Brock & Blevins Co. v. United States

170 Ct. Cl. 52
CourtUnited States Court of Claims
DecidedApril 16, 1965
DocketNo. 292-59
StatusPublished
Cited by57 cases

This text of 170 Ct. Cl. 52 (Brock & Blevins Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brock & Blevins Co. v. United States, 170 Ct. Cl. 52 (cc 1965).

Opinion

Durfee, Judge,

delivered the opinion of the court:

This is a suit to recover damages for delays due to the fault of the Government arising out of a subcontract (later [54]*54assigned to the Department of tbe Army), entered into by plaintiff with the prime contractor, Hiwassee Constructors on October 27, 1952. The subcontract covered rehabilitation of piping, mechanical and electrical equipment of the North Acid area of the Volunteer Ordnance Works at Chattanooga, Tennessee.

Plaintiff claims damages for breach of the subcontract through unreasonable delays caused by defendant which increased its cost for equipment, overtime and overhead. More specifically, plaintiff claims that defendant’s refusal to grant time extensions until after the expiration of the original contract performance period, coupled with defendant’s demands throughout the original performance period that plaintiff complete its subcontract on time despite delays caused by defendant, caused great overtime expense, thereby increasing the cost of performing the contract.

Defendant, besides denying that it caused any delay to plaintiff, has raised several defenses including lack of privity between plaintiff and defendant, accord and satisfaction, and plaintiff’s failure to exhaust its administrative remedy. We believe that plaintiff’s claim may be disposed of on the ground that an accord and satisfaction was agreed upon by the parties, and therefore will limit ourselves to that aspect of the case.1

At the outset, let us make clear our belief that there is no doubt that plaintiff suffered considerable expenses as the result of Government occasioned delays. Our findings of fact establish that plaintiff was delayed a total of 60 days in the completion of the work. It would be far too cumbersome to examine the specifics of each delay claim in the body of this opinion, so for the sake of brevity, they will not be delved into further.

The contract in issue contained no specific provision authorizing payment for delays, such as a “suspension of work” clause which is sometimes so treated. It did contain ia [55]*55“changes” clause which provided for an equitable adjustment for the reasonable cost of performing extra work. Due to hastily drafted and incomplete specifications, plaintiff was compelled to perform a great amount of extra work, work not included in the original contract specifications. At various times during the performance of the contract, plaintiff was given equitable adjustments in the form of additional compensation for the performance of extra work. Also, at various times during performance, plaintiff requested extensions of time due to the quantity of extra work ordered outside the original contract. These requests were rejected however, and plaintiff had to use extra help and pay overtime wages in an attempt to complete the contract on time. Finally, eight days after the scheduled completion date of the contract, plaintiff was allowed an extension of time. Subsequent extensions of time were thereafter given; however, they came too late to benefit plaintiff. The rejections of plaintiff’s requests for time extensions caused plaintiff to make unnecessary expenditures in overtime in order to meet a completion date which intervening circumstances (Government caused delays) had made unrealistic. The subsequent time extensions which were granted could in no Avay have helped plaintiff avoid the previous investments in overtime. Had plaintiff been able to anticipate the time extensions which were eventually granted, the overtime and extra forces which it employed to accelerate completion of the original subcontract work would have been sharply reduced, if not eliminated.

After completion of the contract, plaintiff was not satisfied with two contract modifications which had been proposed as payment for some of the aforementioned extra work. Plaintiff accepted the sums offered, hut not unqualifiedly, as it reserved its rights in this matter and specifically stated in written form that it was appealing to the Chief Engineer, Washington, D.C. for the additional sums to which plaintiff believed it was entitled.

After a duly filed notice of appeal, plaintiff filed its appeal with the Engineers Claims and Appeals Board, seeking payment of $265,688.03 as additional equitable adjustment under [56]*56the contract. Representatives of plaintiff then agreed to meet with the Division Engineer, South Atlantic Division, Corps of Engineers, in an attempt to work out a fair price for the performance of the work in issue.2 The parties met for a 30-day period, and considered in great detail the aspects of plaintiff’s claim. Thereafter, the Division Engineer put out a detailed Conferees Report on Review of Claim which concluded that plaintiff was entitled to be paid $114,673.28 more than it had been paid in the two aforementioned contract modifications. The following conclusions were among those agreed to by the conferees:

(1) A forty-hour work week was used from the start of construction through January 1953.
(2) A forty-eight hour work week or more was used from February 1953 through to completion.
(3) There was approximately a 300 percent turnover in labor.
(4) There was no delay in construction due to late delivery of materials or equipment.
(5) The agreement on the amount of direct labor involved in the disputed items was increased by one-third to provide for lost time, on the basis of two hours lost time for each 8 hour work day.
(6) An amount of 16% percent was included in the estimates for overtime premium payment, based on an average week of 48 hours with premium payment for 8 hours.
(7) Allowances for overhead included, among other matters, costs of supervision, tools, equipment and supplies, and equipment operators.

The Conferees Report was sent to the contracting officer who would not accept it. However, plaintiff then submitted the dispute to the Engineers Claims and Appeals Board on the record, including the Conferees Report. The Board found plaintiff due the sum of $116,057.28. The Chief of Engineers approved the decision. Modification No. 14 to the contract was issued, authorizing payment of this sum to plaintiff. Plaintiff signed its acceptance and made no [57]*57reservations, exceptions, or other claims at that time.3 Plaintiff executed a final payment estimate in the amount of $116,057.28 under the certification that “The above bill is correct and just * *

From the above resume of the pertinent facts in this case, we conclude that an accord and satisfaction exists, which precludes plaintiff from any further recovery. There are certain elements of the equitable adjustment here that are virtually interchangeable with delay-damage ingredients. In fact, it is evident that much of the extra work came about as a result of the delay. Plaintiff maintains, and we agree, that had a time extension been given in order to rectify the hold up in performance of the contract, plaintiff would not have had to hire extra labor and pay overtime wages. Deciding when delay damages begin and equitable adjustment for extra work ends is not an easy task in this case. One is dependent upon or related to the other. Plaintiff fully realized this fact when it made its claim for equitable-adjustment for extra work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lankster v. United States
87 Fed. Cl. 747 (Federal Claims, 2009)
Holland v. United States
86 Fed. Cl. 681 (Federal Claims, 2009)
Bell BCI Co. v. United States
72 Fed. Cl. 164 (Federal Claims, 2006)
Axion Corp. v. United States
68 Fed. Cl. 468 (Federal Claims, 2005)
District of Columbia v. United States
67 Fed. Cl. 292 (Federal Claims, 2005)
Addison-Taylor v. United States
63 Fed. Cl. 345 (Federal Claims, 2004)
Jackson Construction Co. v. United States
62 Fed. Cl. 84 (Federal Claims, 2004)
Abatement Contracting Corp. v. United States
58 Fed. Cl. 594 (Federal Claims, 2003)
W & F Building Maintenance Co. v. United States
56 Fed. Cl. 62 (Federal Claims, 2003)
Ryco Construction, Inc. v. United States
55 Fed. Cl. 184 (Federal Claims, 2002)
Donald O'connor, and Benjamin M. Aban, Donald N. Adaniya, Rolando R. Alvarado, Joseph A. Alvitre, Larry Andrews, Jeannett Armstrong, Robert G. Ashmore, Lee E. Austin, David K. Bahl, Lawrence R. Barron, Kenneth R. Battle, Jeanette Binion, Royce Binion, Eleanor M. Bishop, Gaetane M. Boutin, Thomas R. Boyden, Deena J. Bradshaw, Shadrach Breaux, Stephen G. Broich, Michael C. Brown, Yulanda S. Brown, David S. Buchanan, Maria L. Buenrostro, Gail Burnett, William D. Byrd, Richard F. Camacho, Elaine L. Carr, Larry Carr, Ruby L. Carter, Daniel Castellano, Raymond Cervantes, Alyce Chacon, Joyce M. Chalenor, William Q. Chavira, Mary R. Clarett, Jacqueline v. Clayter, Janice L. Cobb, Paula Sue Conklin, Sandra G. Contreras, Lori A. Cook, Patricia A. Cormier, Osvaldo R. Cosme, John D. Cota, Jr., Scott A. Craddolph, Ronnie F. Crews, Joselito S. Cristobal, Sherron S. Cryer, Marjorie E. Cunningham, Elmito A. Danggoec, Gibson Nancy Darley, Valynda D. Davis, Claudia L. Dawkins, Mark W. Day, David Martin De Losreyes, Firmo C. De Mesa, Carolyn De Ruso, Mary E. Dean, Daniel J. Devoy, Rita P. Dietrich, John A. Dimercurio, Marianito G. Domingo, Viola E. Eaton, John T. Elliott, June E. Erwin, Sharon Espinoza, Joan E. Farber, Richard G. Ferguson, Craig E. Finch, Olivia Flores, Anna J. Fontana, Carl R. Fontana, David Russell Ford, Kevin Foreman, Salvador Franco, Donald R. Freeman, Richard C. Fromm, Charles E. Fuller, Donato F. Garcia, Lydia Garcia-Espinoza, Jerry A. Gasbarra, Andrea S. Gilbert, Frank C. Giovenco, Gabriel Giraco, Carmen Y. Glass Lang, Alan J. Glassman, Ralph J. Gomez, Gay Gorski, Russell L. Gosselin, Leland A. Gotwals, Regina Goudeau, Timothy N. Graham, Melody A. Grant, Kathryn I. Gregor, Gordon C. Gregory, Victor A. Guerra, Eduardo Guirado, Mary L. Gunn, Victor Guzman, Douglas A. Hackett, Clara N. Hansen, Joan C. Harkins, Sharon Chaney Harris, Ingrid A. Harrison Meyerhofer, Luella L. Hartman, Edmore Hatcher, Dennis W. Hattan, Clifford L. Hawk, Barbara A. Hayes, Alice L. Heftye, Robert L. Henson, Sr., George Hernandez, Eric D. Hibbler, Talbert L. Hignight, Dwight E. Hill, Vivian Hill, Karen L. Hillblom, Ernest L. Hines, Barbara A. Holland, Antonius A. Holst, Mark J. Hopkins, Richard J. Huerta, Edward E. Huizar, Michael F. Humphrey, Eileen Hutchings, Pamela M. Iseri, Carole A. Jackson, Pamela A. Jarrett, Ronald D. Jensen, Odalie K. Johannessen, Judith A. John, Fred C. Johnson, David L. Johnson, Brian L. Jones, Altheria v. Jones, Ethelyn J. Jones, Charles L. King, John L. King, Edward S. Kirol, Stacey A. Koide, Jean K. Konnoff, Geza C. Koszty, Michael J. Kunza, Kenneth R. Kyle, Philip L. Lamontagne, Timothy D. Lane, Larry A. Latine, Phillip E. Lawson, Deirdre Anne Leary, James F. Lindekugel, Nelson Lugo, Teofilo M. Lugo, Laisene Malauulu, Gregory D. Marinas, Patrice A. Markham, Val S. Marquez, Richard D. McCaffery Lance E. McNeil Johnny McQueen Jr., Anthony C. Metoyer, Jr., Troy J. Montgomery, Jong-Boon Moon, Don A. Morales, Donald F. Morgan, Barbara R. Murtagh, Albert W. Myers, Joyce C. Naeyaert, Mark D. Neumeister, Robert D. Nickens, Roque Nieto, Michael C. Nimtz, Sandra Lee Nunally, Yolanda Ontiveros-Duncan, Ronald L. Orr, Michael A. Paez, Kenneth F. Paffrath, Evelyn P. Palencia, Hugo A. Palomo, Roy H. Parker, Iii, Gary A. Patterson, Henry P. Perez, Robert A. Perez, Arthur R. Pimentel, Stanley H. Polinsky, Thomas H. Potter, Valerie B. Prather, John L. Quaderer, Lance D. Queen, Sandra A. Quintard, Timothy John Ramirez, Veda R. Ramsey, Linda Rau, Natividad Reyes, Jr., Frances A. Riedel, Edgar B. Roa, Angela K. Robbins, Roxie A. Roddy, Sharon L. Rodriguez, Joseph v. Rodriguez, Robert G. Rollings, Frank Romero, Richard M. Rosenthal, John G. Rossi, Ann Rubin, Vito Ruggiero, Ronald S. Sadora, Carlos E. Salazar, Priscilla B. Samson, Debra D. Sanchez, Robert Sanchez, Mark A. Sands, Jessie G. Santos, Ymelda Sasseen, William P. Shea, James E. Sheldon, Raymond J. Shipley, James N. Shows, Frank R. Silkwood, Deborah L. Sitlington, William H. Slaton, Charlotte C. Sluder, Gladys L. Snowden, Thomas I. Sorrels, Dennis E. Spain, Vivienne Steele, William H. Stephens, John W. Strandberg, Barry R. Stratton, Cathy D. Stratton, Belinda A. Sturz, Mick Suarez, Cindy J. Sulistio, Arturo L. Tabios, Jaime E. Tagle, George v. Taylor, John S. Telles, Dominic A. Thomas, Mia P. Thompson, Betty A. Todd, Rebecca M. Upton, Maria Suzette Vaccaro, James T. Vanhorn, Dana P. Vanorman, Joan C. Vincent, Warren E. Voss, Lula M. Wall, Vincent K. Warren, Bobby Lee Washington, Stephanie Renee Washington, James A. Wathen, Ii, Irma Weaver, Francis E. Whalen, Jr., Elvira A. White, Mary A. Wicker, Walter Gene Wilkerson, Merle A. Wilkison, Brenda G. Williams, Ervin Williams, Jr., Greg F. Wolfslau, Robert C. Woolfork, Rodney A. Wright, and Stanley E. Zubas v. United States
308 F.3d 1233 (Federal Circuit, 2002)
O'Connor v. United States
308 F.3d 1233 (Federal Circuit, 2002)
Kanag'Iq Construction Co. v. United States
51 Fed. Cl. 38 (Federal Claims, 2001)
O'Connor v. United States
50 Fed. Cl. 285 (Federal Claims, 2001)
National Steel & Shipbuilding Co. v. United States
49 Fed. Cl. 579 (Federal Claims, 2001)
Starflight Boats v. United States
48 Fed. Cl. 592 (Federal Claims, 2001)
Centex Corp. v. United States
48 Fed. Cl. 625 (Federal Claims, 2001)
First Nationwide Bank v. United States
48 Fed. Cl. 248 (Federal Claims, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
170 Ct. Cl. 52, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brock-blevins-co-v-united-states-cc-1965.