Bell BCI Co. v. United States

72 Fed. Cl. 164, 2006 U.S. Claims LEXIS 199, 2006 WL 1994581
CourtUnited States Court of Federal Claims
DecidedJuly 14, 2006
DocketNo. 03-1613C
StatusPublished
Cited by10 cases

This text of 72 Fed. Cl. 164 (Bell BCI Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bell BCI Co. v. United States, 72 Fed. Cl. 164, 2006 U.S. Claims LEXIS 199, 2006 WL 1994581 (uscfc 2006).

Opinion

OPINION AND ORDER

WHEELER, Judge.1

This case is before the Court on Defendant’s motion to dismiss a promissory estoppel count of Plaintiffs Complaint for lack of subject matter jurisdiction, and on the parties’ cross-motions for partial summary judgment regarding accord and satisfaction issues. The parties’ dispute arises from a building construction project for the National [166]*166Institutes of Health (“NIH”) in Bethesda, Maryland. Among a host of changes on the project, the Government added a new floor to the building design after construction had commenced. Plaintiff Bell BCI Company (“Bell”) alleges a “cumulative impact” claim against the Government for the disruptive effect of the many modifications issued during the course of the project. In defense, the Government asserts that Bell agreed to the allowance of additional time and compensation in 44 individual modifications, reserved no rights to further relief, and released the Government from any further equitable adjustment attributable to each modification. Bell also moves for partial summary judgment on the ground that the Government improperly assessed liquidated damages.

Without objection from Bell, the Court grants Defendant’s motion to dismiss Count VI of the Complaint, relating to Bell’s allegations of promissory estoppel. In all other respects, the Court denies the parties’ cross-motions for partial summary judgment. While it may be that Defendant ultimately can show a valid accord and satisfaction defense, or that Bell can show an improper assessment of liquidated damages, the outcome of those issues is heavily fact dependent. The briefing on the pending motions has demonstrated that the parties disagree on many of the relevant facts of the ease. A trial will be necessary to address and resolve the material fact issues.

Factual Background2

On March 26,1998, NIH awarded Contract No. 263-98-C-0102 to Bell for the fixed price of $63,663,745 to construct a new laboratory research building at NIH’s Bethesda, Maryland campus. The new building, known as NIH Building 50, originally was designed to have five above-ground stories and a functional basement. The Contract called for Bell to complete the project within 821 calendar days after NIH issued the notice to proceed. NIH issued this notice on April 1, 1998, making the completion date June 29, 2000. If Bell did not complete the work within the agreed time, NIH could assess liquidated damages against Bell of $3,721 for each day of contractor delay.

In December 1998, with construction well underway, NIH notified Bell that it wanted to add a new fourth floor to the building, changing the design from a five-story to a six-story structure. NIH requested Bell to prepare a proposal for the fourth floor addition. The fourth floor negotiations between NIH and Bell proceeded in three phases: (1) structural steel and concrete work; (2) core and shell work; and (3) fit out work. In early 1999, NIH agreed to Bell’s proposal for the fourth floor structural steel and concrete work, adding $1,579,127 to the contract price, and extending the completion date by 30 days to July 29, 2000. On June 23, 1999, NIH and Bell agreed to a modification for the fourth floor core and shell work, adding $6,891,118 to the contract price, and extending the completion date by another 30 days.

The resolution of phase three for the fourth floor fit-out work did not proceed as smoothly. On October 2, 2000, after extensive negotiations, NIH and Bell entered into bilateral contract Modification No. 093, increasing the contract price by $2,296,963 and establishing a new completion date of April 30, 2001. In this modification, the parties also set 14 substantial completion milestone dates between October 1, 2000 and April 30, 2001, and changed the liquidated damages amount to $266 per calendar day for contractor delays in meeting any of the 14 milestone dates.3 This modification expressly resolved all time impact and delay issues relating to changes issued on or before August 31, 2000. The modification contained the following release language:

8. The modification agreed to herein is a fair and equitable adjustment for the Contractor’s direct and indirect costs. This [167]*167modification provides full compensation for the changed work, including both Contract cost and Contract time. The Contractor hereby releases the Government from any and all liability under this Contract for further equitable adjustment attributable to the Modification.

(Pl.App. at 64; Deft.App. at 28). Between October 2, 2000 and April 5, 2001, NIH and Bell entered into 43 other bilateral contract modifications, designated as Modification No. 094 through Modification No. 140, all of which contained the same release language as above.

None of these 44 bilateral modifications contains a reservation of rights by Bell to assert a later claim for cumulative impact, disruption, or labor inefficiency. However, the modifications do not contain any explicit release of such claims either. The specific facts underlying Plaintiffs claim are not yet in evidence, and the Court cannot determine whether Plaintiffs claim is “attributable to the Modification,” or is an “indirect cost” covered by the release language above. Id. Similarly, the Court cannot yet discern when Plaintiffs claim matured to the point that Plaintiff knew or should have known that it was experiencing cumulative impact, disruption, or labor inefficiency. It does not appear that any of these 44 bilateral modifications included a payment to Bell that might be regarded as legal consideration for the costs of cumulative impact, disruption, or labor inefficiency.

After April 5, 2001, the parties executed other modifications beginning with Modification No. 142, dated September 10, 2001, through Modification No. 205, dated September 22, 2003. These later modifications contain a contractor reservation of rights stating “[tjhis agreement does not affect the contractor’s rights for damages due to any delays or disruptions that may have occurred as a result of this work.” See, e.g., Pl.App. at 95. The Contracting Officer typically inserted a handwritten notation on the modification stating “[tjhis modification and the language reserving to the contractor certain rights does not constitute an admission by the Government that the contractor is entitled to an equitable adjustment.” Id.

On July 31, 2001, Bell submitted a letter to NIH seeking to reserve its rights retroactively for “additional compensation for delays, disruptions and/or damages resulting from the changes” since September 1, 2000. (Deft.App. at 169).

The parties disagree on the date of project completion. Bell asserts in its Complaint that NIH took beneficial occupancy of the project as early as March 26, 2001 when it began to use and occupy the second floor (Complaint at ¶ 64), that Bell substantially completed the base contract work on December 31, 2001, id. at ¶ 65, and that Bell substantially completed the NIH changed work by February 5,2002. Id. at ¶ 66. Defendant denies all of these allegations, but does not state when it believes Bell completed the project. (Answer at ¶¶ 64, 65, 66).

On April 5, 2002, Bell submitted a request for equitable adjustment to the Contracting Officer, which included Bell's own increased costs and the “pass through” requests of five subcontractors on the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shell Oil Company v. United States
130 Fed. Cl. 8 (Federal Claims, 2017)
East Coast Repair & Fabrication, LLC v. United States
199 F. Supp. 3d 1006 (E.D. Virginia, 2016)
County of Galveston v. Triple B Services, LLP
498 S.W.3d 176 (Court of Appeals of Texas, 2016)
Structural Concepts, Inc. v. United States
103 Fed. Cl. 84 (Federal Claims, 2012)
Bell Bci Co. v. United States
570 F.3d 1337 (Federal Circuit, 2009)
Bell BCI Co. v. United States
81 Fed. Cl. 617 (Federal Claims, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
72 Fed. Cl. 164, 2006 U.S. Claims LEXIS 199, 2006 WL 1994581, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bell-bci-co-v-united-states-uscfc-2006.