Ryco Construction, Inc. v. United States

55 Fed. Cl. 184, 2002 U.S. Claims LEXIS 368, 2002 WL 31958792
CourtUnited States Court of Federal Claims
DecidedDecember 23, 2002
DocketNo. 01-151 C
StatusPublished
Cited by11 cases

This text of 55 Fed. Cl. 184 (Ryco Construction, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ryco Construction, Inc. v. United States, 55 Fed. Cl. 184, 2002 U.S. Claims LEXIS 368, 2002 WL 31958792 (uscfc 2002).

Opinion

OPINION

HEWITT, Judge.

This matter comes before the court on Defendant’s Motion for Summary Judgment (Def.’s Mot.). Plaintiff, Ryco Construction, Inc. (Ryco), is an engineering and construction company based in Gardena, California. Complaint (Compl.) at ¶ 5. In its complaint, plaintiff asserts a right to compensation for road repair work done in Los Padres National Forest, California under a contract with the United States Forest Service. Id. at ¶¶ 3-4. Plaintiff alleges that because of a delay caused by the government it incurred additional costs at Big Caliente, one of the twenty project sites covered by the contract. Plaintiffs Opposition to Motion for Summary Judgment (Pl.’s Opp.) at 3-6.

Defendant argues that it is entitled to summary judgment on many grounds. Defendant notes that plaintiffs argument is premised on having unrestricted access to the Big Caliente site. Defendant argues that the contract did not guarantee plaintiff unrestricted access to all the project sites and, for that reason, this case should be resolved in defendant’s favor. Defendant’s Motion for Summary Judgment (Def.’s Mot.) at 5. Defendant argues that bilateral contract modification number 3 was an accord and satisfaction, which precludes plaintiff from seeking further damages. Id. at 8-13. Defendant argues that plaintiff did not give the government adequate notice of its increased costs, and therefore is precluded from bringing suit now. Id. at 13-15. Because the delay resulted from the discovery of an endangered species at Big Caliente, defendant argues [188]*188that the cause of the delay was an act of government, and that plaintiffs contract does not entitle plaintiff to compensation for additional work performed as a result of acts of government. Id. at 16-17. Defendant argues that the terms of plaintiffs contract do 'not entitle plaintiff to compensation for the period during which the contract was suspended due to winter shutdowns. Id. at 17-19. With regard to damages, defendant argues that plaintiff is precluded from recovery because it failed to support its claim with actual cost data, id. at 19-25, and that, even if the delay was caused solely by the government, plaintiff is not entitled to payment of extended home office overhead. Id. at 25-28.

Plaintiff argues against the legal merits of defendant’s arguments, and asserts that there are genuine issues of material fact that must be resolved at trial. PL’s Opp. passim. Plaintiff argues that the contract by its express language gave it unrestricted access to all project sites. Id. at 9-13. Plaintiff argues that contract modification number 3 was not an accord and satisfaction because there was no meeting of the minds regarding the claims plaintiff was settling. Id. at 14. Plaintiff argues that it gave the government adequate notice of its increased costs and, even if it did not, there is no showing of prejudice to defendant. Id. at 21-26. Plaintiff further argues that it is entitled to compensation for both the winter shutdowns and the delay caused by the act of government. Id. at 27-30. As to damages, plaintiff contends that it has supported its claims with actual cost data, and that it is entitled to extended home office overhead. Id. at 30-38.

For the following reasons, defendant’s motion for summary judgment is GRANTED in part and DENIED in part.

I. Background

On August 26, 1996, Ryco Construction Co. was awarded a contract with the Forest Service to perform storm damage repairs at 20 different sites on and adjacent to roads located in the Los Padres National Forest (National Forest). Defendant’s Proposed Findings of Uncontroverted Facts (DPFUF) ¶ 1.1 Many of the project sites were in remote areas of the National Forest, scattered over a total area of several hundred square miles. Id. ¶ 4. The scope involved “the repair of storm damaged roads, which consist of earthwork, construction staking, sampling & testing, reinforced concrete crib walls, galvanized berm drains, corrugated metal pipe, rolling drainage dips, reinforced concrete low water crossings, riprap bank armoring, and grout riprap spillways.” Id. ¶ 7. After modifications, the total contract price was $629,532.32. Id. ¶ 6.

Big Caliente was one of the riparian project sites to which a project season limitation applied, and is at the center of this dispute. DPFUF ¶ 17. The contract drawings for this site included the statement that the construction season was limited to “when stream is dry to winter rains or as approved by COR [Contracting Officer’s Representative].” Id.; Joint Appendix of Supplemental Documents (J.A.) at 229. Generally, the construction season occurred when streams were dry: in the summer, fall, and early winter. See J.A. Exhibit (Exh.) 6. In its bid, Ryco anticipated subcontracting most of the work at Big Caliente; of the $108,970 bid for the work, Ryco’s portion of the work was $40,370. DPFUF 1127.

Problems began at Big Caliente when endangered frogs were found at the job site. J.A. at 269. On August 26, 1997, the government issued work order no. 4, which ordered plaintiff not to begin construction at the site during the then current construction season. Id.; DPFUF ¶ 37. The purpose of work order no. 4 was to allow the Forest Service to consult with the Fish and Wildlife Service and obtain a biological report concerning the endangered species at the site. DPFUF ¶ 37. That report was issued on September 15, 1998. J.A. at 302; DPFUF ¶ 38. On October 7, 1998, the Forest Service issued a notice to resume work at the site. Plaintiffs Proposed Findings of Undisputed Fact (PPFUF) ¶ 29. One day later, plaintiff began to remobilize to complete work at Big Caliente. Id. ¶ 31.

[189]*189During the course of performance, the parties entered into four bilateral modifications. DPFUF ¶ 5. Of greatest importance to the facts of this case is modification 3, which increased the contract performance period by ten days and the contract price by $25,003.38. Id. Modification 3 did not contain a contract release or other similar language. J.A. Exh. 4. The stated justifications for modification 3 were that:

1. Contractor was prevented from beginning work on Big Caliente due to shutdown by FS [Forest Service] as the result of discovering endangered species on site requiring consultation with U.S. F & WS [U.S. Fish & Wildlife Service] which took approximately] Pk years.
2. Demolition of old crossing was erroneously left out of contract.
3. A design change was required to shift low spot of crossing over to center of channel, which required modifying spillway into a cutoff wall.
4. The increase in square footage of crib-wall was required to meet grade.

Id. at 210.

Modification 3 was issued in response to a letter sent by plaintiff on October 12, 1998, advising the Forest Service that it had been delayed from performing contract work at Big Caliente due to the discovery of endangered species. PPFUF ¶ 32; Defendant’s Response to Plaintiffs Proposed Findings of Uncontroverted Fact ¶ 32. Plaintiff has conceded that the date of its notice forecloses recovery for any costs of the work relating to the period prior to October 12, 1998, but leaves open its effect on other damages. Pl.’s Opp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pew Forest Products v. United States
105 Fed. Cl. 59 (Federal Claims, 2012)
Datamill, Inc. v. United States
91 Fed. Cl. 722 (Federal Claims, 2010)
Oak Environmental Consultants, Inc. v. United States
77 Fed. Cl. 688 (Federal Claims, 2007)
Renda Marine, Inc. v. United States
71 Fed. Cl. 378 (Federal Claims, 2006)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
W & F Building Maintenance Co. v. United States
56 Fed. Cl. 62 (Federal Claims, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
55 Fed. Cl. 184, 2002 U.S. Claims LEXIS 368, 2002 WL 31958792, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ryco-construction-inc-v-united-states-uscfc-2002.