Kudsk Construction, Inc. v. United States

CourtUnited States Court of Federal Claims
DecidedAugust 30, 2019
Docket18-1032
StatusPublished

This text of Kudsk Construction, Inc. v. United States (Kudsk Construction, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kudsk Construction, Inc. v. United States, (uscfc 2019).

Opinion

In the United States Court of Federal Claims No. 18-1032C

(E-Filed: August 30, 2019)

) KUDSK CONSTRUCTION, INC., ) ) Contract; RCFC 12(b)(6); Plausible Plaintiff, ) Claim for Damages Due to Delayed ) Notice to Proceed; Reporting v. ) Requirements Not Necessarily ) Incorporated into Contract by THE UNITED STATES, ) Christian Doctrine. ) Defendant. ) )

William J. Braun, La Jolla, CA, for plaintiff.

Rebecca S. Kruser, Trial Attorney, with whom were Joseph H. Hunt, Assistant Attorney General, Robert E. Kirschman, Jr., Director, and Deborah A. Bynum, Assistant Director, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, for defendant. MAJ Christopher A. Lacour, United States Army Litigation Division, Fort Belvoir, VA, of counsel.

OPINION

CAMPBELL-SMITH, Judge.

This matter is before the court on defendant’s motion for partial dismissal, filed pursuant to Rule 12(b)(6) of the Rules of the United States Court of Federal Claims (RCFC), addressing a portion of Count I and all of Count IV of plaintiff’s complaint. See ECF No. 8. Plaintiff’s complaint, ECF No. 1, plaintiff’s response to defendant’s motion to dismiss, ECF No. 9, and defendant’s reply, ECF No. 16, were also considered by the court. Oral argument was not requested by the parties nor required by the court. For the reasons set forth below, defendant’s motion is DENIED. I. Background 1

Plaintiff Kudsk Construction, Inc. (Kudsk) was awarded a construction contract, Contract No. W9124N-09-C-0040, by the United States Army Reserve Contracting Center (Army) on or about September 11, 2009. ECF No. 1 at 1-2. The contract was for the renovation of six barracks at an Army Reserve Training Area. Id. at 2. Approximately ten days after award, the Army notified Kudsk to suspend any work on the contract, because a bid protest had been filed. Id. On December 1, 2009, Kudsk was notified that the protest had been denied and that the work could proceed. Id. Kudsk filed a claim on December 30, 2009, under Federal Acquisition Regulation (FAR) 52.233-3(b)(2), for “administrative and overhead” incurred while “waiting for [a] Notice to Proceed.” 2 Id.

After contract performance was complete, Kudsk filed a certified claim with the contracting officer. Id. at 3. Two elements of that claim, which was approved in part and denied in part, are at issue in the motion for partial dismissal now before the court. In Count I of the complaint, Kudsk seeks “increased costs and unabsorbed home office expenses” for the period of time Kudsk was on standby, from September 11, 2009, through December 11, 2009, when the Notice to Proceed issued. Id. at 4-5. This claim is in the amount of $66,738. Id. at 5.

In Count IV of the complaint, Kudsk asserts that on or about July 15, 2010, the Army directed Kudsk to comply with the reporting requirements of the American Recovery and Reinvestment Act of 2009 (ARRA), Pub. L. No. 111-5, Div. A, § 1512, 123 Stat. 115, 287-88, pursuant to a regulation that was not part of this construction contract. ECF No. 1 at 8. Kudsk began complying with these reporting requirements under protest. Id. at 9. According to Kudsk, the cost of compliance with ARRA reporting requirements over the period of contract performance was $6,739, and this amount, too, was included in plaintiff’s certified claim. Id.

Defendant’s motion to dismiss asserts that the claim for unabsorbed home office overhead contained in Count I, and the claim for ARRA reporting costs in Count IV, should be dismissed for failure to state a claim upon which relief can be granted. To the extent that Count I also contains a claim for “increased costs” that is distinct from

1 The facts recounted here are taken from the complaint. The court makes no findings of fact in this opinion. Although the government invites the court to consider exhibits attached to its motion to dismiss to support the dismissal of a portion of Count I of the complaint, the court does not require these exhibits for its analysis. See ECF No. 8 at 7 n.2. 2 All citations to the Federal Acquisition Regulation (FAR) in this opinion are to the 2018 version of Title 48 of the Code of Federal Regulations, unless otherwise noted.

2 plaintiff’s unabsorbed home office overhead claim, such a claim is not addressed in defendant’s motion for partial dismissal. ECF No. 8 at 10-11; ECF No. 16 at 1 n.1. For the reasons set forth below, neither of the claims identified by defendant’s motion can be dismissed pursuant to RCFC 12(b)(6).

II. Standard of Review

When considering a motion to dismiss brought under RCFC 12(b)(6), “[w]e must presume that the facts are as alleged in the complaint, and make all reasonable inferences in favor of the plaintiff.” Cary v. United States, 552 F.3d 1373, 1376 (Fed. Cir. 2009) (citing Gould Inc. v. United States, 935 F.2d 1271, 1274 (Fed. Cir. 1991)). It is well- settled that a complaint should be dismissed under RCFC 12(b)(6) “when the facts asserted by the claimant do not entitle him to a legal remedy.” Lindsay v. United States, 295 F.3d 1252, 1257 (Fed. Cir. 2002). “To survive a motion to dismiss, a complaint must contain sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible on its face.’” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007)).

III. Analysis 3

A. Count I – Unabsorbed Overhead Claim

1. Introduction

When the government delays a construction contract, so that no direct costs are incurred by the contractor for a period of time, fixed home office overhead costs, which normally are paid proportionally through payments for the direct costs of various construction projects, may be “unabsorbed.” Defendant’s motion provides this explanation of the concept:

A contractor recovers these indirect costs, such as home office overhead, by allocating a share of these costs to each contract throughout the year, with allocation proportional to the direct costs of each contract. When the Government suspends performance under the contract, the contractor ceases to incur direct costs. If the Government requires the contractor to be on standby during the suspension, so to begin work immediately or on short notice, then the contractor may be unable to take on replacement work and recover the proportional share of the home office overhead originally allocated to the suspended project. This unrecovered home office overhead

3 The court has considered all of the parties’ arguments. The court only discusses in this opinion the arguments that were dispositive.

3 is unabsorbed during the period of suspension and, under very specific circumstances, a contractor may be entitled to compensation.

ECF No. 8 at 11 (internal quotations and citations omitted). Plaintiff’s Count I clearly contains a claim for unabsorbed home office overhead. ECF No. 1 at 4-5; see also ECF No. 9 at 5 (“The reasonable implication of these allegations is that KUDSK was unable to bid on new work to cover its overhead costs during the suspension period, and that during that period of time the project was unable to cover its share of overhead expenses.”). This type of claim is often referred to as a claim for Eichleay damages, but here it is better to describe plaintiff’s claim as a claim for unabsorbed overhead. See ECF No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Limar Shipping Ltd. v. United States
324 F.3d 1 (First Circuit, 2003)
Cary v. United States
552 F.3d 1373 (Federal Circuit, 2009)
G. L. Christian and Associates v. The United States
312 F.2d 418 (Court of Claims, 1963)
G. L. Christian and Associates v. The United States
320 F.2d 345 (Court of Claims, 1963)
Capital Electric Company v. The United States
729 F.2d 743 (Federal Circuit, 1984)
Gould, Inc. v. The United States
935 F.2d 1271 (Federal Circuit, 1991)
Daniel A. Lindsay v. United States
295 F.3d 1252 (Federal Circuit, 2002)
Nicon, Inc. v. United States
331 F.3d 878 (Federal Circuit, 2003)
Jmr Construction Corp. v. United States
117 Fed. Cl. 436 (Federal Claims, 2014)
H. J. Lyness Construction, Inc. v. United States
121 Fed. Cl. 287 (Federal Claims, 2015)
K-Con, Inc. v. Secretary of the Army
908 F.3d 719 (Federal Circuit, 2018)
Ryco Construction, Inc. v. United States
55 Fed. Cl. 184 (Federal Claims, 2002)
Oak Environmental Consultants, Inc. v. United States
77 Fed. Cl. 688 (Federal Claims, 2007)
Redland Co. v. United States
97 Fed. Cl. 736 (Federal Claims, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Kudsk Construction, Inc. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kudsk-construction-inc-v-united-states-uscfc-2019.