Bell BCI Co. v. United States

91 Fed. Cl. 664, 2010 U.S. Claims LEXIS 41, 2010 WL 743888
CourtUnited States Court of Federal Claims
DecidedFebruary 24, 2010
DocketNo. 03-1613C
StatusPublished
Cited by8 cases

This text of 91 Fed. Cl. 664 (Bell BCI Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bell BCI Co. v. United States, 91 Fed. Cl. 664, 2010 U.S. Claims LEXIS 41, 2010 WL 743888 (uscfc 2010).

Opinion

OPINION AND ORDER ON MOTIONS FOR PARTIAL FINAL JUDGMENT

WHEELER, Judge.

This construction case is before the Court on remand from the United States Court of Appeals for the Federal Circuit. See Bell BCI Co. v. United States, 570 F.3d 1337 (Fed.Cir.2009). The Federal Circuit directed this Court to make new determinations regarding three of the six categories of damages presented at trial, but affirmed this Court’s rulings on the remaining three categories. Id. Plaintiff Bell BCI (“Bell”) and its subcontractor, Stromberg Metal Works, Inc. (“Stromberg”), have filed motions for partial final judgment as to claims that the Federal Circuit affirmed. For reasons that are puzzling to the Court, Defendant opposes Bell’s and Stromberg’s motions. It is unknown why Defendant would construct an argument opposing the prompt payment of decided claims under the Contract Disputes Act.

The previous decisions of this Court and the Federal Circuit provide a full explanation of this extensive controversy,1 but a brief [666]*666summary may prove helpful. Following a project fraught with changes and delays, Bell submitted a certified claim to the contracting officer on April 5, 2002 to recover additional costs incurred in the construction of a laboratory building for the National Institutes of Health (“NIH”) in Bethesda, Maryland. The claim included Bell’s additional costs, as well as “pass through claims” to recover the additional costs of Bell’s subcontractors. The contracting officer denied the claim, and Bell filed suit in this Court on June 27, 2003.

At the trial of this matter in October 2007, Bell presented evidence covering six separate categories of damages: (1) $2,058,456 in labor inefficiency costs attributable to the cumulative impact of government-issued changes; (2) $1,602,053 for the delays of remaining on the project after April 30, 2001; (3) $366,051 as a 10 percent profit on the delay and inefficiency costs; (4) $563,125 for the unpaid balance of the contract price; (5) $1,610,987 for unresolved changes not addressed in any contract modification; and (6) pass through claims of $1,690,352 on behalf of five subcontractors. In an April 21, 2008 decision, the Court found in favor of Bell, and awarded damages to Bell totaling $6,200,672, plus interest as allowed under the Contract Disputes Act, 41 U.S.C. § 611 (2006) (“CDA”). Bell BCI Co. v. United, States, 81 Fed.Cl. 617 (2008). The Court also granted Stromberg’s pass through claim for $812,092, plus CDA interest. Id. at 641-42.

The Government appealed the Court’s decision to the Federal Circuit. In a June 25, 2009 decision, the Federal Circuit affirmed in part, vacated in part, and remanded the case to this Court. Bell BCI, 570 F.3d at 1338. With regard to Bell’s six categories of damages, the Federal Circuit affirmed the awards to Bell of $563,125 for the unpaid balance of the contract price, and of $1,610,987 for unresolved changes not addressed in any contract modification, and to Stromberg for the $812,092 pass through claim. Id. at 1342-43. The Federal Circuit vacated the awards of $2,058,456 for labor inefficiency costs, and $1,602,053 for government-caused delays, and remanded to this Court to determine the damages for these items. Id. at 1342. Implicitly, the Federal Circuit also reopened Bell’s claim for profit on the remanded damages items. As to the three categories that the Federal Circuit affirmed, Defendant has not paid Bell for any of these damages.

After receipt of the Federal Circuit’s mandate in this Court on October 21, 2009, both Bell and Stromberg filed motions for entry of partial final judgment as to the damages items that the Federal Circuit affirmed.2 Stromberg filed its motion on December 23, 2009, and Bell filed a similar motion on January 11, 2010. Bell and Stromberg assert that the affirmed damages items will not be the subject of any remand proceedings, and should be considered final. Bell, however, argues that Stromberg’s motion should be denied as moot because Stromberg is not a party to this action, and in any event, Bell has included the amount for Stromberg in its own motion for entry of partial judgment. Defendant filed an opposition brief to Bell’s and Stromberg’s motions on February 2, 2010, and both Bell and Stromberg have filed reply briefs.

Discussion

A. Bell’s Motion for Partial Final Judgment

Pursuant to RCFC 54(b), this Court is authorized to “direct entry of final judgment as to one or more, but fewer than all, claims” upon an express finding that “there is no just reason for delay.” The full text of this rule reads as follows:

(b) Judgment on Multiple Claims or Involving Multiple Parties.
When an action presents more than one claim for relief — whether as a claim, counterclaim, or third-party claim — or when multiple parties are involved, the court may direct entry of a final judgment as to one or more, but fewer than all, claims or [667]*667parties only if the court expressly determines that there is no just reason for delay. Otherwise, any order or other decision, however designated, that adjudicates fewer than all the claims or the rights and liabilities of fewer than all of the parties does not end the action as to any of the claims or parties and may be revised at any time before the entry of a judgment adjudicating all the claims and all the parties’ rights and liabilities.

RCFC 54(b). This rule applies to all categories of cases that come before the Court, without restriction. In the current posture of the ease, this Court would need to issue a partial final judgment under RCFC 54(b) to grant relief to Bell on its motion. This is so because the Federal Circuit remanded the entire case to this Court without issuing any partial judgment in Bell’s favor.

The CDA also contains a provision at 41 U.S.C. § 609(e) providing for the entry of partial final judgments in cases involving multiple claims or multiple parties. This provision states as follows:

(e) Judgments as to fewer than all claims
In any suit filed pursuant to this chapter involving two or more claims, counterclaims, cross-claims, or third-party claims, and where a portion of one such claim can be divided for purposes of decision or judgment, and in any civil suit where multiple parties are involved, the court, whenever such action is appropriate, may enter a judgment as to one or more but fewer than all of the claims, portions thereof, or parties.

41 U.S.C. § 609(e). Defendant attempts to give this provision a very narrow reading by relying upon the title of § 609, “Judicial review of board decisions.” Based upon this title, Defendant suggests that § 609(e) applies only to appeals from board of contract appeals’ decisions, and thus would apply only when the Federal Circuit is reviewing a board decision. (Def. Opp. 6.) However, the Court does not read this provision so narrowly.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Entergy Nuclear Palisades, LLC v. United States
122 Fed. Cl. 225 (Federal Claims, 2015)
Stockton East Water District v. United States
120 Fed. Cl. 80 (Federal Claims, 2015)
Aeroplate Corp. v. United States
112 Fed. Cl. 88 (Federal Claims, 2013)
Rosa D. Bonewell v. United States
111 Fed. Cl. 129 (Federal Claims, 2013)
Wolfchild v. United States
73 A.L.R. Fed. 2d 569 (Federal Claims, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
91 Fed. Cl. 664, 2010 U.S. Claims LEXIS 41, 2010 WL 743888, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bell-bci-co-v-united-states-uscfc-2010.