CJW Contractors Inc.

CourtArmed Services Board of Contract Appeals
DecidedJanuary 23, 2023
DocketASBCA No. 63228
StatusPublished

This text of CJW Contractors Inc. (CJW Contractors Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CJW Contractors Inc., (asbca 2023).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - ) ) CJW Contractors Inc. ) ASBCA No. 63228 ) Under Contract No. N40085-16-D-0300 )

APPEARANCES FOR THE APPELLANT: Douglas L. Patin, Esq. Erik M. Coon, Esq. Bradley Arant Boult Cummings LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq. Navy Chief Trial Attorney Robyn L. Hamady, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE SHACKLEFORD PURSUANT TO RULE 12.3

This appeal involves a dispute regarding the replacement of the heating system in Buildings 3, 4, and 5, at the Naval Support Activity in Mechanicsburg, Pennsylvania. CJW Contractors, Inc. (CJW) seeks to recover additional costs that it claims it incurred from furnishing and installing 52 20-foot long W6x15 steel I beams in Building 5. CJW argues that the Navy failed to (1) include a structural steel section or require Steel I beams in Building 5’s specifications despite explicitly referencing steel W and S beams, and (2) provide structural and mechanical design drawings free from latent ambiguities and contradicting design details. The Navy asserts that CJW improperly interpreted the contract by failing to read the drawings and specifications as a whole, and that any ambiguities in the contract documents were patent and thus imposed a duty upon CJW to inquire before the contract was awarded. We sustain the appeal.

FINDINGS OF FACT

1. On December 7, 2015, the Navy awarded Contract No. N40085-16-D-0300 (the contract) to CJW. The contract was a multiple award construction contract for new construction, renovation, alteration, and repair projects primarily located in Pennsylvania. (R4, tab 1 at GOV0001)

2. The contract included a one-year base period with four option years. The guaranteed minimum award amount was $5,000, with an estimated construction cost for all contracts not to exceed $95,000,000 for the life of the contract. (R4, tab 1 at GOV0038)

3. The contract incorporated by reference Federal Acquisition Regulation (FAR) 52.236-21, SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997), which provides:

Anything mentioned in the specifications and not shown on the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both. In case of difference between drawings and specifications, the specifications shall govern. In case of discrepancy in the figures, in the drawings, or in the specifications, the matter shall be promptly submitted to the Contracting Officer.

(R4, tab 1 at GOV0057)

4. The contract included FAR 52.216-18, ORDERING (OCT 1995), which provides:

All delivery orders or task orders are subject to the terms and conditions of this contract. In the event of conflict between a delivery order or task order and this contract, the contract shall control.

(R4, tab 1 at GOV0059)

5. The contract included Defense Federal Acquisition Regulation Supplement (DFARS) 252.236-7001, CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000), which provides:

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall—

(1) Check all drawings furnished immediately upon receipt;

2 (2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general—

(1) Large-scale drawings shall govern small-scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and the contract drawings identified for the project.

(R4, tab 1 at GOV0071-72)

6. The government exercised the contract’s option years through December 6, 2020, via Modification Nos. P00001 through P00004 (R4, tabs 2-5).

7. On or about July 31, 2019, the Naval Facilities Engineering Systems Command (NAVFAC), Mid-Atlantic issued a firm-fixed-price multiple award construction contract (MACC) task order request for proposal (RFP) No. N4008519R1791 entitled “BUILDING 3, 4 AND 5 REPLACE HEAT SYSTEM” at Naval Support Activity Mechanicsburg, Pennsylvania (R4, tab 6).

3 8. The RFP described the scope of the work as follows:

This project consists of the replacement of the existing heating system in buildings 3, 4 and 5. Project will remove the existing furnace and associated items including ductwork, registers and asbestos board and install new heating units, air intakes, vent units, and miscellaneous equipment to accomplish a functional heating system. The new work includes installation of associated wiring and controls. This [is] a DLA Distribution funded project for Building 3, 4 and 5 at NSA Mechanicsburg, PA. Complete the entire work ready for use not later than 380 calendar days after notice to proceed.

Drawings for Work Orders# 1588370, 1588369, 1588367 Attachment 4.

(R4, tab 6 at GOV0090) (emphasis in original)

9. The work in building 5 included, among other things, the installation of a hydronic heating system, which relies on water run through a pipe to heat the building (gov’t br. ex. 1 (Lefin decl.) ¶ 8).

10. The RFP provided:

All contract clauses contained in the respective MACC [indefinite delivery, indefinite quantity] contracts are hereby incorporated into this solicitation and the resultant task order. If there are any conflicts between the contract clauses and the information outlined in the resultant task order, the contract language takes precedence over the information in the task order.

(R4, tab 6 at GOV0090)

11. The RFP included two sets of complete design specifications and drawings, one for Buildings 3 and 4 and one for Building 5 (R4, tabs 6c-6d). Paragraph 10 of the RFP provided that “[t]his project is for Design Bid Build construction only. (There is no requirement for design effort) and includes a 100% design package.” (R4, tab 6 at GOV0091) (emphasis in original)

12. While the specifications for Buildings 3 and 4 included a section for Structural Steel at 05 12 00 (R4, tab 6d at GOV0172), the specifications for Building 5

4 did not (R4, tab 6d). The Structural Steel specifications for Buildings 3 and 4 provided a detailed list of the American Society for Testing and Materials (ASTM) requirements for every steel part, ranging from structural steel beams and pipes all the way down to steel bolts, nuts, and washers (R4, tab 6d at GOV0511-14). No such list was provided for Building 5 (R4, tab 6d).

13. Attachment #3 to the RFP included the Basis of Design for the project, which consisted of 64 pages of drawings related to Replacing Heating Systems in Buildings 3, 4 & 5 (R4, tab 6c; see also R4, tab 6 at GOV0093).

14. General Note 2 of Drawing S-001 provides: “STRUCTURAL DRAWINGS MAY NOT SHOW ALL EQUIPMENT PADS AND OTHER EQUIPMENT SUPPORTS REQUIRED. REFER TO CIVIL, ARCHITECTURAL, MECHANICAL AND ELECTRICAL DRAWINGS” (R4, tab 6c at GOV0134).

15.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
CJW Contractors Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/cjw-contractors-inc-asbca-2023.