(a) provides in relevant part:

' The Secretary of a military department may not adjust any price under a shipbuilding contract entered into after December 7, 1983, for an amount set forth in a claim, request for equitable adjustment, or demand for payment under the contract ... arising out of events occurring more than 18 months before the submission of the claim, request, or demand.

Section 2405(b) further provides:

For the purposes of subsection (a), a claim, request, or demand shall be considered to have been submitted only when the contractor has provided the certification required by section 6(c)(1) of the Contract Disputes Act of 1978 (41 U.S.C. 605(c)(1)) and the supporting data for the claim, request, or demand.

10 U.S.C. § 2405. The CO found that BIW did not submit a properly certified claim satisfying the CDA requirements until November 13, 1989. Therefore, the CO determined that price adjustments for events occurring prior to May 14, 1988 were barred under section 2405.

Although “events” is nowhere defined in the statute, the CO determined that in this case “an event” for purposes of calculating the 18-month time limit was the receipt by BIW of the ECNs/drawings in excess of those used to price the corresponding ECP. Because all of the alleged excess ECNs/drawings supposedly responsible for the increased costs were received by BIW prior to May 14, 1988 (the date 18 months prior to BIWs duly submitted claims), the CO concluded that all recovery was barred as outside the statutory time period.

C. Court of Federal Claims Action

On September 7, 1990, BIW brought suit in the CFC, asserting entitlement to the requested price adjustments under the Changes clause of both contracts and under the CDA.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Molina Healthcare of California, Inc. v. United States
133 Fed. Cl. 14 (Federal Claims, 2017)
Moda Health Plan, Inc. v. United States
130 Fed. Cl. 436 (Federal Claims, 2017)
Kellogg Brown & Root Services, Inc.
Armed Services Board of Contract Appeals, 2014
Abbey v. United States
106 Fed. Cl. 254 (Federal Claims, 2012)
Orion Technology, Inc. v. United States
102 Fed. Cl. 218 (Federal Claims, 2011)
Northrop Grumman Computing Systems, Inc. v. United States
101 Fed. Cl. 362 (Federal Claims, 2011)
Lummi Tribe of the Lummi Reservation v. United States
99 Fed. Cl. 584 (Federal Claims, 2011)
L.A. Ruiz Associates, Inc. v. United States
94 Fed. Cl. 768 (Federal Claims, 2010)
Bell BCI Co. v. United States
91 Fed. Cl. 664 (Federal Claims, 2010)
Digital Technologies, Inc. v. United States
89 Fed. Cl. 711 (Federal Claims, 2009)
Laudes Corp. v. United States
86 Fed. Cl. 152 (Federal Claims, 2009)
Lublin Corp. v. United States
84 Fed. Cl. 678 (Federal Claims, 2008)
BLR Group of America, Inc. v. United States
84 Fed. Cl. 634 (Federal Claims, 2008)
Bannum, Inc. v. United States
80 Fed. Cl. 239 (Federal Claims, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
20 F.3d 1567, 1994 WL 73993, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bath-iron-works-corporation-v-united-states-cafc-1994.