Idaho Stage LLC v. United States

131 Fed. Cl. 727, 2017 U.S. Claims LEXIS 437, 2017 WL 1709700
United States Court of Federal Claims·Decided May 2, 2017·No. 16-548C·Published

Opinion

Motion in Limine, Contract Interpretation; Request for Equitable Adjustment.

ORDER

HORN, J.

FINDINGS OF FACT

Before the court is defendant’s motion in limine seeking to bar plaintiff from presenting certain evidence or argument at trial. Plaintiff, Idaho Stage, LLC, (Idaho Stage) filed a complaint in the United States Court of Federal Claims alleging j&at defendant, the United States, acting through the Department of the Navy, Naval Facilities Engineering Command Northwest, changed the terms of the contract such jdiat plaintiff is entitled to an equitable adjustment. According to the complaint, the parties entered into a task order contract, number N44255-14-D-9016, on February 26, 2015, fpr construction, renovation, alteration, demolition, and repair *729 work of facilities located on Naval Base Kit-sap in the State of Washington. The task order was awarded for a firm fixed price of $4,087,500.00.

Pertinent to the current motion in limine dispute between the parties, the contract called for a project superintendént and a Site Safety and Health Officer (SSHO). Contract section 1.6.2.1 describes the duties of the SSHO as follows:

The SSHO shall:

a. Conduct daily safety and health inspections and maintain a written log which includes area/operation inspected, date of inspection, identified hazards, recommended corrective actions, estimated and actual dates of corrections. Attach safety inspection logs to the Contractors’ daily production report.
b. Conduct mishap investigations and complete required reports. Maintain the OSHA Form 300 and Daily Production reports for prime and sub-contractors.
c. Maintain applicable safety reference material on the job site.
d. Attend the pre-construction conference, pre-work meetings including preparatory inspection meeting, and periodic in-progress meetings.
e. Implement and enforce accepted APPs [Accident Prevention Plans] and AHAs [Activity Hazard Analysis],
f. Maintain a safety and health deficiency tracking system that monitors outstanding deficiencies until resolution. Post a list of unresolved safety and health deficiencies on the safety bulletin board.
g. Ensure sub-contractor compliance with safety and health requirements.
h.Maintain a list of hazardous chemicals on site and their material safety data sheets.
Failure to perform the above duties will result in dismissal of the superintendent, QC [Quality Control] Manager, and/or SSHO, and a project work stoppage.

Additional language concerning the SSHO is set forth in contract Section 01 35 26, which explains the “GOVERNMENTAL SAFETY REQUIREMENTS” that apply to contract performance, (capitalization in original). Contract Section 01 35 26 identifies publications that were intended to “form a part of this specification to the extent referenced.” Section 1.5 of the contract specifications provides that, “[i]n addition to the detailed requirements included in the provisions of this contract,” the contractor should “comply with the most recent edition of USACE [United States Army Corps of Engineers] EM 385 — 1— 1,” a manual describing safety and health requirements. 1

With regard to the SSHO, the contract states at Section 01 35 26:

The SSHO must meet the requirements of EM 385-1-1 section 1 and ensure that the requirements of 29 CFR 1926.16 are met for the project. Provide a Safety oversight team that includes a minimum of one (1) person at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO or an equally-qualified Designated Representative/altemate shall be at the work site at all times to implement and administer the Contractor’s safety program and government-accepted Accident Prevention Plan. The SSHO’s training, experience, and qualifications shall be as required by EM 385-1-1 paragraph 01.A.17, entitled SITE SAFETY AND HEALTH OFFICER (SSHO), and all associated sub-paragraphs. (capitalization in original).

*730 The EM 385-1-1 Manual sets forth SSHO requirements at section 01.A.17. According to section 01.A.17 of the EM 385-1-1 Manual, the contractor is required to “employ a minimum of one CP [Competent Person] at each project site to function as the SSHO (primary), depending on job complexity, size and any other pertinent factors.” Additionally, section 01.A17 states:

a. The SSHO shall:
(1) Be a full-time responsibility. The SSHO shall be present at the project site, located so they have full mobility and reasonable access to all major work operations during the shift.
(2) Be an employee other than the supervisor, unless specified differently in the contract and coordinated with the local SOH Office, and
(3) Report to a senior project (or corporate) official.

(emphasis in original). Separate from section 01.A.17 of the EM 385-1-1 Manual, Appendix Q of the EM 385-1-1 Manual sets forth “Definitions,” in which the SSHO is defined as “the superintendent or other qualified or competent person who is responsible for on-site safety and health.” Unlike for the SSHO position, neither the contract, nor the EM 385-1-1 Manual, indicates whether the project superintendent position should be considered a full-time responsibility. Moreover, the Appendix Q “Definitions” section of the EM 385-1-1 Manual defines the SSHO as “the superintendent or other qualified or competent person who is responsible for on-site safety and health,” suggesting the possibility of dual roles.

Free access — add to your briefcase to read the full text and ask questions with AI

Idaho Stage LLC v. United States, 131 Fed. Cl. 727, 2017 U.S. Claims LEXIS 437, 2017 WL 1709700 (uscfc 2017).

131 Fed. Cl. 727 (Idaho Stage LLC v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Precision Pine & Timber, Inc. v. United States
596 F.3d 817 (Federal Circuit, 2010)
McHugh v. DLT Solutions, Inc.
618 F.3d 1375 (Federal Circuit, 2010)
Holland v. United States
621 F.3d 1366 (Federal Circuit, 2010)
LAI Services, Inc. v. Gates
573 F.3d 1306 (Federal Circuit, 2009)
Arko Executive Services, Inc. v. United States
553 F.3d 1375 (Federal Circuit, 2009)
Medlin Construction Group, Ltd. v. Harvey
449 F.3d 1195 (Federal Circuit, 2006)
Flexfab, L.L.C. v. United States
424 F.3d 1254 (Federal Circuit, 2005)
First Annapolis Bancorp, Inc. v. United States
644 F.3d 1367 (Federal Circuit, 2011)
Hol-Gar Manufacturing Corp. v. The United States
351 F.2d 972 (Court of Claims, 1965)
Alvin, Ltd. v. United States Postal Service
816 F.2d 1562 (Federal Circuit, 1987)
Beta Systems, Inc. v. The United States
838 F.2d 1179 (Federal Circuit, 1988)
Craft MacHine Works, Inc. v. The United States
926 F.2d 1110 (Federal Circuit, 1991)
Gould, Inc. v. The United States
935 F.2d 1271 (Federal Circuit, 1991)
Foley Company v. United States
11 F.3d 1032 (Federal Circuit, 1993)
McAbee Construction, Inc. v. United States
97 F.3d 1431 (Federal Circuit, 1996)
Wayne B. Harris v. Department of Veterans Affairs
142 F.3d 1463 (Federal Circuit, 1998)
H.B. Mac, Inc. v. United States
153 F.3d 1338 (Federal Circuit, 1998)