Pew Forest Products v. United States

105 Fed. Cl. 59, 2012 U.S. Claims LEXIS 464, 2012 WL 1574109
CourtUnited States Court of Federal Claims
DecidedMay 7, 2012
DocketNo. 09-814C
StatusPublished
Cited by7 cases

This text of 105 Fed. Cl. 59 (Pew Forest Products v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pew Forest Products v. United States, 105 Fed. Cl. 59, 2012 U.S. Claims LEXIS 464, 2012 WL 1574109 (uscfc 2012).

Opinion

OPINION

ALLEGRA, Judge:

In this government contract ease, Pew Forest Products (Pew) alleges that the United States Forest Service (the Forest Service) breached its timber sale contracts by delaying logging operations, and by failing to provide plaintiff with the contractual remedies for that delay to which it was entitled. The parties have filed cross-motions for summary judgment. Following oral argument, and after further review of the briefs and accompanying appendices, the court GRANTS defendant’s motion for summary judgment and DENIES plaintiff’s cross-motion for partial summary judgment.

I. BACKGROUND

A brief recitation of the underlying facts sets the context for this decision.

Pew is a family-owned logging company based in Crescent Mills, California. Pew has been involved in the purchase and harvest of timber from the Forest Service for the past thirty-five years.

In September 2006, the Forest Service approved the Freeman Project, a forest management plan that included the sale and harvest of certain timber located in the Plumas National Forest in California (Plumas).1 On May 21, 2007, the Forest Service sent Pew and other logging companies prospectuses for two timber sales: the Jenkins Multi-Product Thin (Jenkins) and the Summit Bear Multi-Product Thin (Summit Bear). Both sales involved timber located on the Beckw-ourth Ranger District in Plumas. The letter accompanying these prospectuses indicated that bids for these projects would be opened on June 26, 2007. Both the letter and the prospectuses, however, warned potential bidders that a pike eradication project, planned by the California Department of Fish and Game for “areas immediately adjacent to Lake Davis and perennial stream courses flowing into Lake Davis” could disrupt access to the timber sale area for up to one month between July and October of 2007. These same documents warned that ongoing environmental litigation regarding the Freeman Project could lead to the suspension, modification or termination of any contract, adding that the contracts would provide “for limited remedies” in the case of such litigation-generated action.2

[62]*62On May 22, 2007, as part of ongoing litigation involving timber sales, environmental groups filed a motion for a preliminary injunction to prevent the Forest Service from “awarding logging contracts or otherwise carrying out the Freeman Project.” The United States District Court for the Eastern District of California denied the environmentalists’ motion on June 8, 2007. On June 26, 2007, Pew submitted bid forms for both timber sales. These bids were submitted on preprinted forms supplied by the Forest Service. These forms contained language that provided — “[sjigning this bid form binds the Bidder to accept award under the terms of the sample contract and this bid form if its bid is accepted within 90 days after bid opening.” They also stated that “[t]he Bidder whose bid is accepted will, within 30 days of the award letter’s date, or any written extension thereof by the Forest Service, execute a timber sale contract which shall be provided by the Forest Service and be based on the sample contract referenced in the prospectus.” On June 26, 2007, Joseph Franco, the Forest Service contracting officer (CO) for the Jenkins and Summit Bear contracts, determined that the Freeman Project could proceed and opened the bids. As plaintiff was the only bidder for these contracts, it was declared the high bidder.

The Forest Service’s regional office instructed the CO to delay awarding the contracts while negotiations with the environmental groups progressed. The CO passed this information along to Randy Pew, Pew’s owner, and asked him to attend a meeting with representatives from the Forest Service and the environmental groups. Mr. Pew complied with this request. At that meeting, the environmental groups explained their concerns with the Jenkins and Summit Bear timber sales, but agreed to drop their opposition to those sales as long as the logging operations did not begin until after September 15, 2007.

On August 31, 2007, the Forest Service sent Pew a letter for each of the Jenkins and Summit Bear timber sales indicating that “[yjour bid has been accepted and you are hereby awarded the timber sale contract.” Enclosed with each letter was a contract for the respective timber sale. That same day, the CO and Mr. Pew signed an agreement that delayed operations on the Jenkins and Summit Bear sales until after September 15, 2007. Shortly before the award of these contracts, the CO and Mr. Pew also signed a “Pre-Award Waiver, Release and Limitation of Liability Agreement” for each sales contract. These waivers both stated, in pertinent part, that plaintiff “desires the Forest Service to proceed with the award of the contract, despite the possibility that the Forest Service might delay or suspend operations, and/or modify or terminate the contract.” Mr. Pew, who signed the waiver agreements on behalf of Pew, did not inform anyone at the Forest Service that he was unwilling to accept this limitation. He alleges that he felt that if he did not sign the waivers, Pew would be viewed by the Forest Service as having repudiated the contracts.

Plaintiff moved its logging equipment to the Jenkins timber sale area on September 17, 2007. The parties dispute when plaintiff actually commenced logging. Plaintiff suffered further delays when access to the logging site was disrupted by a pike eradication project run by the California Department of Fish and Game. That project was completed on October 1, 2007. On October 2, 2007, plaintiff removed the first load of timber from the Jenkins site.

On January 4, 2008, Pew requested a rate redetermination pursuant to paragraph B3.33 of its contracts to compensate it for what it claimed was a drop in the value of the contract. That paragraph provided that—

In the event of delay or interruption, exceeding 90 days, under B8.33, Contracting Officer shall make an appraisal to determine for each species the difference between the appraised unit value of Included Timber immediately prior to the delay or interruption and the appraised unit value of Included Timber immediately after the delay or interruption.

[63]*63The CO granted the request and the rate determination was performed. However, the Forest Service found that the value of the contract had increased and, therefore, denied plaintiff the adjustment it sought. Pew completed logging operations on the Jenkins sale on January 8, 2008. It never began logging operations on the Summit Bear sale because a decline in timber prices led it to believe that the area could no longer be logged profitably under the 2007 contract. On August 29, 2008, plaintiff submitted a certified claim to the CO, seeking damages for the losses sustained as a result of the delays. On May 21, 2009, the CO denied this claim.

Plaintiff filed its complaint in this court on November 20, 2009. Following discovery, on May 13, 2011, defendant filed a motion for summary judgment. On June 13, 2011, plaintiff filed a cross-motion for partial summary judgment. Briefing and argument of these cross-motions has been completed.

II. DISCUSSION

We begin with common ground. Summary judgment is appropriate when there is no genuine dispute as to any material fact and the moving party is entitled to judgment as a matter of law. See RCFC 56; Anderson v. Liberty Lobby, Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Urban v. United States
119 Fed. Cl. 57 (Federal Claims, 2014)
Dobyns v. United States
118 Fed. Cl. 289 (Federal Claims, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
105 Fed. Cl. 59, 2012 U.S. Claims LEXIS 464, 2012 WL 1574109, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pew-forest-products-v-united-states-uscfc-2012.