Arko Executive Services, Inc. v. United States

553 F.3d 1375, 2009 U.S. App. LEXIS 912, 2009 WL 129718
CourtCourt of Appeals for the Federal Circuit
DecidedJanuary 21, 2009
Docket2008-5011
StatusPublished
Cited by63 cases

This text of 553 F.3d 1375 (Arko Executive Services, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arko Executive Services, Inc. v. United States, 553 F.3d 1375, 2009 U.S. App. LEXIS 912, 2009 WL 129718 (Fed. Cir. 2009).

Opinion

WALKER, Chief District Judge.

Plaintiff-appellant Arko Executive Services, Inc (“Arko”) appeals from a final order of the Court of Federal Claims granting summary judgment in favor of defendant-appellee United States (“the government”) in this services contract dispute brought pursuant to the Contract Disputes Act of 1978, 41 USC §§ 601-613. See Arko Executive Servs., Inc. v. United States, 78 Fed Cl 420 (2007). Because the trial court correctly interpreted the contract at issue, we affirm.

BACKGROUND

Arko, an American security company, contracted with the government to provide guard services to the American Embassy Nicosia, Cypress. Services were provided pursuant to Contract No S-CY-600-00-0006 (“the contract”), which provided a base year of service beginning April 2000 and four optional one-year renew-

*1377 The government exercised the four one-year options to renew, and the last of these options was set to expire on March 31, 2005. In November 2004, the government solicited offers for the successor contract, with an anticipated start date of April 1, 2005. Two timely offers were submitted, neither by Arko.

On February 8 and again on February 15, 2005, Arko inquired whether the government would require phase-in, phase-out services after March 31, 2005. On February 16, the government responded that it did “not anticipate the need for any phase-in/phase-out services.” Then, on March 4, 2005, the government notified Arko that it would require services through April 30, 2005, citing FAR 52.217-8, the “Option to Extend Services” for its unilateral extension of the performance period.

Arko immediately disputed the government’s authority to extend Arko’s provision of services under FAR 52.217-8, stating that Arko would perform the services under protest. Arko’s position apparently was that the only contractual provision allowing continued services after the exercise of the four one-year options to renew was FAR 52.237-3, the “Continuity of Services” clause, which, unlike FAR 52.217-8, provided for cost-plus reimbursement of expenses incurred by Arko during the extension. By letter dated March 18, 2005, the government notified Arko that its final decision was to invoke FAR 52.217-8 and that it now would require service through May 31, 2005. According to the letter, the government required the additional month of services to ensure time for a replacement contractor to be fully operational and to avoid the need for later extensions. The government issued amended contract modification 21 on March 22, 2005, formalizing its invocation of an extension of services pursuant to FAR 52.217-8. Modification 21 specified that Arko would be paid for services performed from April 1 to May 31, 2005 at the same rate it had been paid for services during the immediately preceding renewal period.

Arko continued performing guard services at the embassy in Nicosia until May 31, 2005. A successor contractor was selected on April 26, 2005 and began performance June 1, 2005.

On November 5, 2005, Arko filed a suit, case no 05-1193C, in the United States Court of Federal Claims (“the trial court”) challenging the government’s final decision to exercise the government’s option to extend services pursuant to FAR 52.217-8 rather than FAR 52.237-3. Arko then submitted a claim to the government seeking compensation of $184,010.10 pursuant to FAR 52.237-3; the government denied that claim on March 21, 2006. On April 14, 2006, Arko filed a new suit in the trial court, case no 06-0296C, challenging the denial of compensation. The trial court consolidated the two cases on May 12, 2006.

Arko filed a motion for summary judgment on the issue whether it was entitled to payment pursuant to FAR 52.237-3. The government moved for summary judgment on liability, arguing that FAR 52.237-3 did not apply to the services performed by Arko from April 1 to May 31, 2005 and that government had the authority to require those services under FAR 52.217-8. The trial court granted summary judgment in favor of the government, finding no genuine issue of material fact whether the government validly exercised the FAR 52.217-8 clause and finding no basis for Arko’s contention that the services provided from April 1 to May 31, 2005 were the phase-in, phase-out services contemplated by FAR 52.237-3. See Arko, 78 Fed Cl at 423-25.

The trial court entered final judgment on September 26, 2007, and Arko timely appealed to this court, which has jurisdic *1378 tion pursuant to 28 USC § 1295(a)(3). We heard oral argument on September 4, 2008.

DISCUSSION

We review the trial court’s decisions on summary judgment de novo. St. Christopher Assoes., LP v. United States, 511 F.3d 1376, 1380 (Fed.Cir.2008). Summary judgment is appropriate where there is no genuine dispute as to any material fact and the moving party is entitled to judgment as a matter of law. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). Here, there are no disputes of material fact, and the case turns on issues of contract interpretation.

This case centers on several labyrinthine provisions of the contract between Arko and the government. Section F.4 of the contract defines the period of performance:

F.4. Period of Performance.

F.4.1. The performance period of this contract is from the date of Notice to Proceed and continuing for 12 months, with four, one-year options to renew. The initial period of performance includes any transition period authorized under the contract.
F.4.2. The Government may extend this contract in accordance with the option clause at Subsection 1.1.2, FAR Clauses Incorporated by Full Text (FAR 52.217-9), Option to Extend the Term of the Contract (Deviation), which also specifies the total duration of this contract.
F.4.3 The Government may exercise the option set forth at Subsection 1.1.1, “FAR 52.217-8, Option to Extend Services”, within the currently ongoing period of performance or within 30 days after funds for the option become available, whichever is later.

FAR 52.217-9, a clause of the Federal Acquisition Regulations (“FAR”) incorporated into the contract in full text, provides:

52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 1989) (DEVIATION)
(a) The Government may extend the term of this contract by written notice to the Contractor within the performance period of the contract or within 30 days after funds for the option year become available, whichever is later.
(b) If the Government exercises this option, the extended contract shall be considered to include this option provision.
(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed five years.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

King v. United States
Federal Circuit, 2025
Castillo v. United States
Federal Claims, 2023
Flint v. United States
Federal Claims, 2022
Fluor Federal Solutions, Inc.
Armed Services Board of Contract Appeals, 2022
Albright v. United States
Federal Circuit, 2020
GSC Construction, Inc.
Armed Services Board of Contract Appeals, 2020
DCX-CHOL Enterprises, Inc.
Armed Services Board of Contract Appeals, 2020
Cheung v. United States
Federal Claims, 2019
Curtis Jue
Armed Services Board of Contract Appeals, 2019
Menendez v. United States
Federal Claims, 2018
Lucier v. United States
Federal Claims, 2018
Wade v. United States
Federal Claims, 2018
Yee v. United States
Federal Claims, 2017

Cite This Page — Counsel Stack

Bluebook (online)
553 F.3d 1375, 2009 U.S. App. LEXIS 912, 2009 WL 129718, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arko-executive-services-inc-v-united-states-cafc-2009.