Granite Construction Company

CourtArmed Services Board of Contract Appeals
DecidedDecember 3, 2020
DocketASBCA No. 62281
StatusPublished

This text of Granite Construction Company (Granite Construction Company) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Granite Construction Company, (asbca 2020).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Granite Construction Company ) ASBCA No. 62281 ) Under Contract No. W9126G-15-C-0037 )

APPEARANCES FOR THE APPELLANT: Michael A. Branca, Esq. Joshua Morehouse, Esq. Peckar & Abramson, P.C. Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Clark Bartee, Esq. Engineer Trial Attorney U.S. Army Engineer District, Galveston

OPINION BY ADMINISTRATIVE JUDGE CLARKE ON CROSS-MOTIONS FOR SUMMARY JUDGMENT

Although we have before us cross-motions for summary judgment, because there are disputed material facts, we ultimately grant only partial summary judgment. This case involves the proper interpretation of the Federal Acquisition Regulation (FAR) 52.249-10, DEFAULT (APR 1984), and FAR 52.242-14, SUSPENSION OF WORK (APR 1984) and whether the monthly anticipated adverse weather delay in Specification SECTION 01 10 00.00 45, 1.4 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER may be subtracted from a suspension period. We have jurisdiction pursuant to the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 7101-7109. We find that the adverse weather delay may not be subtracted from a suspension period and grant partial summary judgment to Granite.

STATEMENT OF FACTS (SOF) FOR THE PURPOSES OF THE MOTION

For purposes of resolving the pending cross-motions for summary judgment, the parties entered into a joint stipulation of twenty-five numbered paragraphs which is incorporated below.

1. On August 31, 2015, Granite Construction Company (Granite) was awarded Contract No. W9126G-15-C-0037 by the United States Army Corps of Engineers (COE) to perform the construction of new outlet structures and cutoff walls at the Addicks and Barker dams as a portion of the Buffalo Bayou and Tributaries federal flood control project in Houston, Texas (R4, tab 1).

2. On September 29, 2015, the COE issued and Granite acknowledged a Notice to Proceed to Granite that established a required completion date of the contract of May 31, 2019.

3. At all times relevant to this action, the COE exercised exclusive control over the operation of Addicks and Barker dams.

4. Under Section 01 00 10, part 1.4 of the contract, under normal conditions the combined release of water from the Addicks and Barker dams was to be limited to 2,000 cubic feet per second (CFS) as measured downstream at the Piney Point gauging station (R4, tab 1 at 2628-29).

5. Section 00 31 33, paragraph 2.3 of the contract similarly provides that the combined releases cannot exceed 2,000 CFS under normal operating conditions and that the maximum discharge from one reservoir of 2,000 CFS requires the other to be closed.

6. On August 25, 2017, Hurricane Harvey made landfall on the coast of Texas. In the following days, Hurricane Harvey brought rain as well as flooding to the Houston, Texas, Metropolitan Area, which includes the contract project site at the Addicks and Barker Dams.

7. After the landfall of Hurricane Harvey, on or before August 28, 2017, the COE began releasing water from the Addicks and Barker dams, with the combined flow rate increasing to over 4,000 CFS.

8. The COE continued to increase the combined flows of water from the Addicks and Barker dams through August 29, 2017.

9. By August 29, 2017, the combined discharges from Addicks and Barker dams into the Buffalo Bayou, in conjunction with flows entering Buffalo Bayou downstream of the dams, caused the measured flow at the Piney Point gauging station to be in excess of 10,000 CFS.

10. By letter dated September 5, 2017, the COE issued Serial Letter No. C-0039 to Granite, which directed Granite to “SUSPEND WORK” on Construction of the New Outlet Structure at the Addicks Dam site; Construction of Cutoff Walls and New Outlet Structure at the Barker Dam site; and Construction of Cutoff Walls at the Noble Road site of Barker Dam, both retroactively to August 28, 2017 and prospectively through October 15, 2017, pursuant to FAR 52.242-14, SUSPENSION OF WORK (APR 1984) (R4, tab 3).

2 11. The suspension of work outlined in Serial Letter No. C-0039 did not apply to contract requirements to assist in emergency repairs of damage to the dams; repairs to any part of the temporary or permanent work performed by Granite that is damaged by the flood from Hurricane Harvey; construction activities related to site recovery and restoration which could be performed safely, as conditions improved; and activities that were not affected by the flooding in and around the dams.

12. The total period of suspension ordered by the contracting officer (CO) was 49 calendar days, from August 28, 2017 through October 15, 2017.

13. After the suspension expired, Granite and the COE executed Modification No. A00030, which extended the Contract time by 49 calendar days. In part, Modification No. A00030 states that it was issued “for delays from the suspension of work due to Hurricane Harvey during the period August 28, 2017 thru October 15, 2017” (R4, tab 4).

14. Modification No. A00030 states that it is “not a release of claims by the Contractor and does not preclude the Contractor from pursuing any claim for monetary compensation from events occurring during the timeframe of the days covered in this modification” (R4, tab 4 at 003547).

15. On June 14, 2018, Granite submitted a Request for Equitable Adjustment seeking $1,250,474 and five (5) calendar days as compensation for the additional costs that it had incurred as a result of the suspension of work to the extent directed by the COE’s September 5, 2017, letter.

16. On November 30, 2018, the COE and Granite executed bilateral Modification No. P00008 for $961,008 and four (4) calendar days as compensation to Granite for additional work performed and for its time-related costs associated with 30 of the 49 days for which the work was suspended. The modification referenced Hurricane Harvey and stated in part that it included “cost associated with the direction to partially suspend work on September 5, 2017 due to unprecedented rain and flooding caused by Hurricane Harvey as well as site reclamation activities required to repair the site to pre-flood conditions.” (R4, tab 5)

17. Modification No. P00008 included an express reservation of rights for Granite to pursue compensation for the remaining 19 days of time-related costs in the amount of $233,779.

18. Modification No. P00008 excluded compensation for Granite’s time-related costs associated with the remaining 19 days requested by Granite in part due to contract Section 01 10 00.00 45, part 1.4 which provides a chart of monthly anticipated adverse weather delay days.

3 19. Contract Section 01 10 00.00 45, paragraph 1.4 is titled “TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (31 OCT 1989) (ER 415-1-15).”

20. Paragraph 1.4.2, “Baseline for Monthly Weather Time Evaluations” requires the contractor’s progress schedule to reflect these anticipated adverse weather delays in all weather dependent activities.

21. The exclusion of compensation for 19 days was based in part upon the anticipated adverse weather days identified in paragraph 1.4.2 of Section 01 10 00.00 45.

22. By letter dated May 23, 2019, Granite submitted a certified claim under the contract and requested a final decision of the CO. Granite’s claim sought $233,779, plus interest, which represented the time-related costs that Granite alleged it had incurred as a result of an express suspension of the work by the COE. (R4, tab 6)

23. By letter dated August 30, 2019, the CO issued a final decision denying Granite’s claim (R4, tab 8).

24.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
States Roofing Corporation v. Winter
587 F.3d 1364 (Federal Circuit, 2009)
LAI Services, Inc. v. Gates
573 F.3d 1306 (Federal Circuit, 2009)
Teg-Paradigm Environmental, Inc. v. United States
465 F.3d 1329 (Federal Circuit, 2006)
Hol-Gar Manufacturing Corp. v. The United States
351 F.2d 972 (Court of Claims, 1965)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Gould, Inc. v. The United States
935 F.2d 1271 (Federal Circuit, 1991)
Foley Company v. United States
11 F.3d 1032 (Federal Circuit, 1993)
McAbee Construction, Inc. v. United States
97 F.3d 1431 (Federal Circuit, 1996)
P.R. Burke Corp. v. United States
277 F.3d 1346 (Federal Circuit, 2002)
Nvt Technologies, Inc. v. United States
370 F.3d 1153 (Federal Circuit, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
Granite Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/granite-construction-company-asbca-2020.