Gould, Inc. v. The United States

935 F.2d 1271, 37 Cont. Cas. Fed. 76,108, 1991 U.S. App. LEXIS 11829, 1991 WL 95335
CourtCourt of Appeals for the Federal Circuit
DecidedJune 7, 1991
Docket90-5062
StatusPublished
Cited by513 cases

This text of 935 F.2d 1271 (Gould, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gould, Inc. v. The United States, 935 F.2d 1271, 37 Cont. Cas. Fed. 76,108, 1991 U.S. App. LEXIS 11829, 1991 WL 95335 (Fed. Cir. 1991).

Opinion

ARCHER, Circuit Judge.

Gould, Inc. (Gould) appeals the judgment of the United States Claims Court, Gould, Inc. v. United States, 19 Cl.Ct. 257 (1990), dismissing its complaint against the United States for failure to state a claim upon which relief can be granted. We vacate and remand.

I

After a period of soliciting proposals in October 1983, the Naval Electronics Systems Command (Navy) awarded Gould a five-year contract, No. N00039-84-C-0168, to build Bancroft-type tactical radios at a fixed price of $44,778,779.00. The Navy’s request for proposals (RFP) contained detailed performance specifications. Included with the RFP were design specifications and drawings for a prior Bancroft radio developed for the Army, headed “for informational purposes only.” Gould initially attempted to redesign the Army Bancroft radio to satisfy the Navy’s different performance requirements, but was unable to do so. Gould then performed additional design work, which it contends had not been contemplated or reflected in its bid, in an effort to meet the Navy’s specifications. During contract performance, the Navy provided Gould with data that showed the many differences between the Navy’s requirements and the Army’s Bancroft radio design. According to Gould, the data revealed that simply upgrading the Army’s radio would not meet the performance requirements of the Navy contract and that a complete redesign of the Army model would be necessary. Gould alleges that it had requested this information at a pre-award conference.

On December 11, 1986, Gould submitted a certified claim to the contracting officer seeking “equitable reformation and upward adjustment in the price of [the] contract.” The claim specifically requested that the Navy compensate Gould for:

costs to achieve a “stable design,” was [sic] well as its unanticipated, increased recurring costs resulting from achieving a much more complex “stable design” than envisioned. In short, Gould should be entitled to its total overrun.

It also stated that Gould is “entitled to equitable relief on other, independent grounds based on [the government’s] withholding of information and/or mutual mistake.” The claim concluded with a pricing section which requested money damages in the amount of $57,545,719 for “excess development costs plus increased recurring costs.” The requested relief sought in the claim was contract reformation for the amount claimed.

In support of the requested relief, the claim asserted, first, that the Navy violated 10 U.S.C. § 2306(h)(1) by failing to supply a stable design for the multi-year procurement, thus making the contract illegal from its inception; second, that prior to the award of the contract the Navy withheld documents that would have permitted bidders to estimate “the degree of design effort and risk involved in meeting the Navy’s performance specification;” and, third, that there was a mutual mistake by Gould and the Navy regarding a basic assumption of the contract because both believed “that only minimal design and development effort would be required.”

The contract contained the standard default clause, see DAR § 7.103.11 (1969), allowing the United States to terminate the contract if Gould failed to meet delivery schedules. Gould was unable to deliver a device for testing within the contract deadline. After negotiations, Gould and the Navy, on December 9, 1987, entered into a *1273 settlement by executing a bilateral modification to the contract (settlement agreement). Under this settlement agreement, the Navy terminated the contract for default but waived all rights to demand monetary damages from Gould. Gould, in turn, released the Navy from any and all claims under the contract, except for its December 11, 1986 claim, which was still pending when the settlement agreement was signed.

The relevant provisions of the settlement agreement are as follows:

WHEREAS, Gould has submitted a certified claim (the “claim”), under transmittal letter dated 11 December 1986, in the amount of $57,545,719.00, which claim has been the subject of negotiation between Gould and the Government; and
WHEREAS, the claim alleges that Gould is entitled to equitable reformation of the contract for amounts in excess of the contract price based upon the theories of contract invalidity, or Government withholding of necessary information, or mutual mistake;
NOW, THEREFORE, the parties hereto do mutually agree as follows:
VIII. Within ten days after the date of this agreement, the Government intends to issue an appealable final decision of the contracting officer in response to Gould’s claim dated 11 December 1986. The Government reserves all defenses, and Gould reserves all affirmative arguments, that would otherwise be available to each under the claim.
X. ... Gould, for itself, its successors and assignees, hereby releases and forever discharges the Government, its officers, agents, and employees, from any and all claims (except with respect to the grounds set forth in Gould’s 11 December 1986 claim).... This agreement is intended to be a complete and final adjustment of this Contract by reason of said events as of the effective date [of] this agreement except with respect to the grounds set forth in Gould’s 11 December 1986 claim.

(Emphasis added.)

On January 6, 1988, the contracting officer issued a decision denying Gould’s claim in its entirety. Gould then filed suit in the Claims Court under the Contract Disputes Act of 1978, Pub.L. No. 95-563, 92 Stat. 2383 (codified at 41 U.S.C. §§ 601-613 (1988)), seeking “compensation damages in the amount of $36,000,000.” 1

In its opinion, the Claims Court assumed, without discussion or explanation, that the terms of the settlement agreement made contract reformation the only remedy that Gould was entitled to pursue. Gould, 19 Cl.Ct. at 263-64. As a result, the court’s opinion is directed primarily to whether Gould was entitled to contract reformation under any of the three counts of the complaint which alleged (1) violation of 10 U.S.C. § 2306(h)(1) by the government, (2) withholding of information by the government, and (3) a mutual mistake. The court stated: “To dispose of defendant’s motion [to dismiss], this court shall first determine whether reformation is appropriate relief for the particular claims asserted by plaintiff.” Id. at 264. The Claims Court determined that each of the three counts in the complaint was legally insufficient to support contract reformation. The court also determined that Gould had not alleged, or would be unable to prove at trial, certain facts deemed essential to support the particular counts. The complaint was therefore dismissed under Rule 12(b)(4) of the Rules of the United States Claims Court (RUSCC) for failure to state a claim upon which relief can be granted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Liu
625 F. Supp. 3d 1378 (Court of International Trade, 2023)
CJW Contractors Inc.
Armed Services Board of Contract Appeals, 2023
Granite Construction Company
Armed Services Board of Contract Appeals, 2020
Richmond v. United States
Federal Claims, 2020
Hilex Poly Co. v. United States
450 F. Supp. 3d 1390 (Court of International Trade, 2020)
American Drew v. United States
450 F. Supp. 3d 1378 (Court of International Trade, 2020)
Adee Honey Farms v. United States
450 F. Supp. 3d 1365 (Court of International Trade, 2020)
Optimization Consulting, Inc.
Armed Services Board of Contract Appeals, 2019
L&M Technologies, Inc.
Armed Services Board of Contract Appeals, 2018
Payne v. United States
Federal Claims, 2018
Cubic Defense Applications, Inc.
Armed Services Board of Contract Appeals, 2018
Quaker Pet Grp., LLC v. United States
2018 CIT 9 (Court of International Trade, 2018)
Welty v. United States
Federal Claims, 2017
Zebel LLC v. United States
Federal Claims, 2017
weston/bean Joint Venture v. United States
123 Fed. Cl. 341 (Federal Claims, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
935 F.2d 1271, 37 Cont. Cas. Fed. 76,108, 1991 U.S. App. LEXIS 11829, 1991 WL 95335, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gould-inc-v-the-united-states-cafc-1991.